Monthly Local Let Maintenance Report For Bryan District As Of Apr 11, 2014 Page 3 Of 4

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWALKER
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6263-21-001
Proj ID RMC - 626321001
Work Type TREE REMOVAL
 
0.001 123450.00 31813.00 51624.00 41.8
Work Order 01-21-14
Work Began 01-29-14
Work Completed  
Time Computed 01-29-14
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 11
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6263-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131702
Totals 123450.00 31813.00 51624.00 41.8

CountyMILAM
Highway FM0486
From VARIOUS
To VARIOUS
CSJ 6263-24-001
Proj ID RMC - 626324001
Work Type TREE REMOVAL
 
0.001 127955.00 29059.00 55269.00 43.1
Work Order 11-24-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 14
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131703
Totals 127955.00 29059.00 55269.00 43.1

CountyBRAZOS
Highway SH0021
From VARIOUS
To VARIOUS
CSJ 6263-25-001
Proj ID RMC - 626325001
Work Type TREE REMOVAL
 
0.001 152345.00 0.00 45754.00 33.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-08-14
Work Began 01-08-14
Work Completed  
Time Computed 01-16-14
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 25
Contractor(s)
HAM-BAR, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6263-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131704
Totals 152345.00 0.00 45754.00 33.5

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6263-30-001
Proj ID RMC - 626330001
Work Type INSTALL / REMOVE RAISED PAVEMENT MARKERS
 
0.001 95000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-08-14
Work Began 00-00-00
Work Completed  
Time Computed 04-16-14
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6263-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131705
Totals 95000.00 0.00 0.00 0.0

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6263-31-001
Proj ID RMC - 626331001
Work Type INSTALL / REMOVE RAISED PAVEMENT MARKERS
 
0.001 95000.00 0.00 67250.00 70.7
Work Order 01-09-14
Work Began 01-09-14
Work Completed  
Time Computed 01-17-14
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 46
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6263-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131706
Totals 95000.00 0.00 67250.00 70.7

CountyWALKER
Highway SH0030
From VARIOUS
To VARIOUS
CSJ 6263-32-001
Proj ID RMC - 626332001
Work Type INSTALL / REMOVE RAISED PAVEMENT MARKERS
 
0.001 123000.00 65178.00 83744.00 68.0
Work Order 02-04-14
Work Began 02-06-14
Work Completed  
Time Computed 02-14-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 56
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6263-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131707
Totals 123000.00 65178.00 83744.00 68.0

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6264-03-001
Proj ID SUP - 626403001
Work Type BUILDING JANITORIAL FOR FREESTONE CO
 
0.001 17710.72 0.00 8395.82 54.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-03-13
Work Began 09-03-13
Work Completed  
Time Computed 09-03-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6264-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131733
Totals 17710.72 0.00 8395.82 54.3

CountyROBERTSON
Highway FM0485
From @ THE BRAZOS RIVER BRIDGE
To @ THE BRAZOS RIVER BRIDGE
CSJ 6264-05-001
Proj ID RMC - 626405001
Work Type DRIFTWOOD AND DEBRIS REMOVAL
 
0.001 17498.00 16998.00 16998.00 97.1
Work Order 02-20-14
Work Began 02-20-14
Work Completed  
Time Computed 02-28-14
Contract Working Days 7
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 42
Contractor(s)
RHB CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131702
Totals 17498.00 16998.00 16998.00 97.1

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6265-66-001
Proj ID SUP - 626566001
Work Type LITTER PICKUP
 
0.010 108023.00 10742.75 40072.72 37.0
Work Order 12-18-13
Work Began 12-02-13
Work Completed  
Time Computed 12-18-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131733
Totals 108023.00 10742.75 40072.72 37.0

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6265-67-001
Proj ID SUP - 626567001
Work Type LITTER PICKUP
 
0.010 285041.42 16447.26 69500.77 24.3
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-10-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131733
Totals 285041.42 16447.26 69500.77 24.3

CountyLEON
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6265-68-001
Proj ID SUP - 626568001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 155024.96 0.00 76891.18 49.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131735
Totals 155024.96 0.00 76891.18 49.5

CountyBURLESON
Highway SH0021
From VARIOUS
To VARIOUS
CSJ 6265-69-001
Proj ID SUP - 626569001
Work Type LITTER PICKUP
 
0.010 99643.76 0.00 35954.52 36.0
Work Order 12-01-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131736
Totals 99643.76 0.00 35954.52 36.0

CountyMILAM
Highway US0077
From VARIOUS
To VARIOUS
CSJ 6265-70-001
Proj ID SUP - 626570001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 83777.44 0.00 0.00 0.0
Work Order 02-19-14
Work Began 00-00-00
Work Completed  
Time Computed 02-27-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131737
Totals 83777.44 0.00 0.00 0.0

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6265-71-001
Proj ID SUP - 626571001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 170897.72 10801.44 20604.55 12.0
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6265-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131738
Totals 170897.72 10801.44 20604.55 12.0

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6265-72-001
Proj ID SUP - 626572001
Work Type LITTER PICKUP
 
0.010 86595.45 0.00 11685.37 13.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-14
Work Began 00-00-00
Work Completed  
Time Computed 03-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131739
Totals 86595.45 0.00 11685.37 13.4

CountyWALKER
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6265-73-001
Proj ID SUP - 626573001
Work Type LITTER PICKUP
 
0.010 204135.80 26602.06 52941.23 25.9
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131740
Totals 204135.80 26602.06 52941.23 25.9

CountyMADISON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6265-74-001
Proj ID SUP - 626574001
Work Type LITTER PICKUP
 
0.010 110951.28 0.00 29526.94 26.6
Work Order 12-17-13
Work Began 12-02-13
Work Completed  
Time Computed 12-17-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131741
Totals 110951.28 0.00 29526.94 26.6

CountyGRIMES
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6265-75-001
Proj ID SUP - 626575001
Work Type LITTER PICKUP
 
0.010 96370.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 12-02-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131742
Totals 96370.09 0.00 0.00 0.0

CountyWALKER
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6265-92-001
Proj ID RMC - 626592001
Work Type MBGF & CABLE BARRIER REPAIR
 
0.001 146182.00 0.00 0.00 0.0
Work Order 03-14-14
Work Began 00-00-00
Work Completed  
Time Computed 03-22-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 2
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6265-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141705
Totals 146182.00 0.00 0.00 0.0

CountyBRAZOS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6266-15-001
Proj ID RMC - 626615001
Work Type INSTALLATION OF DRIVEWAY PIPE
 
0.001 285604.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6266-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131701
Totals 285604.00 0.00 0.00 0.0