| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | FREESTONE |
| Highway |
IH0045 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6181-44-001 |
| Proj ID |
RMC - 618144001 |
| Work Type |
PICNIC AREA MAINTENANCE |
| |
|
0.100 |
30120.00 |
0.00 |
7680.00 |
32.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-01-08 |
| Work Began |
08-01-08 |
| Work Completed |
|
| Time Computed |
08-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
33 |
| Contractor(s) |
| FRONTIER PEST CONTROL CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6181-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081703 |
|
Totals |
30120.00 |
0.00 |
7680.00 |
32.4 |
|
| County | LEON |
| Highway |
IH0045 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6181-45-001 |
| Proj ID |
RMC - 618145001 |
| Work Type |
PICNIC AREA & WEIGH STATION MAINTENANCE |
| |
|
0.100 |
43440.00 |
2880.00 |
13720.00 |
31.5 |
| Work Order |
08-01-08 |
| Work Began |
08-01-08 |
| Work Completed |
|
| Time Computed |
08-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
33 |
| Contractor(s) |
| BLANKENSHIP CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 6181-45-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081704 |
|
Totals |
43440.00 |
2880.00 |
13720.00 |
31.5 |
|
| County | ROBERTSON |
| Highway |
SH0006 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6182-18-001 |
| Proj ID |
SUP - 618218001 |
| Work Type |
PICNIC AREA MAINTENANCE |
| |
|
0.010 |
18313.16 |
1245.32 |
6840.60 |
37.3 |
| Work Order |
07-15-08 |
| Work Began |
07-15-08 |
| Work Completed |
|
| Time Computed |
07-15-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
139 |
| Percent Time Used |
38 |
| Contractor(s) |
TIBH INDUSTRIES, INC. JUNCTION FIVE-O-FIVE |
SUBCONTRACTOR(S) FOR CCSJ: 6182-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081713 |
|
Totals |
18313.16 |
1245.32 |
6840.60 |
37.3 |
|
| County | MILAM |
| Highway |
FM0485 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6182-48-001 |
| Proj ID |
SUP - 618248001 |
| Work Type |
DELINEATOR |
| |
|
0.010 |
27510.00 |
0.00 |
10650.00 |
38.7 |
| Work Order |
07-03-08 |
| Work Began |
07-07-08 |
| Work Completed |
|
| Time Computed |
07-07-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
147 |
| Percent Time Used |
40 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6182-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
06081713 |
|
Totals |
27510.00 |
0.00 |
10650.00 |
38.7 |
|
| County | FREESTONE |
| Highway |
SH0075 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6182-73-001 |
| Proj ID |
RMC - 618273001 |
| Work Type |
TREE REMOVAL |
| |
|
0.100 |
79500.00 |
0.00 |
0.00 |
72.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-17-08 |
| Work Began |
11-17-08 |
| Work Completed |
|
| Time Computed |
11-17-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
7 |
| Percent Time Used |
1 |
| Contractor(s) |
| K & R CONTRACTORS |
SUBCONTRACTOR(S) FOR CCSJ: 6182-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08081701 |
|
Totals |
79500.00 |
0.00 |
0.00 |
72.9 |
|
| County | WASHINGTON |
| Highway |
US0290 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6182-98-001 |
| Proj ID |
RMC - 618298001 |
| Work Type |
TREE REMOVAL |
| |
|
0.010 |
45272.00 |
0.00 |
42617.00 |
94.1 |
| Work Order |
09-09-08 |
| Work Began |
09-09-08 |
| Work Completed |
|
| Time Computed |
09-16-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
76 |
| Percent Time Used |
20 |
| Contractor(s) |
| CASTANON LANDSCAPING |
SUBCONTRACTOR(S) FOR CCSJ: 6182-98-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08081702 |
|
Totals |
45272.00 |
0.00 |
42617.00 |
94.1 |
|
| County | LEON |
| Highway |
IH0045 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6182-99-001 |
| Proj ID |
RMC - 618299001 |
| Work Type |
TREE REMOVAL |
| |
|
0.010 |
39327.00 |
6813.50 |
19992.50 |
50.8 |
| Work Order |
09-24-08 |
| Work Began |
10-01-08 |
| Work Completed |
|
| Time Computed |
10-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
61 |
| Percent Time Used |
16 |
| Contractor(s) |
| CASTANON LANDSCAPING |
SUBCONTRACTOR(S) FOR CCSJ: 6182-99-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08081703 |
|
Totals |
39327.00 |
6813.50 |
19992.50 |
50.8 |
|
| County | BRAZOS |
| Highway |
US0190 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-00-001 |
| Proj ID |
RMC - 618300001 |
| Work Type |
SPOT PAINT & BEAD STRIPING |
| |
|
0.010 |
224300.00 |
11329.74 |
119921.10 |
53.4 |
| Work Order |
09-04-08 |
| Work Began |
09-15-08 |
| Work Completed |
|
| Time Computed |
09-10-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
22 |
| Contractor(s) |
| HIGHWAY TECHNOLOGIES, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-00-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08081704 |
|
Totals |
224300.00 |
11329.74 |
119921.10 |
53.4 |
|
| County | LEON |
| Highway |
SH0075 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-01-001 |
| Proj ID |
RMC - 618301001 |
| Work Type |
GUARD FENCE REPAIR |
| |
|
0.010 |
144670.00 |
6680.00 |
6680.00 |
4.6 |
| Work Order |
11-10-08 |
| Work Began |
11-10-08 |
| Work Completed |
|
| Time Computed |
11-17-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
14 |
| Percent Time Used |
3 |
| Contractor(s) |
| MERKEL CONSTRUCTION CO INC |
SUBCONTRACTOR(S) FOR CCSJ: 6183-01-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10081705 |
|
Totals |
144670.00 |
6680.00 |
6680.00 |
4.6 |
|
| County | FREESTONE |
| Highway |
SH0075 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-02-001 |
| Proj ID |
RMC - 618302001 |
| Work Type |
CLEANING AND SEALING CRACKS |
| |
|
0.010 |
158788.63 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
36 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| D & M CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6183-02-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10081708 |
|
Totals |
158788.63 |
0.00 |
0.00 |
0.0 |
|
| County | MADISON |
| Highway |
US0190 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-04-001 |
| Proj ID |
RMC - 618304001 |
| Work Type |
TREE REMOVAL |
| |
|
0.010 |
38375.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-24-08 |
| Work Began |
12-01-08 |
| Work Completed |
|
| Time Computed |
12-01-08 |
| Contract Working Days |
316 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CASTANON LANDSCAPING |
SUBCONTRACTOR(S) FOR CCSJ: 6183-04-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09081708 |
|
Totals |
38375.00 |
0.00 |
0.00 |
0.0 |
|
| County | FREESTONE |
| Highway |
IH0045 |
| From |
NAVARRO C/L |
| To |
LEON C/L |
| CSJ |
6183-06-001 |
| Proj ID |
SUP - 618306001 |
| Work Type |
REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES |
| |
|
0.010 |
42984.00 |
0.00 |
11462.40 |
33.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-29-08 |
| Work Began |
08-01-08 |
| Work Completed |
|
| Time Computed |
08-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
33 |
| Contractor(s) |
TIBH INDUSTRIES, INC. D & D HELPING OTHERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-06-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081723 |
|
Totals |
42984.00 |
0.00 |
11462.40 |
33.3 |
|
| County | LEON |
| Highway |
IH0045 |
| From |
FREESTONE C/L |
| To |
MADISON C/L |
| CSJ |
6183-07-001 |
| Proj ID |
SUP - 618307001 |
| Work Type |
REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES |
| |
|
0.010 |
38954.25 |
3462.60 |
13850.40 |
35.5 |
| Work Order |
08-01-08 |
| Work Began |
08-01-08 |
| Work Completed |
|
| Time Computed |
08-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
33 |
| Contractor(s) |
TIBH INDUSTRIES, INC. D & D HELPING OTHERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-07-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081733 |
|
Totals |
38954.25 |
3462.60 |
13850.40 |
35.5 |
|
| County | MADISON |
| Highway |
IH0045 |
| From |
LEON C/L |
| To |
WALKER C/L |
| CSJ |
6183-08-001 |
| Proj ID |
SUP - 618308001 |
| Work Type |
REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES |
| |
|
0.010 |
25521.75 |
0.00 |
6805.80 |
35.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-01-08 |
| Work Began |
08-01-08 |
| Work Completed |
|
| Time Computed |
08-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
33 |
| Contractor(s) |
TIBH INDUSTRIES, INC. D & D HELPING OTHERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-08-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081743 |
|
Totals |
25521.75 |
0.00 |
6805.80 |
35.5 |
|
| County | WALKER |
| Highway |
IH0045 |
| From |
MONTGOMERY C/L |
| To |
MADISON C/L |
| CSJ |
6183-09-001 |
| Proj ID |
SUP - 618309001 |
| Work Type |
REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES |
| |
|
0.010 |
44327.25 |
3940.20 |
15760.80 |
35.5 |
| Work Order |
07-31-08 |
| Work Began |
08-01-08 |
| Work Completed |
|
| Time Computed |
08-01-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
33 |
| Contractor(s) |
TIBH INDUSTRIES, INC. D & D HELPING OTHERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081753 |
|
Totals |
44327.25 |
3940.20 |
15760.80 |
35.5 |
|
| County | BRAZOS |
| Highway |
SH0006 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-19-001 |
| Proj ID |
SUP - 618319001 |
| Work Type |
LITTER PICKUP |
| |
|
0.010 |
185024.16 |
8392.32 |
63879.84 |
34.5 |
| Work Order |
07-24-08 |
| Work Began |
07-24-08 |
| Work Completed |
|
| Time Computed |
07-24-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
130 |
| Percent Time Used |
35 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081756 |
|
Totals |
185024.16 |
8392.32 |
63879.84 |
34.5 |
|
| County | BURLESON |
| Highway |
SH0021 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-20-001 |
| Proj ID |
SUP - 618320001 |
| Work Type |
LITTER PICKUP |
| |
|
0.010 |
96373.56 |
0.00 |
45936.78 |
47.6 |
| Work Order |
07-24-08 |
| Work Began |
07-24-08 |
| Work Completed |
|
| Time Computed |
07-24-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
130 |
| Percent Time Used |
35 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-20-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081761 |
|
Totals |
96373.56 |
0.00 |
45936.78 |
47.6 |
|
| County | FREESTONE |
| Highway |
IH0045 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-21-001 |
| Proj ID |
SUP - 618321001 |
| Work Type |
LITTER PICKUP |
| |
|
0.010 |
188090.22 |
0.00 |
44939.73 |
27.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-23-08 |
| Work Began |
07-24-08 |
| Work Completed |
|
| Time Computed |
07-24-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
130 |
| Percent Time Used |
35 |
| Contractor(s) |
TIBH INDUSTRIES, INC. CEN-TEX ASSOCIATION FOR RETARDED CHILDREN |
SUBCONTRACTOR(S) FOR CCSJ: 6183-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081755 |
|
Totals |
188090.22 |
0.00 |
44939.73 |
27.0 |
|
| County | GRIMES |
| Highway |
SH0006 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-22-001 |
| Proj ID |
SUP - 618322001 |
| Work Type |
LITTER PICKUP |
| |
|
0.010 |
94939.39 |
0.00 |
32452.26 |
34.1 |
| Work Order |
07-23-08 |
| Work Began |
07-24-08 |
| Work Completed |
|
| Time Computed |
07-24-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
130 |
| Percent Time Used |
35 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-22-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081762 |
|
Totals |
94939.39 |
0.00 |
32452.26 |
34.1 |
|
| County | MADISON |
| Highway |
SH0075 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6183-24-001 |
| Proj ID |
SUP - 618324001 |
| Work Type |
LITTER PICKUP |
| |
|
0.010 |
99201.45 |
34082.30 |
34082.30 |
34.3 |
| Work Order |
07-22-08 |
| Work Began |
07-24-08 |
| Work Completed |
|
| Time Computed |
07-24-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
130 |
| Percent Time Used |
35 |
| Contractor(s) |
TIBH INDUSTRIES, INC. RUCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6183-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07081758 |
|
Totals |
99201.45 |
34082.30 |
34082.30 |
34.3 |
|