Monthly Local Let Maintenance Report For Bryan District As Of Oct 14, 2014 Page 5 Of 5

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6275-76-001
Proj ID RMC - 627576001
Work Type REPAIR OF METAL BEAM GUARD FENCE
 
0.001 178903.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6275-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141708
Totals 178903.00 0.00 0.00 0.0

CountyFREESTONE
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6277-31-001
Proj ID SUP - 627731001
Work Type REMOVAL OF SCRAP WHOLE TIRES
 
0.010 37348.52 0.00 7181.39 19.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-11-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 10
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141733
Totals 37348.52 0.00 7181.39 19.2

CountyLEON
Highway IH0045
From FREESTONE C/L
To MADISON C/L
CSJ 6277-32-001
Proj ID SUP - 627732001
Work Type STATE USE
 
0.010 31699.41 0.00 7312.82 23.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 10
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141743
Totals 31699.41 0.00 7312.82 23.0

CountyMADISON
Highway IH0045
From LEON C/L
To WALKER C/L
CSJ 6277-33-001
Proj ID SUP - 627733001
Work Type STATE USE
 
0.010 26255.19 0.00 6055.38 23.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 10
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141753
Totals 26255.19 0.00 6055.38 23.0

CountyWALKER
Highway IH0045
From MADISON C/L
To MONTGOMERY C/L
CSJ 6277-34-001
Proj ID SUP - 627734001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 12527.56 0.00 2885.44 23.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-14
Work Began 00-00-00
Work Completed  
Time Computed 08-11-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 9
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141763
Totals 12527.56 0.00 2885.44 23.0

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6277-35-001
Proj ID SUP - 627735001
Work Type BUILDING JANITORIAL
 
0.010 16610.45 0.00 2048.13 12.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141733
Totals 16610.45 0.00 2048.13 12.3

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6277-37-001
Proj ID SUP - 627737001
Work Type PICNIC AREA MAINTENANCE
 
0.001 31818.28 0.00 3791.84 11.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6277-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141743
Totals 31818.28 0.00 3791.84 11.9

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6278-02-001
Proj ID SUP - 627802001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 106899.19 0.00 11065.51 10.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-18-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141773
Totals 106899.19 0.00 11065.51 10.3

CountyLEON
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6279-11-001
Proj ID SUP - 627911001
Work Type PICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.001 34615.92 1337.68 1337.68 3.8
Work Order 09-02-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141783
Totals 34615.92 1337.68 1337.68 3.8

CountyBURLESON
Highway FM0050
From VARIOUS
To VARIOUS
CSJ 6279-12-001
Proj ID SUP - 627912001
Work Type PICNIC / CAR POOL MAINT IN BURLESON CO
 
0.001 30479.34 1250.85 1250.85 4.1
Work Order 09-02-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141793
Totals 30479.34 1250.85 1250.85 4.1

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6279-24-001
Proj ID SUP - 627924001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.001 68046.75 0.00 4536.45 6.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-26-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 3
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141789
Totals 68046.75 0.00 4536.45 6.6

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6279-25-001
Proj ID SUP - 627925001
Work Type BUILDING JANITORIAL FOR FREESTONE CO
 
0.001 18242.52 0.00 473.34 2.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-03-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 3
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6279-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141790
Totals 18242.52 0.00 473.34 2.5

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6279-38-001
Proj ID SUP - 627938001
Work Type PICNIC AREA & WEIGH STATION MAINTENANCE
 
0.010 23471.42 0.00 1119.36 4.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6279-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141791
Totals 23471.42 0.00 1119.36 4.7

CountyGRIMES
Highway BS0006S
From VARIOUS
To VARIOUS
CSJ 6279-40-001
Proj ID SUP - 627940001
Work Type PICNIC AREA MAINTENANCE
 
0.001 38436.32 0.00 1592.40 4.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141792
Totals 38436.32 0.00 1592.40 4.1