Monthly Local Let Maintenance Report For Bryan District As Of Apr 10, 2017 Page 4 Of 4

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-79-001
Proj IDSUP - 631279001
Work TypeLITTER PICKUP
 
0.010130588.1631024.6823.7
Work Order01-04-17
Work Began12-14-16
Work Completed
Time Computed01-12-17
Contract Working Days365
Addl Days Granted0
Working Days Charged108
Percent Time Used29
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161724
Totals130588.1615512.3431024.6823.7

CountyWASHINGTON
HighwayFM0389
From@ LITTLE SANDY CREEK
To@ LITTLE SANDY CREEK
CSJ6313-93-001
Proj IDRMC - 631393001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001146712.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171701
Totals146712.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6314-43-001
Proj IDSUP - 631443001
Work TypeDISTRICT COMPLEX BUILDING JANITORIAL
 
0.00183029.8414150.9517.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6314-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171702
Totals83029.840.0014150.9517.0

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6314-44-001
Proj IDSUP - 631444001
Work TypeBUILDING JANITORIAL
 
0.01020834.003976.7219.0
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171703
Totals20834.001532.483976.7219.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6314-45-001
Proj IDSUP - 631445001
Work TypeBUILDING JANITORIAL
 
0.01012349.622256.8118.2
Work Order02-10-17
Work Began02-01-17
Work Completed
Time Computed02-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged50
Percent Time Used13
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171704
Totals12349.621591.352256.8118.2

CountyBRAZOS
HighwayFM0974
FromVARIOUS
ToVARIOUS
CSJ6314-46-001
Proj IDSUP - 631446001
Work TypeREMOVAL & DISPOSAL OF SCRAP TIRE & FRAG
 
0.01091911.118156.728.8
Work Order02-09-17
Work Began02-11-17
Work Completed
Time Computed02-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged50
Percent Time Used13
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171705
Totals91911.114078.368156.728.8

CountyMADISON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6314-47-001
Proj IDSUP - 631447001
Work TypeMADISON JANITORIAL
 
0.0105337.46269.585.0
Work Order03-09-17
Work Began03-09-17
Work Completed
Time Computed03-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged29
Percent Time Used7
Contractor(s)
TIBH INDUSTRIES, INC.
ODJ INC. "OUR SPECIALTY HELPING OTHERS IN NEED"
SUBCONTRACTOR(S) FOR CCSJ: 6314-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171702
Totals5337.46269.58269.585.0

CountyBRAZOS
HighwayFM0974
FromVARIOUS
ToVARIOUS
CSJ6314-48-001
Proj IDSUP - 631448001
Work TypeBUILDING JANIT BRAZOS COUNTY WORLD TECH
 
0.00124870.721066.324.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-09-17
Work Began03-12-17
Work Completed
Time Computed03-12-17
Contract Working Days365
Addl Days Granted0
Working Days Charged20
Percent Time Used5
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171703
Totals24870.720.001066.324.2

CountyWALKER
HighwayFM0247
FromFM 247 & FM 2821
ToFM 247 & FM 2821
CSJ6314-49-001
Proj IDSUP - 631449001
Work TypePARK & RIDE MOW & LITTER PICKUP - RUCON
 
0.0105033.84356.957.0
Work Order03-06-17
Work Began03-02-17
Work Completed
Time Computed03-06-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171704
Totals5033.84356.95356.957.0

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6315-09-001
Proj IDRMC - 631509001
Work TypePICNIC AREA MAINTENANCE
 
0.00125570.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TWO SISTER'S CONST CO.
SUBCONTRACTOR(S) FOR CCSJ: 6315-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171703
Totals25570.000.000.000.0