Monthly Local Let Maintenance Report For Bryan District As Of Oct 16, 2017 Page 2 Of 4

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6308-35-001
Proj IDRMC - 630835001
Work TypeROADSIDE MOWING
 
263.500127274.2253703.5442.1
Work Order06-01-17
Work Began05-24-17
Work Completed
Time Computed06-09-17
Contract Working Days43
Addl Days Granted0
Working Days Charged12
Percent Time Used27
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161708
Totals127274.220.0053703.5442.1

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-36-001
Proj IDRMC - 630836001
Work TypeROADSIDE MOWING
 
220.40097648.4843403.4844.4
Work Order05-24-17
Work Began05-24-17
Work Completed
Time Computed06-01-17
Contract Working Days35
Addl Days Granted0
Working Days Charged12
Percent Time Used34
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161709
Totals97648.480.0043403.4844.4

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-37-001
Proj IDRMC - 630837001
Work TypeROADSIDE MOWING
 
278.600167318.5272917.9643.5
Work Order05-30-17
Work Began05-10-17
Work Completed
Time Computed06-08-17
Contract Working Days44
Addl Days Granted0
Working Days Charged10
Percent Time Used22
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161710
Totals167318.520.0072917.9643.5

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-55-001
Proj IDSUP - 630855001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010114516.88109057.62100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-16
Work Began08-18-16
Work Completed09-30-17
Time Computed08-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged373
Percent Time Used102
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161730
Totals114516.880.00109057.62100.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6309-23-001
Proj IDSUP - 630923001
Work TypePICNIC AREA & WEIGH STATION MAINTENANCE
 
0.01025508.7423332.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-16
Work Began09-02-16
Work Completed09-01-17
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6309-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161732
Totals25508.740.0023332.41100.0

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6309-25-001
Proj IDSUP - 630925001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.01072981.0071359.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-13-16
Work Began09-13-16
Work Completed09-30-17
Time Computed09-13-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161734
Totals72981.000.0071359.20100.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6309-27-001
Proj IDSUP - 630927001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.00138028.2436269.16100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-02-16
Work Began09-02-16
Work Completed08-31-17
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged363
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161736
Totals38028.240.0036269.16100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6310-91-001
Proj IDRMC - 631091001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001194000.0045380.0023.3
Work Order04-10-17
Work Began02-01-17
Work Completed
Time Computed04-18-17
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161711
Totals194000.000.0045380.0023.3

CountyROBERTSON
HighwaySH0007
From@ NAVASOTA RIVER RELIEF STRUCTURE 1
To@ NAVASOTA RIVER RELIEF STRUCTURE 2
CSJ6311-25-001
Proj IDBPM - 631125001
Work TypeREPAIR OF CORRODED STEEL PILES
 
0.248226520.00227457.0099.9
Work Order06-27-17
Work Began06-20-17
Work Completed
Time Computed07-05-17
Contract Working Days17
Addl Days Granted0
Working Days Charged14
Percent Time Used82
Contractor(s)
PBX BRIDGE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6311-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171701
Totals226520.000.00227457.0099.9

CountyLEON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6311-27-001
Proj IDBPM - 631127001
Work TypeRIP RAP PLACEMENT AS SCOUR COUNTERMEASUR
 
0.00156555.0037300.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-08-17
Work Completed09-15-17
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged9
Percent Time Used45
Contractor(s)
TEXCAVATION COMPANY LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171702
Totals56555.000.0037300.00100.0

CountyBRAZOS
HighwayUS0190
FromON US 190/SH 21
ToAT INTERSECTION WITH FM 2776/ANDERT RD
CSJ6311-40-001
Proj IDRMC - 631140001
Work TypeINSTALLATION OF HIGHWAY TRAFFIC SIGNALS
 
0.001218890.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171701
Totals218890.160.000.000.0

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6311-88-001
Proj IDSUP - 631188001
Work TypePICNIC AREA MAINTENANCE
 
0.00121475.0018067.5084.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-04-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged331
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161705
Totals21475.001522.5018067.5084.1

CountyWASHINGTON
HighwayFM0389
FromVARIOUS
ToVARIOUS
CSJ6311-90-001
Proj IDRMC - 631190001
Work TypeCHANNEL AND SCOUR REPAIR
 
0.001224006.00259865.1399.9
Work Order03-29-17
Work Began03-29-17
Work Completed
Time Computed03-29-17
Contract Working Days35
Addl Days Granted0
Working Days Charged35
Percent Time Used100
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161714
Totals224006.000.00259865.1399.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-27-001
Proj IDRMC - 631227001
Work TypeINSTALL SHORTLINE AND SPECIALTY MARKINGS
 
0.001227312.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171703
Totals227312.500.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6312-28-001
Proj IDRMC - 631228001
Work TypeINSTALL SHORTLINE AND SPECIALTY MARKINGS
 
0.001227312.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171702
Totals227312.500.000.000.0

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6312-29-001
Proj IDRMC - 631229001
Work TypeINSTALL SHORTLINE AND SPECIALTY MARKINGS
 
0.001227312.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171701
Totals227312.500.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-71-001
Proj IDSUP - 631271001
Work TypeLITTER PICKUP
 
0.010395432.40251953.02100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-14-16
Work Completed09-26-17
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged260
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161716
Totals395432.400.00251953.02100.0

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6312-72-001
Proj IDSUP - 631272001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.010124173.4277424.73100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-17
Work Began12-14-16
Work Completed09-30-17
Time Computed01-25-17
Contract Working Days365
Addl Days Granted0
Working Days Charged260
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161717
Totals124173.420.0077424.73100.0

CountyBURLESON
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6312-73-001
Proj IDSUP - 631273001
Work TypeLITTER PICKUP
 
0.010106366.6263644.84100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-16
Work Began12-14-16
Work Completed09-26-17
Time Computed12-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged255
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161718
Totals106366.620.0063644.84100.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-76-001
Proj IDSUP - 631276001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.010120266.6657883.33100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-03-17
Work Began12-14-16
Work Completed09-26-17
Time Computed01-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged255
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161721
Totals120266.660.0057883.33100.0

page 1 | page 2 | page 3 | page 4