Monthly Local Let Maintenance Report For Paris District As Of May 15, 2013 Page 2 Of 6

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRED RIVER
Highway US0082
From FOR THE RED RIVER COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6226-50-001
Proj ID SUP - 622650001
Work Type GROUNDS MAINTENANCE
 
0.010 11960.00 638.00 5588.00 46.7
Work Order 08-17-11
Work Began 08-17-11
Work Completed  
Time Computed 08-17-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 623
Percent Time Used 85
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6226-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08110132
Totals 11960.00 638.00 5588.00 46.7

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS COUNTY
CSJ 6226-52-001
Proj ID SUP - 622652001
Work Type LITTER PICKUP
 
0.010 59862.31 0.00 56543.13 94.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-11
Work Began 09-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 366
Percent Time Used 100
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6226-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08110134
Totals 59862.31 0.00 56543.13 94.4

CountyDELTA
Highway SH0019
From VARIOUS AREAS IN
To DELTA COUNTY
CSJ 6226-54-001
Proj ID SUP - 622654001
Work Type PICNIC AREA MAINTENANCE
 
1.010 29550.00 1005.00 15800.00 53.4
Work Order 11-01-11
Work Began 11-01-11
Work Completed  
Time Computed 11-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 547
Percent Time Used 74
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6226-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10110131
Totals 29550.00 1005.00 15800.00 53.4

CountyDELTA
Highway SH0019
From FOR THE DELTA COUNTY
To MAINTENANCE OFFICE COMPLEX
CSJ 6226-55-001
Proj ID SUP - 622655001
Work Type GROUNDS MAINTENANCE
 
0.001 10850.00 340.00 4130.00 38.0
Work Order 04-01-12
Work Began 04-01-12
Work Completed  
Time Computed 04-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 395
Percent Time Used 54
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6226-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03120131
Totals 10850.00 340.00 4130.00 38.0

CountyHUNT
Highway IH0030
From FOR THE HUNT COUNTY AREA OFFICE AND
To MAINTENANCE OFFICE COMPLEX
CSJ 6226-56-001
Proj ID SUP - 622656001
Work Type GROUNDS MAINTENANCE
 
0.001 27840.00 435.00 21311.00 78.1
Work Order 05-09-11
Work Began 05-09-11
Work Completed  
Time Computed 05-09-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 723
Percent Time Used 99
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6226-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05110135
Totals 27840.00 435.00 21311.00 78.1

CountyHOPKINS
Highway SH0011
From FOR THE HOPKINS CO AREA OFFICE AND
To MAINTENANCE OFFICE COMPLEX
CSJ 6226-57-001
Proj ID SUP - 622657001
Work Type GROUNDS MAINTENANCE
 
0.001 24268.00 724.00 18862.00 77.7
Work Order 05-06-11
Work Began 05-06-11
Work Completed  
Time Computed 05-06-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 726
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6226-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05110134
Totals 24268.00 724.00 18862.00 77.7

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS IN RED RIVER
To COUNTY
CSJ 6226-58-001
Proj ID SUP - 622658001
Work Type PICNIC AREA MAINTENANCE
 
0.010 20895.00 1605.00 7520.00 35.9
Work Order 11-07-12
Work Began 11-17-12
Work Completed  
Time Computed 11-17-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 45
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6226-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11120131
Totals 20895.00 1605.00 7520.00 35.9

CountyHOPKINS
Highway IH0030
From VARIOUS ROADWAYS IN HOPKINS
To COUNTY
CSJ 6226-60-001
Proj ID SUP - 622660001
Work Type PICNIC AREA MAINTENANCE
 
0.010 28676.00 2187.50 6922.50 24.1
Work Order 01-15-13
Work Began 01-15-13
Work Completed  
Time Computed 01-15-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 29
Contractor(s)
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6226-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01130108
Totals 28676.00 2187.50 6922.50 24.1

CountyHUNT
Highway IH0030
From VARIOUS ROADWAYS IN HUNT AND
To RAINS COUNTIES
CSJ 6230-38-001
Proj ID RMC - 623038001
Work Type ON CALL METAL BEAM GUARD FENCE
 
0.010 64821.00 12008.00 93671.00 99.9
Work Order 03-07-12
Work Began 04-12-12
Work Completed  
Time Computed 04-19-12
Contract Working Days 260
Addl Days Granted 260
Working Days Charged 263
Percent Time Used 50
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02120107
Totals 64821.00 12008.00 93671.00 99.9

CountyGRAYSON
Highway FM0120
From ADD LEFT TURN LANE/UPGRADE
To SIGNAL SH 289 @ FM 120
CSJ 6230-66-001
Proj ID RMC - 623066001
Work Type ADD LEFT TURN LANE / UPGRADE SIGNAL
 
0.010 197948.52 3446.00 172622.90 98.8
Work Order 07-05-12
Work Began 07-05-12
Work Completed  
Time Computed 07-12-12
Contract Working Days 45
Addl Days Granted 15
Working Days Charged 99
Percent Time Used 165
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03120101
Totals 197948.52 3446.00 172622.90 98.8

CountyRED RIVER
Highway BU0082J
From TXDOT MAINTENANCE FACILITY
To IN CLARKSVILLE, TX
CSJ 6231-02-001
Proj ID RMC - 623102001
Work Type JANITORIAL SERVICES
 
0.001 4020.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS CUTTERS
SUBCONTRACTOR(S) FOR CCSJ: 6231-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10110107
Totals 4020.00 0.00 0.00 0.0

CountyLAMAR
Highway US0271
From VARIOUS AREAS IN LAMAR
To COUNTY
CSJ 6231-50-001
Proj ID RMC - 623150001
Work Type PICNIC AREA MAINTENANCE
 
0.010 99976.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 614
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
METT INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6231-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11110105
Totals 99976.00 0.00 0.00 0.0

CountyLAMAR
Highway BU0271B
From PARIS DISTRICT HEADQUARTERS
To AT 1365 N MAIN STREET
CSJ 6232-31-001
Proj ID RMC - 623231001
Work Type GROUNDS MAINTENANCE
 
0.010 22845.00 1466.00 17696.50 77.4
Work Order 11-18-11
Work Began 12-01-11
Work Completed  
Time Computed 12-08-11
Contract Working Days 365
Addl Days Granted 182
Working Days Charged 510
Percent Time Used 93
Contractor(s)
TEXAS CUTTERS
SUBCONTRACTOR(S) FOR CCSJ: 6232-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10110112
Totals 22845.00 1466.00 17696.50 77.4

CountyHUNT
Highway IH0030
From VARIOUS RAMPS ON
To IH 30 IN HUNT CO
CSJ 6234-58-001
Proj ID RMC - 623458001
Work Type MILL & INLAY
 
1.000 381791.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R. K. HALL CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6234-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02120109
Totals 381791.94 0.00 0.00 0.0

CountyDELTA
Highway SH0154
From VARIOUS ROADWAYS DISTRICT
To WIDE
CSJ 6234-60-001
Proj ID RMC - 623460001
Work Type REMOVE NON - STANDARD HEADWALLS
 
0.010 85294.00 0.00 88976.44 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-12
Work Began 06-12-12
Work Completed  
Time Computed 06-19-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 95
Contractor(s)
J. M. CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6234-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03120103
Totals 85294.00 0.00 88976.44 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS ROADWAYS IN
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6234-62-001
Proj ID RMC - 623462001
Work Type ON - CALL MBGF REPAIR
 
0.001 39802.00 17024.00 83012.13 99.9
Work Order 06-15-12
Work Began 06-15-12
Work Completed  
Time Computed 06-22-12
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 85
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05120107
Totals 39802.00 17024.00 83012.13 99.9

CountyGRAYSON
Highway US0082
From VARIOUS ROADWAYS IN
To GRAYSON AND FANNIN COUNTIES
CSJ 6234-63-001
Proj ID RMC - 623463001
Work Type ON - CALL RPM'S
 
0.001 35099.50 0.00 10338.52 29.4
Work Order 11-08-12
Work Began 12-03-12
Work Completed  
Time Computed 12-10-12
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 38
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07120102
Totals 35099.50 0.00 10338.52 29.4

CountyLAMAR
Highway LP0286
From GROUNDS MAINTENANCE AT THE
To PARIS AREA OFFICE
CSJ 6234-89-001
Proj ID RMC - 623489001
Work Type GROUNDS MAINTENANCE
 
0.010 5700.00 450.00 4300.00 75.4
Work Order 07-12-12
Work Began 07-20-12
Work Completed  
Time Computed 07-27-12
Contract Working Days 255
Addl Days Granted 255
Working Days Charged 185
Percent Time Used 36
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06120105
Totals 5700.00 450.00 4300.00 75.4

CountyFRANKLIN
Highway IH0030
From VARIOUS ROADWAYS IN HOPKINS
To AND FRANKLIN COUNTIES
CSJ 6235-80-001
Proj ID RMC - 623580001
Work Type ON CALL TREE REMOVAL
 
0.001 72515.00 28229.00 113787.00 99.9
Work Order 04-18-12
Work Began 04-18-12
Work Completed  
Time Computed 04-25-12
Contract Working Days 255
Addl Days Granted 255
Working Days Charged 258
Percent Time Used 50
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6235-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02120104
Totals 72515.00 28229.00 113787.00 99.9

CountyHOPKINS
Highway IH0030
From HOPKINS COUNTY
To AREA/MAINTENANCE OFFICE COUNTIES
CSJ 6235-87-001
Proj ID SUP - 623587001
Work Type JANITORIAL SERVICES
 
0.010 29564.32 1016.42 17211.81 58.2
Work Order 03-01-12
Work Began 03-01-12
Work Completed  
Time Computed 03-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 116
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6235-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01120132
Totals 29564.32 1016.42 17211.81 58.2