Monthly Local Let Maintenance Report For Bryan District As Of Mar 13, 2017 Page 3 Of 4

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-34-001
Proj IDRMC - 630834001
Work TypeROADSIDE MOWING
 
288.315147689.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161707
Totals147689.390.000.000.0

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6308-35-001
Proj IDRMC - 630835001
Work TypeROADSIDE MOWING
 
263.500127274.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161708
Totals127274.220.000.000.0

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-36-001
Proj IDRMC - 630836001
Work TypeROADSIDE MOWING
 
220.40097648.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161709
Totals97648.480.000.000.0

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-37-001
Proj IDRMC - 630837001
Work TypeROADSIDE MOWING
 
278.600167318.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161710
Totals167318.520.000.000.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-55-001
Proj IDSUP - 630855001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010114516.8854528.6047.6
Work Order08-24-16
Work Began08-18-16
Work Completed
Time Computed08-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged195
Percent Time Used53
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161730
Totals114516.884741.6254528.6047.6

CountyLEON
HighwayUS0079
FromON US79
ToAT INTERSECTION WITH FM542
CSJ6308-75-001
Proj IDRMC - 630875001
Work TypeSIGNAL AND ILLUMINATION WORK
 
0.05082485.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-28-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171701
Totals82485.000.000.000.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6309-22-001
Proj IDSUP - 630922001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00141135.0019007.8846.2
Work Order08-30-16
Work Began09-02-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161731
Totals41135.002726.7219007.8846.2

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6309-23-001
Proj IDSUP - 630923001
Work TypePICNIC AREA & WEIGH STATION MAINTENANCE
 
0.01025508.7411473.5644.9
Work Order09-06-16
Work Began09-02-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged179
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6309-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161732
Totals25508.741882.8211473.5644.9

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6309-24-001
Proj IDSUP - 630924001
Work TypeBUILDING JANITORIAL
 
0.00118242.528647.9247.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-16
Work Began09-03-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged179
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6309-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161733
Totals18242.520.008647.9247.4

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6309-25-001
Proj IDSUP - 630925001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.01072981.0032436.0044.4
Work Order09-13-16
Work Began09-13-16
Work Completed
Time Computed09-13-16
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161734
Totals72981.003243.6032436.0044.4

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6309-26-001
Proj IDSUP - 630926001
Work TypePICNIC/CAR POOL MAINT IN BURLESON COUNTY
 
0.00132332.3214887.4646.0
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161735
Totals32332.322123.3614887.4646.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6309-27-001
Proj IDSUP - 630927001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.00138028.2417635.0446.3
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161736
Totals38028.242764.4817635.0446.3

CountyLEON
HighwayUS0079
FromSH 7
ToIH 45
CSJ6310-79-001
Proj IDRMC - 631079001
Work TypeTREE TRIMMING
 
18.900119510.00165157.0099.9
Work Order12-27-16
Work Began12-27-16
Work Completed
Time Computed12-27-16
Contract Working Days38
Addl Days Granted21
Working Days Charged32
Percent Time Used54
Contractor(s)
KENT PHILLIPS PUMPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161701
Totals119510.00110507.00165157.0099.9

CountyFREESTONE
HighwayFM0488
FromAT RICHLAND CREEK
ToAT RICHLAND CREEK
CSJ6310-85-001
Proj IDBPM - 631085001
Work TypeBRIDGE JOINT REPAIR
 
0.303267641.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161712
Totals267641.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6310-91-001
Proj IDRMC - 631091001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001194000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged28
Percent Time Used3
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161711
Totals194000.000.000.000.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6311-88-001
Proj IDSUP - 631188001
Work TypePICNIC AREA MAINTENANCE
 
0.00121475.006035.0028.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-04-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161705
Totals21475.000.006035.0028.1

CountyWASHINGTON
HighwayFM0389
FromVARIOUS
ToVARIOUS
CSJ6311-90-001
Proj IDRMC - 631190001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001224006.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161714
Totals224006.000.000.000.0

CountyMADISON
HighwaySH0090
FromVARIOUS
ToVARIOUS
CSJ6311-91-001
Proj IDRMC - 631191001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001158724.0034286.8021.6
Work Order02-09-17
Work Began02-15-17
Work Completed
Time Computed02-17-17
Contract Working Days25
Addl Days Granted0
Working Days Charged9
Percent Time Used36
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161713
Totals158724.0034286.8034286.8021.6

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6312-70-001
Proj IDSUP - 631270001
Work TypeLITTER PICKUP
 
0.010116769.6212880.7611.0
Work Order01-03-17
Work Began12-14-16
Work Completed
Time Computed12-20-16
Contract Working Days365
Addl Days Granted0
Working Days Charged77
Percent Time Used21
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161715
Totals116769.6212880.7612880.7611.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-71-001
Proj IDSUP - 631271001
Work TypeLITTER PICKUP
 
0.010395432.4058027.3014.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged77
Percent Time Used21
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161716
Totals395432.400.0058027.3014.6