AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - HOUSTON DISTRICT

Last Update: Wednesday, July 2, 2014
ITEMS 500 2001 TO 540 2036
Items Items Bid Code Range
0100 - 0193
0247 - 0292
0305 - 0368
0400 - 0497
0500 - 0560
0610 - 0690
0730 - 0760
1009 - 1133
2034 - 2239
3061 - 3275
4001 - 4654
5050 - 5969
6004 - 6986
7384 - 7622
8020 - 8997
9009 - 9009
500 2001 - 540 2036
540 2037 - 560 2034
Item No Description Units June 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS 10.000 82,403.80000 85.000 791,637.90929 85
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 61.000 1,142.65574 877.000 4,973.96786 85
506 2034 TEMPORARY SEDIMENT CONTROL FENCE LF     560.000 1.00000 1
508 2002 CONSTRUCTING DETOURS SY     70,386.000 43.36192 5
508 2005 CONSTRUCTING DETOURS (EBSS) SY 2,727.000 6.00000 22,742.000 6.46683 4
512 2004 PORT CTB (FUR & INST) (SNGL SLP) (TY 1) LF     2,725.000 50.00000 1
512 2005 PORT CTB (FUR & INST) (SNGL SLP) (TY 2) LF     6,690.000 54.84000 1
512 2008 PORT CTB (FUR & INST) (LOW PROF) (TY 1) LF     26,632.000 22.82217 5
512 2009 PORT CTB (FUR & INST) (LOW PROF) (TY 2) LF     1,058.000 41.03025 5
512 2010 PORT CTB (DES SOURCE) (SAFETY SH) (TY 1) LF     24,570.000 12.60000 1
512 2017 PORT CTB (DES SOURCE) (LOW PROF) (TY 1) LF 1,080.000 10.00000 43,360.000 6.98323 15
512 2018 PORT CTB (DES SOURCE) (LOW PROF) (TY 2) LF 200.000 10.00000 2,480.000 11.43169 14
512 2019 PORT CTB (MOVE) (SAFETY SH) (TY 1) LF     99,362.000 3.00000 1
512 2026 PORT CTB (MOVE) (LOW PROF) (TY 1) LF 920.000 3.00000 91,042.000 4.24100 17
512 2027 PORT CTB (MOVE) (LOW PROF) (TY 2) LF 160.000 3.00000 5,158.000 8.20008 17
512 2035 PORT CTB (STKPL) (LOW PROF) (TY 1) LF 1,080.000 10.00000 64,890.000 5.75784 17
512 2036 PORT CTB (STKPL) (LOW PROF) (TY 2) LF 200.000 10.00000 3,040.000 8.71888 16
512 2041 PORT CTB (REMOVE) (SNGL SLP) (TY 2) LF     6,690.000 5.09000 1
512 2044 PORT CTB (REMOVE) (LOW PROF) (TY 1) LF     4,722.000 3.97289 3
512 2045 PORT CTB (REMOVE) (LOW PROF) (TY 2) LF     1,238.000 3.08562 3
512 2058 PORT CTB (FUR & INST) (SNGL SLP) (TY J - J LF 760.000 68.00000 760.000 68.00000 1
512 2059 PORT CTB (DES SOURCE) (SNGL SLP) (TY J - J LF     221,040.000 4.31567 11
512 2060 PORT CTB (MOVE) (SNGL SLP) (TY J - J) LF 2,150.000 6.00000 332,490.000 4.05644 11
512 2061 PORT CTB (STKPL) (SNGL SLP) (TY J - J) LF     214,490.000 4.27282 11
512 2062 PORT CTB (REMOVE) (SNGL SLP) (TY J - J) LF 760.000 25.00000 760.000 25.00000 1
512 2069 PORT CTB (FUR & INST) (SAFETY SH) (TY P) LF     1,170.000 85.00000 1
512 2096 PORT CTB (REMOVE) (SAFETY SH) (TY P & P) LF     1,170.000 12.00000 1
512 2097 REMOVE PRECAST PORTABLE TRAFFIC BARRIE LF     36,956.000 4.14747 3
514 2004 PERM CONC TRF BARR (SGL SLP) (TY 1) (42" LF     5,366.000 57.25813 2
514 2005 PERM CONC TRF BARR (SGL SLP) (TY 2) (42" LF     45,505.000 33.45973 3
514 2006 PERM CONC TRF BARR (SGL SLP) (TY 3) (42" LF     630.000 124.60317 2
514 2014 PERM CONC TRF BARR (SGL SLP) (TY 2) (36") LF     70.000 37.86000 1
514 2022 PERM CONC TRF BARR (SGL SLP) (TY 4) (42" LF     200.000 38.10000 1
514 2045 PERM CONC TRF BARR (SGL SLP) (J - J) (36") LF     15,326.000 25.00000 1
514 2053 PERM CONC TRF BARR (F - SHAPE) (BRIDGE) LF     180.000 117.00000 1
528 2002 COLORED TEXTURED CONC (6") SY     117.000 55.00000 1
528 2004 LANDSCAPE PAVERS SY 138.000 179.35000 48,929.570 49.87125 10
529 2001 CONC CURB (TY I) LF     111.000 25.00000 1
529 2002 CONC CURB (TY II) LF     16,749.000 12.04964 6
529 2004 CONC CURB & GUTTER (TY II) LF     574.000 25.24390 2
529 2005 CONC CURB (MONO) (TY I) LF     4,009.000 14.17723 2
529 2006 CONC CURB (MONO) (TY II) LF 9.000 36.05000 202,094.000 3.11518 18
529 2007 CONC CURB (DOWEL) LF     66,603.000 9.27014 12
529 2011 CONC CURB & GUTTER (SAWTOOTH) LF     26.000 85.00000 1
529 2021 CONC CURB (DOWEL) (REINF) (TY II) LF     1,062.000 21.28249 3
529 2023 CONC CURB (MONO) LF     440.000 4.50000 1
529 2035 CONC CURB & GUTTER (TY II) (MOD) LF     60.000 75.00000 1
529 2070 CONCRETE CURB (TYPE U - TURN) (SPECIAL) LF     4,171.000 34.25428 2
529 2071 CONC CURB (SLOTTED) LF     8,081.110 5.78060 5
529 2086 CONC CURB (DOWEL) (SLOTTED) LF 720.000 22.50000 37,790.000 7.93830 7
530 2002 INTERSECTIONS (ACP) EA     26.000 3,125.00000 1
530 2005 INTERSECTIONS (ACP) SY     230.000 50.00000 1
530 2007 DRIVEWAYS (CONC) EA     4.000 4,000.00000 1
530 2008 DRIVEWAYS (ACP) EA 11.000 1,350.00000 209.000 540.81340 3
530 2010 DRIVEWAYS (CONC) SY 264.000 87.00000 45,596.960 58.03079 21
530 2011 DRIVEWAYS (ACP) SY 2,547.710 68.43652 24,200.160 44.66021 15
530 2014 TURNOUTS (ACP) EA 11.000 1,772.72727 20.000 1,740.00000 3
530 2030 DRIVEWAYS (ACP) (TYPE 1) SY     3,262.000 39.30993 2
530 2036 DRIVEWAYS (CONC) (TYPE 2) SY     1,574.700 61.81082 2
531 2003 CONC SIDEWALKS (5') (6") LF     191.000 40.00000 1
531 2004 CONC SIDEWALKS (6") SY     16,595.000 55.89538 8
531 2005 CURB RAMPS (TY 1) EA     228.000 1,346.54461 18
531 2006 CURB RAMPS (TY 2) EA 2.000 1,905.50000 51.000 1,360.98510 7
531 2007 CURB RAMPS (TY 3) EA     114.000 1,290.35088 2
531 2008 CURB RAMPS (TY 4) EA     5.000 1,300.00000 1
531 2009 CURB RAMPS (TY 6) EA     116.000 1,150.49103 2
531 2010 CURB RAMPS (TY 7) EA 3.000 2,163.00000 554.000 1,338.16323 26
531 2012 CURB RAMPS (TY 9) EA     11.000 1,345.45455 2
531 2013 CURB RAMPS (TY 20) EA     27.000 1,178.14815 2
531 2014 CURB RAMPS (TY 22) EA     16.000 2,568.78500 5
531 2015 CONC SIDEWLKS (4") SY 30.000 97.85000 4,466.000 36.17470 5
531 2017 CURB RAMPS (TY 21) EA     29.000 1,922.99310 9
531 2018 CURB RAMPS (SPECIAL) EA     19.000 4,200.00000 1
531 2019 CONC SIDEWALKS (4.5") SY     3,654.000 39.40120 2
531 2024 CONC SIDEWALK (5") SY 12.000 84.35000 10,546.000 51.11206 5
531 2040 CURB RAMPS (TY 5) EA     18.000 2,308.33333 5
531 2041 CURB RAMPS (TY 10) EA     59.000 1,250.00000 4
531 2054 CURB RAMPS SY     17.000 55.00000 1
531 2070 CURB RAMPS (TY 5) SY     76.000 207.00000 1
531 2077 CURB RAMPS (TY 3) (MOD) EA     1.000 2,000.00000 1
531 2119 CONC SIDEWALKS (SHARED USE) (10'X6") SY     4,798.200 52.00000 1
531 2120 CURB RAMPS (TY21) (TRUNCATED DOME ONLY) EA     4.000 550.00000 1
533 2006 SHOULDER TEXTURING (MILLED) (ASPHALT) LF 35,065.000 .56336 437,463.000 .26796 12
533 2007 SHOULDER TEXTURING (MILLED) (CONCRETE) LF     70,960.000 .60399 2
536 2001 CONC MEDIAN LF 100.000 92.00000 2,485.500 33.57690 4
536 2002 CONC MEDIAN SY     1,128.000 73.11010 4
536 2003 CONC DIRECTIONAL ISLAND LF     37,879.500 13.54276 3
536 2004 CONC DIRECTIONAL ISLAND SY     263.000 65.53422 2
536 2010 CONCRETE MEDIAN (DOWEL) (12") LF     124.000 65.00000 1
536 2011 CONC MEDIAN (DOWEL) (TRANSITION) LF     33.000 100.00000 1
540 2001 MTL W - BEAM GD FEN (TIM POST) LF 3,000.500 18.35886 31,979.500 18.56221 25
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     181.250 40.00000 1
540 2005 TERMINAL ANCHOR SECTION EA     81.000 1,054.56790 4
540 2009 TERMINAL ANCHOR SECTION ADJUSTMENT EA     1.000 850.00000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA 12.000 1,568.33333 113.000 1,793.60381 17
540 2012 MTL BEAM GD FEN TRANS (TL2) EA 4.000 925.00000 40.000 1,013.78350 8
540 2015 MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL LF     80.000 28.00000 1
540 2017 MTL W - BEAM GD FEN (ROUND TIMBER POST) LF     1,600.000 22.72656 2
540 2024 RADIAL TERMINAL ANCHOR SECTION (DRWY) EA     1.000 600.00000 1
540 2036 DRIVEWAY TERMINAL ANCHOR SECTION EA 1.000 725.00000 4.000 756.25000 3