Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6181-44-001
Proj ID RMC - 618144001
Work Type PICNIC AREA MAINTENANCE
 
0.100 30120.00 0.00 7680.00 32.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
FRONTIER PEST CONTROL CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6181-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081703
Totals 30120.00 0.00 7680.00 32.4

CountyLEON
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6181-45-001
Proj ID RMC - 618145001
Work Type PICNIC AREA & WEIGH STATION MAINTENANCE
 
0.100 43440.00 2880.00 13720.00 31.5
Work Order 08-01-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
BLANKENSHIP CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6181-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081704
Totals 43440.00 2880.00 13720.00 31.5

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6182-18-001
Proj ID SUP - 618218001
Work Type PICNIC AREA MAINTENANCE
 
0.010 18313.16 1245.32 6840.60 37.3
Work Order 07-15-08
Work Began 07-15-08
Work Completed  
Time Computed 07-15-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 38
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6182-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081713
Totals 18313.16 1245.32 6840.60 37.3

CountyMILAM
Highway FM0485
From VARIOUS
To VARIOUS
CSJ 6182-48-001
Proj ID SUP - 618248001
Work Type DELINEATOR
 
0.010 27510.00 0.00 10650.00 38.7
Work Order 07-03-08
Work Began 07-07-08
Work Completed  
Time Computed 07-07-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 40
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6182-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06081713
Totals 27510.00 0.00 10650.00 38.7

CountyFREESTONE
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6182-73-001
Proj ID RMC - 618273001
Work Type TREE REMOVAL
 
0.100 79500.00 0.00 0.00 72.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-17-08
Work Began 11-17-08
Work Completed  
Time Computed 11-17-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 1
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6182-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08081701
Totals 79500.00 0.00 0.00 72.9

CountyWASHINGTON
Highway US0290
From VARIOUS
To VARIOUS
CSJ 6182-98-001
Proj ID RMC - 618298001
Work Type TREE REMOVAL
 
0.010 45272.00 0.00 42617.00 94.1
Work Order 09-09-08
Work Began 09-09-08
Work Completed  
Time Computed 09-16-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 20
Contractor(s)
CASTANON LANDSCAPING
SUBCONTRACTOR(S) FOR CCSJ: 6182-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08081702
Totals 45272.00 0.00 42617.00 94.1

CountyLEON
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6182-99-001
Proj ID RMC - 618299001
Work Type TREE REMOVAL
 
0.010 39327.00 6813.50 19992.50 50.8
Work Order 09-24-08
Work Began 10-01-08
Work Completed  
Time Computed 10-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
CASTANON LANDSCAPING
SUBCONTRACTOR(S) FOR CCSJ: 6182-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08081703
Totals 39327.00 6813.50 19992.50 50.8

CountyBRAZOS
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6183-00-001
Proj ID RMC - 618300001
Work Type SPOT PAINT & BEAD STRIPING
 
0.010 224300.00 11329.74 119921.10 53.4
Work Order 09-04-08
Work Began 09-15-08
Work Completed  
Time Computed 09-10-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 22
Contractor(s)
HIGHWAY TECHNOLOGIES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6183-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08081704
Totals 224300.00 11329.74 119921.10 53.4

CountyLEON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6183-01-001
Proj ID RMC - 618301001
Work Type GUARD FENCE REPAIR
 
0.010 144670.00 6680.00 6680.00 4.6
Work Order 11-10-08
Work Began 11-10-08
Work Completed  
Time Computed 11-17-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 3
Contractor(s)
MERKEL CONSTRUCTION CO INC
SUBCONTRACTOR(S) FOR CCSJ: 6183-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10081705
Totals 144670.00 6680.00 6680.00 4.6

CountyFREESTONE
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6183-02-001
Proj ID RMC - 618302001
Work Type CLEANING AND SEALING CRACKS
 
0.010 158788.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6183-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10081708
Totals 158788.63 0.00 0.00 0.0

CountyMADISON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6183-04-001
Proj ID RMC - 618304001
Work Type TREE REMOVAL
 
0.010 38375.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-08
Work Began 12-01-08
Work Completed  
Time Computed 12-01-08
Contract Working Days 316
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CASTANON LANDSCAPING
SUBCONTRACTOR(S) FOR CCSJ: 6183-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09081708
Totals 38375.00 0.00 0.00 0.0

CountyFREESTONE
Highway IH0045
From NAVARRO C/L
To LEON C/L
CSJ 6183-06-001
Proj ID SUP - 618306001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 42984.00 0.00 11462.40 33.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081723
Totals 42984.00 0.00 11462.40 33.3

CountyLEON
Highway IH0045
From FREESTONE C/L
To MADISON C/L
CSJ 6183-07-001
Proj ID SUP - 618307001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 38954.25 3462.60 13850.40 35.5
Work Order 08-01-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081733
Totals 38954.25 3462.60 13850.40 35.5

CountyMADISON
Highway IH0045
From LEON C/L
To WALKER C/L
CSJ 6183-08-001
Proj ID SUP - 618308001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 25521.75 0.00 6805.80 35.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081743
Totals 25521.75 0.00 6805.80 35.5

CountyWALKER
Highway IH0045
From MONTGOMERY C/L
To MADISON C/L
CSJ 6183-09-001
Proj ID SUP - 618309001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 44327.25 3940.20 15760.80 35.5
Work Order 07-31-08
Work Began 08-01-08
Work Completed  
Time Computed 08-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
TIBH INDUSTRIES, INC.
D & D HELPING OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081753
Totals 44327.25 3940.20 15760.80 35.5

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6183-19-001
Proj ID SUP - 618319001
Work Type LITTER PICKUP
 
0.010 185024.16 8392.32 63879.84 34.5
Work Order 07-24-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 35
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081756
Totals 185024.16 8392.32 63879.84 34.5

CountyBURLESON
Highway SH0021
From VARIOUS
To VARIOUS
CSJ 6183-20-001
Proj ID SUP - 618320001
Work Type LITTER PICKUP
 
0.010 96373.56 0.00 45936.78 47.6
Work Order 07-24-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 35
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081761
Totals 96373.56 0.00 45936.78 47.6

CountyFREESTONE
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6183-21-001
Proj ID SUP - 618321001
Work Type LITTER PICKUP
 
0.010 188090.22 0.00 44939.73 27.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-23-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 35
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6183-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081755
Totals 188090.22 0.00 44939.73 27.0

CountyGRIMES
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6183-22-001
Proj ID SUP - 618322001
Work Type LITTER PICKUP
 
0.010 94939.39 0.00 32452.26 34.1
Work Order 07-23-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 35
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081762
Totals 94939.39 0.00 32452.26 34.1

CountyMADISON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6183-24-001
Proj ID SUP - 618324001
Work Type LITTER PICKUP
 
0.010 99201.45 34082.30 34082.30 34.3
Work Order 07-22-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 35
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07081758
Totals 99201.45 34082.30 34082.30 34.3