Monthly Local Let Maintenance Report For Bryan District As Of Dec 9, 2016 Page 4 Of 4

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway SH0164
From SH 164 AT MINE HAUL ROAD
To SH 164 AT MINE HAUL ROAD
CSJ 6305-49-001
Proj ID EMC - 630549001
Work Type BRIDGE REPAIR
 
0.001 1198951.50 0.00 1158472.44 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-19-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 75
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161740
Totals 1198951.50 0.00 1158472.44 96.6

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6306-59-001
Proj ID RMC - 630659001
Work Type REPAIR OF METAL BEAM GUARD FENCE
 
0.001 313405.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161704
Totals 313405.00 0.00 0.00 0.0

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6307-68-001
Proj ID SUP - 630768001
Work Type TREE REMOVAL
 
0.001 30219.00 0.00 7522.00 24.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 38
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161730
Totals 30219.00 0.00 7522.00 24.8

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6307-73-001
Proj ID SUP - 630773001
Work Type BUILDING JANITORIAL
 
0.001 17219.37 1217.20 5173.10 30.0
Work Order 08-02-16
Work Began 08-02-16
Work Completed  
Time Computed 08-02-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161732
Totals 17219.37 1217.20 5173.10 30.0

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6307-74-001
Proj ID SUP - 630774001
Work Type PICNIC AREA MAINTENANCE
 
0.001 34454.32 2204.20 10984.30 31.8
Work Order 08-01-16
Work Began 08-01-16
Work Completed  
Time Computed 08-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6307-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161733
Totals 34454.32 2204.20 10984.30 31.8

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6308-55-001
Proj ID SUP - 630855001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 114516.88 11854.05 37932.93 33.1
Work Order 08-24-16
Work Began 08-18-16
Work Completed  
Time Computed 08-24-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 28
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161730
Totals 114516.88 11854.05 37932.93 33.1

CountyGRIMES
Highway BS0006S
From VARIOUS
To VARIOUS
CSJ 6309-22-001
Proj ID SUP - 630922001
Work Type PICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.001 41135.00 3132.98 10146.04 24.6
Work Order 08-30-16
Work Began 09-02-16
Work Completed  
Time Computed 09-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161731
Totals 41135.00 3132.98 10146.04 24.6

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6309-23-001
Proj ID SUP - 630923001
Work Type PICNIC AREA & WEIGH STATION MAINTENANCE
 
0.010 25508.74 1757.50 5537.15 21.7
Work Order 09-06-16
Work Began 09-02-16
Work Completed  
Time Computed 09-06-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6309-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161732
Totals 25508.74 1757.50 5537.15 21.7

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6309-24-001
Proj ID SUP - 630924001
Work Type BUILDING JANITORIAL
 
0.001 18242.52 0.00 4703.42 25.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-06-16
Work Began 09-03-16
Work Completed  
Time Computed 09-06-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6309-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161733
Totals 18242.52 0.00 4703.42 25.7

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6309-25-001
Proj ID SUP - 630925001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 72981.00 8109.00 21083.40 28.8
Work Order 09-13-16
Work Began 09-13-16
Work Completed  
Time Computed 09-13-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161734
Totals 72981.00 8109.00 21083.40 28.8

CountyBURLESON
Highway FM0050
From VARIOUS
To VARIOUS
CSJ 6309-26-001
Proj ID SUP - 630926001
Work Type PICNIC / CAR POOL MAINT IN BURLESON COUNTY
 
0.001 32332.32 2461.12 7986.54 24.7
Work Order 09-02-16
Work Began 09-02-16
Work Completed  
Time Computed 09-02-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161735
Totals 32332.32 2461.12 7986.54 24.7

CountyLEON
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6309-27-001
Proj ID SUP - 630927001
Work Type PICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.001 38028.24 2979.02 8912.52 23.4
Work Order 09-02-16
Work Began 09-02-16
Work Completed  
Time Computed 09-02-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161736
Totals 38028.24 2979.02 8912.52 23.4

CountyLEON
Highway US0079
From SH 7
To IH 45
CSJ 6310-79-001
Proj ID RMC - 631079001
Work Type TREE TRIMMING
 
18.900 119510.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KENT PHILLIPS PUMPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11161701
Totals 119510.00 0.00 0.00 0.0

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6311-88-001
Proj ID SUP - 631188001
Work Type PICNIC AREA MAINTENANCE
 
0.001 21475.00 0.00 1522.50 7.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 11-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 7
Contractor(s)
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10161705
Totals 21475.00 0.00 1522.50 7.0