AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - HOUSTON DISTRICT

Last Update: Friday, January 29, 2016
ITEMS 400 2001 TO 425 6001
Items Items Bid Code Range
0100 - 0193
0247 - 0292
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0690
0720 - 0786
1004 - 1122
2143 - 2349
3000 - 3267
4003 - 4043
5003 - 5969
6001 - 6920
8317 - 8956
400 2001 - 425 6001
425 6002 - 462 6006
462 6007 - 466 6166
466 6172 - 496 6099
Item No Description Units January 31, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
400 2001 STRUCT EXCAV CY     459.000 10.00000 1
400 2003 STRUCT EXCAV (PIPE) CY     8.000 50.75000 1
400 2005 CEM STABIL BKFL CY     11,021.500 37.06192 5
400 2016 CEMENT STAB BACKFILL (INLET OR MH) CY     64.000 60.42500 2
400 6001 STRUCT EXCAV CY     3,838.000 6.16727 3
400 6002 STRUCT EXCAV (BOX) CY     5,589.000 15.00000 1
400 6003 STRUCT EXCAV (PIPE) CY     10,512.000 14.11035 5
400 6005 CEM STABIL BKFL CY 9,025.000 40.00000 88,937.650 39.75211 28
400 6007 CUT & RESTORE CONC PAVING SY     854.660 149.70870 2
400 6008 CUT & RESTORE ASPH PAVING SY     999.000 139.41942 4
400 6009 CEMENT STAB BACKFILL (INLET OR MH) CY 17.000 50.00000 5,743.110 37.52798 14
401 6001 FLOWABLE BACKFILL CY     579.000 126.62953 4
402 2001 TRENCH EXCAVATION PROTECTION LF     5,134.000 1.87226 3
402 6001 TRENCH EXCAVATION PROTECTION LF 10,603.000 .10000 104,809.600 2.10540 14
403 2001 TEMPORARY SPL SHORING SF     12,668.000 27.50000 1
403 6001 TEMPORARY SPL SHORING SF     138,380.800 7.71515 13
403 6006 TEMPORARY SPL SHORING (COFFERDAM) SF     321.000 130.00000 1
406 6001 TREATED TIMBER PILING LF     1,260.000 119.37000 1
409 2002 PRESTR CONC PIL (18 IN SQ) LF     1,776.000 80.00000 1
409 6001 PRESTR CONC PIL (16 IN SQ) LF     5,790.000 132.31088 3
409 6002 PRESTR CONC PIL (18 IN SQ) LF     3,948.000 89.78723 2
410 6001 SOIL NAIL ANCHORS LF     23,445.000 18.00000 1
416 2002 DRILL SHAFT (24 IN) LF     1,452.000 124.00000 1
416 2003 DRILL SHAFT (30 IN) LF     5,389.000 184.74541 3
416 2004 DRILL SHAFT (36 IN) LF     60.000 170.00000 1
416 2005 DRILL SHAFT (42 IN) LF     20.000 300.00000 1
416 2025 DRILL SHAFT (HIGH MAST POLE) (54 IN) LF     174.000 421.00000 1
416 2026 DRILL SHAFT (HIGH MAST POLE) (60 IN) LF     340.000 510.00000 1
416 2031 DRILL SHAFT (TRF SIG POLE) (30 IN) LF     742.000 165.00000 1
416 2032 DRILL SHAFT (TRF SIG POLE) (36 IN) LF     533.000 191.77531 3
416 2034 DRILL SHAFT (TRF SIG POLE) (48 IN) LF     110.000 364.00000 2
416 6001 DRILL SHAFT (18 IN) LF     1,951.000 94.26961 5
416 6002 DRILL SHAFT (24 IN) LF     1,881.000 140.00000 1
416 6003 DRILL SHAFT (30 IN) LF     19,975.000 158.83206 11
416 6004 DRILL SHAFT (36 IN) LF     8,471.000 192.00039 7
416 6005 DRILL SHAFT (42 IN) LF     7,708.000 255.71809 6
416 6006 DRILL SHAFT (48 IN) LF     1,052.000 413.69259 3
416 6008 DRILL SHAFT (60 IN) LF     483.000 620.00000 1
416 6010 DRILL SHAFT (72 IN) LF     156.000 666.25000 1
416 6011 DRILL SHAFT (78 IN) LF     964.000 665.00000 1
416 6012 DRILL SHAFT (84 IN) LF     2,837.000 564.85456 2
416 6015 DRILL SHAFT (NON - REINFORCED) (12 IN) LF     243.000 76.86008 6
416 6018 DRILL SHAFT (SIGN MTS) (24 IN) LF     153.000 113.23529 3
416 6020 DRILL SHAFT (SIGN MTS) (36 IN) LF     2,640.000 175.00000 1
416 6021 DRILL SHAFT (SIGN MTS) (42 IN) LF     3,852.000 279.78972 4
416 6022 DRILL SHAFT (SIGN MTS) (48 IN) LF     1,214.000 240.28830 3
416 6023 DRILL SHAFT (SIGN MTS) (54 IN) LF     1,018.000 385.60274 4
416 6026 DRILL SHAFT (HIGH MAST POLE) (60 IN) LF     636.000 578.88396 3
416 6027 DRILL SHAFT (HIGH MAST POLE) (66 IN) LF     720.000 525.00000 1
416 6029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF     1,588.000 103.67399 4
416 6031 DRILL SHAFT (TRF SIG POLE) (30 IN) LF     11.000 148.00000 1
416 6032 DRILL SHAFT (TRF SIG POLE) (36 IN) LF 187.000 295.57000 1,379.600 219.41743 15
416 6033 DRILL SHAFT (TRF SIG POLE) (42 IN) LF 35.000 352.67000 52.400 326.87882 2
416 6034 DRILL SHAFT (TRF SIG POLE) (48 IN) LF 176.000 367.83000 680.900 333.07179 11
420 2003 CL C CONC (ABUT) CY     125.800 844.33871 2
420 2004 CL C CONC (BENT) CY     110.400 800.00000 1
420 2011 CL C CONC (RETAINING WALL) CY     13.000 568.40000 1
420 2013 CL C CONC (MISC) CY     185.100 329.82172 2
420 2019 CL C CONC (CAP) CY     10.400 1,110.62981 1
420 2033 CL S CONC (APPR SLAB) CY     343.000 362.59350 2
420 2051 CL C CONC (COLUMN) CY     2.300 922.05652 1
420 6009 CL A CONC (COLLAR) EA     20.000 1,305.00000 2
420 6012 CL B CONC (MISC) CY     32.000 714.00000 1
420 6013 CL C CONC (ABUT) CY     1,411.400 884.77135 11
420 6019 CL C CONC (ABUT) (EXTEND) CY     662.400 1,501.49457 5
420 6025 CL C CONC (BENT) CY     3,133.800 1,033.65221 9
420 6029 CL C CONC (CAP) CY     177.400 2,131.34160 3
420 6033 CL C CONC (CAP) (EXTEND) CY     55.900 3,944.18605 2
420 6037 CL C CONC (COLUMN) CY     1,274.800 1,107.10543 5
420 6043 CL C CONC (FOOTING) CY     726.950 758.60807 5
420 6049 CL C CONC (CRASHWALL) CY     270.600 612.22997 1
420 6066 CL C CONC (RAIL FOUNDATION) CY     230.000 200.00000 1
420 6068 CL C CONC (SIGN COLUMN) CY     1,936.570 827.47667 5
420 6074 CL C CONC (MISC) CY     67.000 1,374.00000 1
420 6082 CL F CONC (CAP) CY     1,881.600 621.13878 3
420 6090 CL F CONC (COLUMN) CY     72.400 900.00000 1
420 6122 CL HES CONC (APPROACH SLAB) CY     2,217.000 425.00000 1
420 6134 CL C CONC (SIGN FOOTING) CY     271.800 614.71670 3
422 2001 REINF CONC SLAB SF     18,856.160 11.02495 2
422 6001 REINF CONC SLAB SF     352,919.000 14.91504 7
422 6003 REINF CONC SLAB (EXTEND SLAB) SF     256,559.000 17.35371 5
422 6005 REINF CONC SLAB (BOX BEAM) SF     4,539.000 20.00000 1
422 6007 REINF CONC SLAB (SLAB BEAM) SF     29,139.510 10.86895 3
422 6011 BRIDGE MEDIAN SF     10,928.000 4.00000 1
422 6013 BRIDGE SIDEWALK SF     13,582.510 9.17419 4
422 6015 APPROACH SLAB CY     1,215.100 576.50260 10
422 6023 SHEAR KEY CY     28.200 475.00000 1
422 6026 SLAB SPAN (EXTEND) CY     441.400 1,400.00000 1
423 2001 RETAINING WALL (MSE) SF     1,241.000 65.75000 1
423 2012 RETAINING WALL (CAST - IN - PLACE) SF     1,780.000 50.00000 1
423 6001 RETAINING WALL (MSE) SF     44,407.000 33.85810 2
423 6008 RETAINING WALL (CAST - IN - PLACE) SF     198.000 120.00000 1
423 6010 RET WALL (SPREAD FOOTING) (SPL) SF     541.000 70.00000 1
423 6014 RETAINING WALL (MSE) (HORIZONTAL SCHEME SF     42,754.000 25.59429 2
423 6015 RETAINING WALL (SPECIAL) SF     319.000 70.00000 1
423 6019 RET WALL (MSE) (VERTICAL SCHEME) (SPL) SF     88,460.000 30.53697 3
423 6022 RETAINING WALL (SOIL NAIL) (FACIA) SF     9,097.000 30.00000 1
425 2016 PRESTR CONC SLAB BEAM (4SB15) LF     1,455.700 135.00000 1
425 2017 PRESTR CONC SLAB BEAM (5SB15) LF     1,455.700 142.00000 1
425 6001 PRESTR CONC BOX BEAM (4B20) LF     818.520 180.00000 1