Monthly Local Let Maintenance Report For Bryan District As Of Aug 12, 2014 Page 3 Of 5

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6264-03-001
Proj ID SUP - 626403001
Work Type BUILDING JANITORIAL FOR FREESTONE CO
 
0.001 17710.72 0.00 13603.94 76.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-03-13
Work Began 09-03-13
Work Completed  
Time Computed 09-03-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 301
Percent Time Used 82
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6264-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131733
Totals 17710.72 0.00 13603.94 76.8

CountyROBERTSON
Highway FM0485
From @ THE BRAZOS RIVER BRIDGE
To @ THE BRAZOS RIVER BRIDGE
CSJ 6264-05-001
Proj ID RMC - 626405001
Work Type DRIFTWOOD AND DEBRIS REMOVAL
 
0.001 17498.00 0.00 16998.00 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-20-14
Work Began 02-20-14
Work Completed  
Time Computed 02-28-14
Contract Working Days 7
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 42
Contractor(s)
RHB CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131702
Totals 17498.00 0.00 16998.00 97.1

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6265-66-001
Proj ID SUP - 626566001
Work Type LITTER PICKUP
 
0.010 108023.00 14253.32 54326.04 50.2
Work Order 12-18-13
Work Began 12-02-13
Work Completed  
Time Computed 12-18-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131733
Totals 108023.00 14253.32 54326.04 50.2

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6265-67-001
Proj ID SUP - 626567001
Work Type LITTER PICKUP
 
0.010 285041.42 16447.26 170365.77 59.7
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-10-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131733
Totals 285041.42 16447.26 170365.77 59.7

CountyLEON
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6265-68-001
Proj ID SUP - 626568001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 155024.96 0.00 117063.17 75.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131735
Totals 155024.96 0.00 117063.17 75.5

CountyBURLESON
Highway SH0021
From VARIOUS
To VARIOUS
CSJ 6265-69-001
Proj ID SUP - 626569001
Work Type LITTER PICKUP
 
0.010 99643.76 24374.20 71946.08 72.2
Work Order 12-01-13
Work Began 12-02-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131736
Totals 99643.76 24374.20 71946.08 72.2

CountyMILAM
Highway US0077
From VARIOUS
To VARIOUS
CSJ 6265-70-001
Proj ID SUP - 626570001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 83777.44 6135.09 45773.81 54.6
Work Order 02-19-14
Work Began 12-02-13
Work Completed  
Time Computed 02-27-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131737
Totals 83777.44 6135.09 45773.81 54.6

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6265-71-001
Proj ID SUP - 626571001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 170897.72 4002.21 49888.80 29.1
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6265-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131738
Totals 170897.72 4002.21 49888.80 29.1

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6265-72-001
Proj ID SUP - 626572001
Work Type LITTER PICKUP
 
0.010 86595.45 0.00 42047.90 48.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-14
Work Began 12-02-13
Work Completed  
Time Computed 03-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131739
Totals 86595.45 0.00 42047.90 48.5

CountyWALKER
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6265-73-001
Proj ID SUP - 626573001
Work Type LITTER PICKUP
 
0.010 204135.80 5590.92 105671.71 51.7
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131740
Totals 204135.80 5590.92 105671.71 51.7

CountyMADISON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6265-74-001
Proj ID SUP - 626574001
Work Type LITTER PICKUP
 
0.010 110951.28 0.00 59053.88 53.2
Work Order 12-17-13
Work Began 12-02-13
Work Completed  
Time Computed 12-17-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131741
Totals 110951.28 0.00 59053.88 53.2

CountyGRIMES
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6265-75-001
Proj ID SUP - 626575001
Work Type LITTER PICKUP
 
0.010 96370.09 0.00 29004.10 30.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-02-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131742
Totals 96370.09 0.00 29004.10 30.0

CountyWALKER
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6265-92-001
Proj ID RMC - 626592001
Work Type MBGF & CABLE BARRIER REPAIR
 
0.001 146182.00 0.00 47221.00 32.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-14-14
Work Began 03-14-14
Work Completed  
Time Computed 03-22-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 27
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6265-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141705
Totals 146182.00 0.00 47221.00 32.3

CountyBRAZOS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6266-15-001
Proj ID RMC - 626615001
Work Type INSTALLATION OF DRIVEWAY PIPE
 
0.001 285604.00 35440.00 77710.00 27.2
Work Order 04-28-14
Work Began 04-28-14
Work Completed  
Time Computed 05-06-14
Contract Working Days 72
Addl Days Granted 16
Working Days Charged 43
Percent Time Used 48
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6266-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131701
Totals 285604.00 35440.00 77710.00 27.2

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6267-66-001
Proj ID SUP - 626766001
Work Type TREE REMOVAL
 
0.001 36600.00 0.00 38770.00 99.9
Work Order 11-21-13
Work Began 11-25-13
Work Completed  
Time Computed 11-25-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131743
Totals 36600.00 0.00 38770.00 99.9

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6268-22-001
Proj ID RMC - 626822001
Work Type ROADSIDE MOWING
 
225.457 182070.20 91035.10 91035.10 50.0
Work Order 05-05-14
Work Began 00-00-00
Work Completed  
Time Computed 05-13-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 5
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141712
Totals 182070.20 91035.10 91035.10 50.0

CountyFREESTONE
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6268-23-001
Proj ID RMC - 626823001
Work Type ROADSIDE MOWING
 
340.700 154649.60 0.00 95356.80 61.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-19-14
Work Began 05-19-14
Work Completed  
Time Computed 05-28-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 28
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141706
Totals 154649.60 0.00 95356.80 61.6

CountyLEON
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6268-24-001
Proj ID RMC - 626824001
Work Type ROADSIDE MOWING
 
350.900 157368.80 0.00 0.00 0.0
Work Order 05-27-14
Work Began 00-00-00
Work Completed  
Time Computed 06-04-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 18
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6268-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141707
Totals 157368.80 0.00 0.00 0.0

CountyMADISON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6268-25-001
Proj ID RMC - 626825001
Work Type ROADSIDE MOWING
 
239.000 99520.85 0.00 41510.05 41.7
Work Order 06-02-14
Work Began 00-00-00
Work Completed  
Time Computed 06-10-14
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 28
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141708
Totals 99520.85 0.00 41510.05 41.7

CountyMILAM
Highway FM0486
From VARIOUS
To VARIOUS
CSJ 6268-26-001
Proj ID RMC - 626826001
Work Type ROADSIDE MOWING
 
333.935 132590.83 43599.30 43599.30 32.8
Work Order 06-24-14
Work Began 00-00-00
Work Completed  
Time Computed 06-13-14
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 45
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141709
Totals 132590.83 43599.30 43599.30 32.8