Monthly Local Let Maintenance Report For Bryan District As Of Aug 11, 2017 Page 2 Of 4

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6308-28-001
Proj IDRMC - 630828001
Work TypeROADSIDE MOWING
 
256.700138446.0054916.0039.6
Work Order05-31-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days45
Addl Days Granted0
Working Days Charged20
Percent Time Used44
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161701
Totals138446.0050230.0054916.0039.6

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-29-001
Proj IDRMC - 630829001
Work TypeROADSIDE MOWING
 
225.457258650.76126142.4048.7
Work Order02-09-17
Work Began02-07-17
Work Completed
Time Computed02-13-17
Contract Working Days70
Addl Days Granted0
Working Days Charged19
Percent Time Used27
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161702
Totals258650.761118.88126142.4048.7

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6308-30-001
Proj IDRMC - 630830001
Work TypeROADSIDE MOWING
 
302.900174929.8870358.3640.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-17
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged8
Percent Time Used16
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161703
Totals174929.889851.5670358.3640.2

CountyBURLESON
HighwayFM0060
FromVARIOUS
ToVARIOUS
CSJ6308-31-001
Proj IDRMC - 630831001
Work TypeROADSIDE MOWING
 
233.630128994.2556586.7043.8
Work Order06-01-17
Work Began05-24-17
Work Completed
Time Computed06-09-17
Contract Working Days41
Addl Days Granted0
Working Days Charged17
Percent Time Used41
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161704
Totals128994.2518813.2056586.7043.8

CountyMILAM
HighwayFM0486
FromVARIOUS
ToVARIOUS
CSJ6308-32-001
Proj IDRMC - 630832001
Work TypeROADSIDE MOWING
 
333.935206653.0583186.9740.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-03-17
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged15
Percent Time Used27
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161705
Totals206653.0583186.9783186.9740.2

CountyFREESTONE
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6308-33-001
Proj IDRMC - 630833001
Work TypeROADSIDE MOWING
 
297.500143162.4560137.5042.0
Work Order03-29-17
Work Began03-29-17
Work Completed
Time Computed04-06-17
Contract Working Days48
Addl Days Granted0
Working Days Charged19
Percent Time Used39
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161706
Totals143162.450.0060137.5042.0

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-34-001
Proj IDRMC - 630834001
Work TypeROADSIDE MOWING
 
288.315147689.3941631.9728.1
Work Order04-12-17
Work Began04-12-17
Work Completed
Time Computed04-12-17
Contract Working Days49
Addl Days Granted0
Working Days Charged28
Percent Time Used57
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161707
Totals147689.3934689.9341631.9728.1

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6308-35-001
Proj IDRMC - 630835001
Work TypeROADSIDE MOWING
 
263.500127274.2253703.5442.1
Work Order06-01-17
Work Began05-24-17
Work Completed
Time Computed06-09-17
Contract Working Days43
Addl Days Granted0
Working Days Charged12
Percent Time Used27
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161708
Totals127274.220.0053703.5442.1

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-36-001
Proj IDRMC - 630836001
Work TypeROADSIDE MOWING
 
220.40097648.4843403.4844.4
Work Order05-24-17
Work Began05-24-17
Work Completed
Time Computed06-01-17
Contract Working Days35
Addl Days Granted0
Working Days Charged12
Percent Time Used34
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161709
Totals97648.480.0043403.4844.4

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-37-001
Proj IDRMC - 630837001
Work TypeROADSIDE MOWING
 
278.600167318.5272917.9643.5
Work Order05-30-17
Work Began05-10-17
Work Completed
Time Computed06-08-17
Contract Working Days44
Addl Days Granted0
Working Days Charged5
Percent Time Used11
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161710
Totals167318.520.0072917.9643.5

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-55-001
Proj IDSUP - 630855001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010114516.8899574.3986.9
Work Order08-24-16
Work Began08-18-16
Work Completed
Time Computed08-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161730
Totals114516.889483.2399574.3986.9

CountyLEON
HighwayUS0079
FromON US79
ToAT INTERSECTION WITH FM542
CSJ6308-75-001
Proj IDRMC - 630875001
Work TypeSIGNAL AND ILLUMINATION WORK
 
0.05082485.0064105.0080.4
Work Order02-28-17
Work Began04-27-17
Work Completed
Time Computed05-01-17
Contract Working Days34
Addl Days Granted0
Working Days Charged38
Percent Time Used111
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171701
Totals82485.000.0064105.0080.4

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6309-22-001
Proj IDSUP - 630922001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00141135.0036848.6689.5
Work Order08-30-16
Work Began09-02-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged333
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161731
Totals41135.003473.8236848.6689.5

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6309-23-001
Proj IDSUP - 630923001
Work TypePICNIC AREA & WEIGH STATION MAINTENANCE
 
0.01025508.7421588.9284.6
Work Order09-06-16
Work Began09-02-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged332
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6309-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161732
Totals25508.741821.3221588.9284.6

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6309-24-001
Proj IDSUP - 630924001
Work TypeBUILDING JANITORIAL
 
0.00118242.5216033.6087.8
Work Order09-06-16
Work Began09-03-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged332
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6309-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161733
Totals18242.521104.4616033.6087.8

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6309-25-001
Proj IDSUP - 630925001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.01072981.0064872.0088.8
Work Order09-13-16
Work Began09-13-16
Work Completed
Time Computed09-13-16
Contract Working Days365
Addl Days Granted0
Working Days Charged333
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161734
Totals72981.008109.0064872.0088.8

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6309-26-001
Proj IDSUP - 630926001
Work TypePICNIC/CAR POOL MAINT IN BURLESON COUNTY
 
0.00132332.3228592.5088.4
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged333
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161735
Totals32332.322388.7828592.5088.4

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6309-27-001
Proj IDSUP - 630927001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.00138028.2433504.6888.1
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged333
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161736
Totals38028.243169.0233504.6888.1

CountyFREESTONE
HighwayFM0488
FromAT RICHLAND CREEK
ToAT RICHLAND CREEK
CSJ6310-85-001
Proj IDBPM - 631085001
Work TypeBRIDGE JOINT REPAIR
 
0.303267641.00321986.75100.0
Work Order04-03-17
Work Began04-03-17
Work Completed08-09-17
Time Computed04-11-17
Contract Working Days32
Addl Days Granted0
Working Days Charged20
Percent Time Used62
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161712
Totals267641.0059748.35321986.75100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6310-91-001
Proj IDRMC - 631091001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001194000.0045380.0023.3
Work Order04-10-17
Work Began02-01-17
Work Completed
Time Computed04-18-17
Contract Working Days730
Addl Days Granted0
Working Days Charged181
Percent Time Used24
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161711
Totals194000.000.0045380.0023.3