Monthly Local Let Maintenance Report For Bryan District As Of Jan 11, 2017 Page 4 Of 5

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6308-35-001
Proj IDRMC - 630835001
Work TypeROADSIDE MOWING
 
263.500127274.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161708
Totals127274.220.000.000.0

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-36-001
Proj IDRMC - 630836001
Work TypeROADSIDE MOWING
 
220.40097648.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161709
Totals97648.480.000.000.0

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-37-001
Proj IDRMC - 630837001
Work TypeROADSIDE MOWING
 
278.600167318.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161710
Totals167318.520.000.000.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-55-001
Proj IDSUP - 630855001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE
 
0.010114516.8842674.5537.2
Work Order08-24-16
Work Began08-18-16
Work Completed
Time Computed08-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161730
Totals114516.884741.6242674.5537.2

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6309-22-001
Proj IDSUP - 630922001
Work TypePICNIC AREA MAINTENANCE IN GRIMES
 
0.00141135.0013213.6032.1
Work Order08-30-16
Work Began09-02-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161731
Totals41135.003067.5613213.6032.1

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6309-23-001
Proj IDSUP - 630923001
Work TypePICNIC AREA & WEIGH STATION
 
0.01025508.747495.4829.3
Work Order09-06-16
Work Began09-02-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6309-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161732
Totals25508.741958.337495.4829.3

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6309-24-001
Proj IDSUP - 630924001
Work TypeBUILDING JANITORIAL
 
0.00118242.525965.6632.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-16
Work Began09-03-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6309-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161733
Totals18242.520.005965.6632.7

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6309-25-001
Proj IDSUP - 630925001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE
 
0.01072981.0024327.0033.3
Work Order09-13-16
Work Began09-13-16
Work Completed
Time Computed09-13-16
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161734
Totals72981.003243.6024327.0033.3

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6309-26-001
Proj IDSUP - 630926001
Work TypePICNIC/CAR POOL MAINT IN BURLESON
 
0.00132332.3210375.3232.0
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161735
Totals32332.322388.7810375.3232.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6309-27-001
Proj IDSUP - 630927001
Work TypePICNIC AREA MAINTENANCE FOR LEON
 
0.00138028.2411891.5431.2
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161736
Totals38028.242979.0211891.5431.2

CountyLEON
HighwayUS0079
FromSH 7
ToIH 45
CSJ6310-79-001
Proj IDRMC - 631079001
Work TypeTREE TRIMMING
 
18.900119510.0016300.0013.6
Work Order12-27-16
Work Began12-27-16
Work Completed
Time Computed12-27-16
Contract Working Days38
Addl Days Granted0
Working Days Charged2
Percent Time Used5
Contractor(s)
KENT PHILLIPS PUMPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161701
Totals119510.0016300.0016300.0013.6

CountyFREESTONE
HighwayFM0488
FromAT RICHLAND CREEK
ToAT RICHLAND CREEK
CSJ6310-85-001
Proj IDBPM - 631085001
Work TypeBRIDGE JOINT REPAIR
 
0.303267641.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161712
Totals267641.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6310-91-001
Proj IDRMC - 631091001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001194000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161711
Totals194000.000.000.000.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6311-88-001
Proj IDSUP - 631188001
Work TypePICNIC AREA MAINTENANCE
 
0.00121475.003017.5014.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-04-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged58
Percent Time Used15
Contractor(s)
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161705
Totals21475.000.003017.5014.0

CountyWASHINGTON
HighwayFM0389
FromVARIOUS
ToVARIOUS
CSJ6311-90-001
Proj IDRMC - 631190001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001224006.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161714
Totals224006.000.000.000.0

CountyMADISON
HighwaySH0090
FromVARIOUS
ToVARIOUS
CSJ6311-91-001
Proj IDRMC - 631191001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001158724.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161713
Totals158724.000.000.000.0

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6312-11-001
Proj IDRMC - 631211001
Work TypePICNIC AREA MAINTENANCE
 
0.001299.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SKLM SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6312-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171702
Totals299.390.000.000.0

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6312-70-001
Proj IDSUP - 631270001
Work TypeLITTER PICKUP
 
0.010116769.620.000.0
Work Order01-03-17
Work Began12-14-16
Work Completed
Time Computed12-20-16
Contract Working Days365
Addl Days Granted0
Working Days Charged18
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161715
Totals116769.620.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-71-001
Proj IDSUP - 631271001
Work TypeLITTER PICKUP
 
0.010395432.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged18
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161716
Totals395432.400.000.000.0

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6312-72-001
Proj IDSUP - 631272001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.010124173.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged18
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161717
Totals124173.420.000.000.0