Monthly Local Let Maintenance Report For Bryan District As Of Apr 10, 2017 Page 2 Of 4

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6305-15-001
Proj IDRMC - 630515001
Work TypeINSTALLATION OF DRIVEWAY PIPE
 
0.001283259.00127229.2044.9
Work Order10-14-16
Work Began10-17-16
Work Completed
Time Computed10-17-16
Contract Working Days72
Addl Days Granted0
Working Days Charged31
Percent Time Used43
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161701
Totals283259.0044064.20127229.2044.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6305-45-001
Proj IDRMC - 630545001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.001199756.0025047.0012.5
Work Order01-12-17
Work Began01-12-17
Work Completed
Time Computed01-18-17
Contract Working Days120
Addl Days Granted0
Working Days Charged12
Percent Time Used10
Contractor(s)
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161703
Totals199756.008334.0025047.0012.5

CountyFREESTONE
HighwaySH0164
FromSH 164 AT MINE HAUL ROAD
ToSH 164 AT MINE HAUL ROAD
CSJ6305-49-001
Proj IDEMC - 630549001
Work TypeBRIDGE REPAIR
 
0.0011198951.501374987.9299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted6
Working Days Charged66
Percent Time Used100
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161740
Totals1198951.500.001374987.9299.9

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6306-59-001
Proj IDRMC - 630659001
Work TypeREPAIR OF METAL BEAM GUARD FENCE
 
0.001313405.0018261.005.8
Work Order12-22-16
Work Began12-22-16
Work Completed
Time Computed12-30-16
Contract Working Days730
Addl Days Granted0
Working Days Charged100
Percent Time Used13
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161704
Totals313405.008961.0018261.005.8

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6307-68-001
Proj IDSUP - 630768001
Work TypeTREE REMOVAL
 
0.00130219.0021311.5970.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-15-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged260
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161730
Totals30219.000.0021311.5970.5

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6307-73-001
Proj IDSUP - 630773001
Work TypeBUILDING JANITORIAL
 
0.00117219.3711741.9768.1
Work Order08-02-16
Work Began08-02-16
Work Completed
Time Computed08-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161732
Totals17219.371217.2011741.9768.1

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6307-74-001
Proj IDSUP - 630774001
Work TypePICNIC AREA MAINTENANCE
 
0.00134454.3221875.4863.4
Work Order08-01-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6307-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161733
Totals34454.323056.5221875.4863.4

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6308-28-001
Proj IDRMC - 630828001
Work TypeROADSIDE MOWING
 
256.700138446.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161701
Totals138446.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-29-001
Proj IDRMC - 630829001
Work TypeROADSIDE MOWING
 
225.457258650.7629065.2411.2
Work Order02-09-17
Work Began02-07-17
Work Completed
Time Computed02-13-17
Contract Working Days70
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161702
Totals258650.760.0029065.2411.2

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6308-30-001
Proj IDRMC - 630830001
Work TypeROADSIDE MOWING
 
302.900174929.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-17
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161703
Totals174929.880.000.000.0

CountyBURLESON
HighwayFM0060
FromVARIOUS
ToVARIOUS
CSJ6308-31-001
Proj IDRMC - 630831001
Work TypeROADSIDE MOWING
 
233.630128994.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days41
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161704
Totals128994.250.000.000.0

CountyMILAM
HighwayFM0486
FromVARIOUS
ToVARIOUS
CSJ6308-32-001
Proj IDRMC - 630832001
Work TypeROADSIDE MOWING
 
333.935206653.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161705
Totals206653.050.000.000.0

CountyFREESTONE
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6308-33-001
Proj IDRMC - 630833001
Work TypeROADSIDE MOWING
 
297.500143162.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-29-17
Work Began03-29-17
Work Completed
Time Computed04-06-17
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161706
Totals143162.450.000.000.0

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-34-001
Proj IDRMC - 630834001
Work TypeROADSIDE MOWING
 
288.315147689.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161707
Totals147689.390.000.000.0

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6308-35-001
Proj IDRMC - 630835001
Work TypeROADSIDE MOWING
 
263.500127274.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161708
Totals127274.220.000.000.0

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-36-001
Proj IDRMC - 630836001
Work TypeROADSIDE MOWING
 
220.40097648.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161709
Totals97648.480.000.000.0

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-37-001
Proj IDRMC - 630837001
Work TypeROADSIDE MOWING
 
278.600167318.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161710
Totals167318.520.000.000.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-55-001
Proj IDSUP - 630855001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010114516.8859270.2251.7
Work Order08-24-16
Work Began08-18-16
Work Completed
Time Computed08-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged226
Percent Time Used61
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161730
Totals114516.884741.6259270.2251.7

CountyLEON
HighwayUS0079
FromON US79
ToAT INTERSECTION WITH FM542
CSJ6308-75-001
Proj IDRMC - 630875001
Work TypeSIGNAL AND ILLUMINATION WORK
 
0.05082485.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-28-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171701
Totals82485.000.000.000.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6309-22-001
Proj IDSUP - 630922001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00141135.0022887.9655.6
Work Order08-30-16
Work Began09-02-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged211
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161731
Totals41135.003880.0822887.9655.6

page 1 | page 2 | page 3 | page 4