Monthly Local Let Maintenance Report For Bryan District As Of May 15, 2013 Page 4 Of 4

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6254-35-001
Proj ID RMC - 625435001
Work Type ROADSIDE MOWING
 
340.700 161391.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131704
Totals 161391.62 0.00 0.00 0.0

CountyROBERTSON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6254-36-001
Proj ID RMC - 625436001
Work Type ROADSIDE MOWING
 
288.315 118536.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-13
Work Began 05-20-13
Work Completed  
Time Computed 05-28-13
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6254-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131705
Totals 118536.17 0.00 0.00 0.0

CountyWALKER
Highway FM1374
From VARIOUS
To VARIOUS
CSJ 6254-37-001
Proj ID RMC - 625437001
Work Type ROADSIDE MOWING
 
296.400 112345.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K&W LAWN CARE
SUBCONTRACTOR(S) FOR CCSJ: 6254-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131706
Totals 112345.12 0.00 0.00 0.0

CountyMADISON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6254-38-001
Proj ID RMC - 625438001
Work Type ROADSIDE MOWING
 
239.000 121785.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 00-00-00
Work Completed  
Time Computed 06-03-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6254-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131707
Totals 121785.20 0.00 0.00 0.0

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6254-39-001
Proj ID RMC - 625439001
Work Type ROADSIDE MOWING
 
225.457 190002.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-13
Work Began 00-00-00
Work Completed  
Time Computed 05-28-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6254-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131708
Totals 190002.40 0.00 0.00 0.0

CountyLEON
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6254-40-001
Proj ID RMC - 625440001
Work Type ROADSIDE MOWING
 
350.900 180329.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-13
Work Began 04-17-13
Work Completed  
Time Computed 05-28-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131709
Totals 180329.60 0.00 0.00 0.0

CountyWALKER
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6254-61-001
Proj ID RMC - 625461001
Work Type TREE REMOVAL
 
0.001 61886.15 10095.00 10095.00 16.3
Work Order 04-18-13
Work Began 04-18-13
Work Completed  
Time Computed 04-26-13
Contract Working Days 93
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 3
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6254-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131703
Totals 61886.15 10095.00 10095.00 16.3

CountyLEON
Highway SH0075
From AT FORT BOGGY STATE PARK
To AT FORT BOGGY STATE PARK
CSJ 6255-01-001
Proj ID RMC - 625501001
Work Type SEAL COAT
 
0.574 80857.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 8
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131703
Totals 80857.50 0.00 0.00 0.0

CountyMADISON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6255-13-001
Proj ID RMC - 625513001
Work Type TREE REMOVAL
 
0.001 61850.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 93
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6255-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131704
Totals 61850.00 0.00 0.00 0.0

CountyGRIMES
Highway SH0090
From VARIOUS
To VARIOUS
CSJ 6255-83-001
Proj ID RMC - 625583001
Work Type TREE REMOVAL
 
0.001 47394.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORES TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6255-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131706
Totals 47394.00 0.00 0.00 0.0

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6255-88-001
Proj ID RMC - 625588001
Work Type TREE REMOVAL
 
0.001 62650.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6255-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131707
Totals 62650.00 0.00 0.00 0.0

CountyWALKER
Highway IH0045
From MM129
To MM130
CSJ 6256-52-001
Proj ID SUP - 625652001
Work Type BRUSH AND TREE REMOVAL
 
1.500 52173.76 0.00 48521.60 93.0
Work Order 03-01-13
Work Began 03-01-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131733
Totals 52173.76 0.00 48521.60 93.0

page 1 | page 2 | page 3 | page 4