AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - HOUSTON DISTRICT

Last Update: Monday, March 31, 2014
ITEMS 100 2001 TO 164 2001
Items Items Bid Code Range
0100 - 0193
0247 - 0292
0305 - 0368
0400 - 0497
0500 - 0560
0610 - 0690
0730 - 0760
1009 - 1133
2086 - 2166
3061 - 3275
4001 - 4654
5050 - 5969
6004 - 6986
7384 - 7622
8020 - 8982
100 2001 - 164 2001
164 2007 - 193 2019
Item No Description Units March 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2001 PREPARING ROW AC     162.460 8,290.09836 12
100 2002 PREPARING ROW STA     2,544.310 17,978.39800 31
100 2003 PREPARING ROW (TREE) (5" TO 12" DIA) EA     5.000 1,000.00000 1
100 2004 PREPARING ROW (TREE) (12" TO 24" DIA) EA     46.000 222.00000 1
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA     56.000 14,000.00000 1
103 2001 DISPOSAL OF WATER WELLS EA     9.000 2,600.00000 2
104 2001 REMOVING CONC (PAV) SY     1,795,566.330 4.19272 26
104 2009 REMOVING CONC (RIPRAP) SY     173,252.440 3.42641 18
104 2011 REMOVING CONC (MEDIANS) SY     5,960.550 10.72392 9
104 2015 REMOVING CONC (SIDEWALKS) SY     6,767.960 4.53844 9
104 2017 REMOVING CONC (DRIVEWAYS) SY     41,590.280 5.55964 19
104 2021 REMOVING CONC (CURB) LF     42,733.000 2.33099 18
104 2022 REMOVING CONC (CURB AND GUTTER) LF     13,649.000 1.55403 3
104 2023 REMOVING CONC (CTB) LF     120,346.000 4.11733 8
104 2024 REMOVING CONC (RETAINING WALLS) SY     35,129.600 14.70835 8
104 2025 REMOVE CONC (WINGWALL) CY     107.000 125.00000 1
104 2027 REMOVING CONC (APPR SLAB) SY     259.000 27.72201 2
104 2028 REMOVING CONC (MISC) SY     4,176.000 3.86353 3
104 2029 REMOVING CONC (CURB OR CURB & GUTTER) LF     41,450.000 1.44165 5
104 2031 REMOVING CONC (HEADWALL) CY     50.000 140.00000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     226.340 16.74870 4
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY     22,795.000 5.31127 8
104 2037 REMOVE CONC (RAIL) LF     59,890.000 7.70408 8
104 2040 REMOVING CONC (PAVERS) SY     5,590.000 5.80823 5
104 2041 REMOVING CONC (GND BOX W / APRON) EA     6.000 244.07000 1
104 2044 REMOVING CONC (FLUME) SY     1,472.000 5.44626 3
104 2045 REMOVE CONC (MISC) EA     25.000 100.00000 1
104 2047 REMOVING CONC (INTER ART CONC BLOCKS) SY     1,420.000 5.00000 1
104 2054 REMOVING CONCRETE (MOW STRIP) LF     21,102.000 2.90460 6
105 2002 REMOVING STAB BASE AND ASPH PAV (2") SY     733.000 2.00000 1
105 2005 REMOVING STAB BASE AND ASPH PAV (3") SY     1,001.000 4.90010 2
105 2008 REMOVING STAB BASE AND ASPH PAV (6") SY     2,314.400 3.15857 5
105 2011 REMOVING STAB BASE AND ASPH PAV (2" - 6" SY     38,512.640 1.84023 5
105 2013 REMOVING STAB BASE & ASPH PAV (9") SY     8,831.000 2.59000 1
105 2014 REMOVING STAB BASE & ASPH PAV (7" - 12") SY     210,631.000 3.15811 5
105 2015 REMOVING STAB BASE & ASPH PAV (8" - 10") SY     1,364.000 8.50000 1
105 2018 REMOVING STAB BASE AND ASPH PAV (7") SY     273,225.000 1.03107 2
105 2020 REMOVING STAB BASE & ASPH PAV (12") SY     310,850.980 3.15633 5
105 2021 REMOVING STAB BASE AND ASPH PAV (0 - 4") SY     152,179.000 1.05908 3
105 2022 REMOVING STAB BASE AND ASPH PAV (13") SY     388,852.000 2.10944 3
105 2026 REMOVE STAB BASE & ASPH PAV (13" - 18") SY     1,010.000 10.40000 1
105 2030 REMOVING STAB BASE & ASPH PAV (8" - 14") SY     6,630.000 10.00000 1
105 2036 REMOVING STAB BASE & ASPH PAV (15" - 20") SY     5,763.000 4.07000 1
105 2037 REMOVING STAB BASE AND ASPH PAV (0" - 16" SY     65,357.000 2.14523 2
105 2039 REMOVE STAB BASE AND ASPH PAV (6" - 20") SY     559,382.000 2.00000 1
105 2041 REMOVING STAB BASE AND ASPH PAV (8") SY     8,999.000 11.00000 1
105 2043 REMOVING STAB BASE & ASPH PAV (0 - 6") SY     14,241.220 4.89836 5
105 2044 REMOVING STAB BASE AND ASPH PAV (10") SY     972.000 11.00000 1
105 2045 REMOVING STAB BASE AND ASPH PAV (2" - 8" SY     5,729.000 5.00000 2
105 2046 REMOVING STAB BASE & ASPH PAV (0" - 10") SY     2,420.000 5.26777 2
105 2048 REMOVING STAB BASE & ASPH PAV (4" - 11") SY     3,504.000 5.66000 1
105 2049 REMOVING STAB BASE & ASPH PAV (4" - 22") SY     1,193.000 6.75000 1
105 2052 REMOVE STAB BASE & ASPH PAV (4" - 5") SY     852.000 10.00000 1
105 2058 REMOVING STAB BASE & ASPH PAV (10" - 12" SY     2,744.000 15.00000 1
105 2061 REMOV STAB BASE & ASPH PAV (8" - 20") SY     716.000 22.00000 1
105 2063 REMOVE STAB BASE AND ASPH PAV (1" - 3") SY     162,404.000 .74967 2
105 2065 REMOVING STAB BASE AND ASPH PAV (1") SY     760.000 15.00000 1
105 2069 REMOVING STAB BASE & ASPH PAV (4" - 6" SY     14,959.000 2.73000 2
105 2075 REMOV STAB BASE AND ASPH PAV (10" - 18") SY     24,890.000 7.00000 1
105 2076 REMOV STAB BASE AND ASPH PAV (2" - 15") SY     6,167.770 5.59100 3
105 2083 REMOVE STAB BASE & ASPH PAV (0" - 11.25" SY     18,371.000 1.60000 1
105 2084 REM STAB BASE & ASPH (6" - 12") SY     704,078.000 2.00000 2
105 2085 REMOVING STAB BASE & ASPH PAV (0 - 19 IN SY     8,059.000 4.00000 1
105 2088 REMOVING STAB BASE AND ASPH PAV (0" - 5") SY     174,422.000 2.00000 1
105 2096 REMOV STAB BASE AND ASPH PAV (0" - 12") SY     13,435.000 2.32000 1
110 2001 EXCAVATION (ROADWAY) CY     1,977,213.620 6.18024 44
110 2002 EXCAVATION (CHANNEL) CY     164,174.000 6.04441 10
110 2003 EXCAVATION (SPECIAL) CY     721,068.000 4.64836 8
110 2004 EXCAVATION (ROADWAY AND CHANNEL) CY     385.000 11.00000 1
112 2001 SUBGRADE WIDENING (ORD COMP) STA     292.810 466.44882 5
112 2002 SUBGRADE WIDENING (DENS CONT) STA     424.980 1,367.78084 10
132 2001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY     1,656.400 21.84451 3
132 2002 EMBANKMENT (FINAL) (DENS CONT) (TY A) CY     2,790.000 6.04634 2
132 2003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY     788.000 16.19924 3
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     286.000 11.50000 1
132 2005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     18,466.000 6.02677 6
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     3,016,367.080 3.62122 36
132 2013 EMBANKMENT (ORIGINAL) (ORD COMP) (TY C) CY     75.000 25.00000 1
132 2036 EMBANK (FINAL) (DC) (TY E) (CSBE) CY     247,169.600 24.63408 13
132 2037 EMB (FNL) (DC) (TYE) (CSBE) (RWALL FND IMPR CY     36,273.000 22.99876 7
134 2001 BACKFILL (TY A) STA 585.000 125.00000 2,770.530 196.55964 9
134 2004 BACKFILL (TY A OR B) STA     2,111.210 319.61652 8
150 2001 BLADING STA     13.000 140.00000 1
150 2002 BLADING HR     262.000 100.00000 1
156 2001 BULLDOZER WORK HR     93.000 96.90323 2
160 2003 FURNISHING AND PLACING TOPSOIL (4") SY     2,230.000 1.50000 1
160 2005 FURNISHING AND PLACING TOPSOIL CY     11,006.000 23.94689 7
160 2006 FURNISHING AND PLACING TOPSOIL (3") SY     46,368.000 1.00000 1
161 2002 COMPOST MANUF TOPSOIL (BOS) (4") SY     27,430.100 .63000 1
161 2005 COMPOST MANUF TOPSOIL (PB) (4") SY     908.000 2.00000 1
161 2006 COMPOST MANUF TOPSOIL (PB) CY     1,338.000 22.00000 1
161 2009 EROSION CONTROL COMPOST CY     1,177.500 22.47041 9
161 2011 GENERAL USE COMPOST (1") SY     4,276.000 .58500 1
161 2012 GENERAL USE COMPOST CY     9,728.500 23.75599 5
161 2014 COMPOST MANUF TOPSOIL (BOS OR PB) (4") SY     29,756.000 1.00000 1
161 2017 COMPOST MANUF TOPSOIL (BIP) (4") SY     1,375,602.900 .71469 21
161 2020 COMPOST MANUF TOPSOIL (BIP) (6") SY     137.000 5.48000 1
162 2002 BLOCK SODDING SY     1,898,486.860 2.47967 45
162 2003 STRAW OR HAY MULCH SY     3,568,321.050 .14283 38
164 2001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY     127,772.000 .10663 2