| AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - EL PASO DISTRICT | ||||
| Last Update: Thursday, October 29, 2009 |
| ITEMS 100 2002 TO 192 2017 |
| Item No | Description | Units | October 31, 2009 | Twelve Month Moving | Usage | ||
|---|---|---|---|---|---|---|---|
| Quantity | Avg Bid | Quantity | Avg Bid | ||||
| 100 2002 | PREPARING ROW | STA | 93.000 | 915.05376 | 2 | ||
| 104 2001 | REMOVING CONC (PAV) | SY | 11,284.000 | 24.00000 | 1 | ||
| 104 2009 | REMOVING CONC (RIPRAP) | SY | 14,708.000 | 12.14727 | 2 | ||
| 104 2015 | REMOVING CONC (SIDEWALKS) | SY | 184.000 | 20.00000 | 1 | ||
| 104 2017 | REMOVING CONC (DRIVEWAYS) | SY | 397.000 | 25.00000 | 1 | ||
| 104 2021 | REMOVING CONC (CURB) | LF | 37,287.000 | 2.01046 | 2 | ||
| 104 2022 | REMOVING CONC (CURB AND GUTTER) | LF | 2,108.000 | 8.39848 | 3 | ||
| 104 2027 | REMOVING CONC (APPR SLAB) | SY | 403.000 | 69.12159 | 2 | ||
| 104 2028 | REMOVING CONC (MISC) | SY | 50.000 | 27.00000 | 1 | ||
| 104 2029 | REMOVING CONC (CURB OR CURB & GUTTER) | LF | 20,737.000 | 4.00000 | 1 | ||
| 104 2032 | REMOVING CONC (WHEELCHAIR RAMP) | SY | 16.000 | 24.00000 | 1 | ||
| 104 2033 | REMOVING CONC (DRAIN) | SY | 150.000 | 14.00000 | 1 | ||
| 104 2037 | REMOVE CONC (RAIL) | LF | 3,084.000 | 6.00000 | 1 | ||
| 105 2070 | REMOVING STAB BASE & ASPH PAV (6" - 8" | SY | 200.000 | 19.00000 | 1 | ||
| 106 2001 | OBLITERATING ABANDONED ROAD | STA | 13.250 | 1,400.00000 | 1 | ||
| 110 2001 | EXCAVATION (ROADWAY) | CY | 9,473.000 | 10.05996 | 4 | ||
| 110 2003 | EXCAVATION (SPECIAL) | CY | 3,584.000 | 4.00000 | 1 | ||
| 132 2002 | EMBANKMENT (FINAL) (DENS CONT) (TY A) | CY | 13,028.000 | 15.63632 | 3 | ||
| 132 2003 | EMBANKMENT (FINAL) (ORD COMP) (TY B) | CY | 240.000 | 11.00000 | 1 | ||
| 134 2001 | BACKFILL (TY A) | STA | 486.000 | 85.00000 | 1 | ||
| 134 2002 | BACKFILL (TY B) | STA | 161.000 | 80.00000 | 484.250 | 82.02375 | 4 |
| 134 2008 | BACKFILL (TY A OR B) | CY | 20.000 | 67.00000 | 1 | ||
| 150 2002 | BLADING | HR | 80.000 | 82.50000 | 2 | ||
| 158 2002 | SPEC EXCAV WORK (BACKHOE) | HR | 5.000 | 80.00000 | 1 | ||
| 161 2026 | COMPOST MANUF TOPSOIL (BOS OR PB) (6") | SY | 452.000 | 9.00000 | 2 | ||
| 162 2002 | BLOCK SODDING | SY | 452.000 | 11.00000 | 2 | ||
| 192 2017 | VEGETATION BARRIER | SY | 471.000 | 2.00000 | 1 | ||
| | ||||
|