Monthly Local Let Maintenance Report For Bryan District As Of Dec 9, 2016 Page 2 Of 4

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFREESTONE
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6293-04-001
Proj ID RMC - 629304001
Work Type ROADSIDE MOWING
 
297.500 157085.87 0.00 133616.84 85.0
Work Order 06-08-16
Work Began 06-08-16
Work Completed  
Time Computed 06-16-16
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 67
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6293-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151706
Totals 157085.87 0.00 133616.84 85.0

CountyROBERTSON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6293-05-001
Proj ID RMC - 629305001
Work Type ROADSIDE MOWING
 
288.315 167840.44 0.00 140540.40 83.7
Work Order 05-24-16
Work Began 05-24-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 55
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6293-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151707
Totals 167840.44 0.00 140540.40 83.7

CountyGRIMES
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6293-08-001
Proj ID RMC - 629308001
Work Type ROADSIDE MOWING
 
278.600 137793.90 0.00 107573.16 78.0
Work Order 06-30-16
Work Began 06-30-16
Work Completed  
Time Computed 07-08-16
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 27
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6293-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12151710
Totals 137793.90 0.00 107573.16 78.0

CountyMILAM
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6297-37-001
Proj ID RMC - 629737001
Work Type PICNIC AREA MAINTENANCE
 
0.001 24875.00 2241.70 18879.47 75.8
Work Order 02-23-16
Work Began 02-23-16
Work Completed  
Time Computed 03-02-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 276
Percent Time Used 75
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01161701
Totals 24875.00 2241.70 18879.47 75.8

CountyWASHINGTON
Highway SH0105
From VARIOUS
To VARIOUS
CSJ 6297-80-001
Proj ID SUP - 629780001
Work Type LITTER PICKUP
 
0.010 114774.68 0.00 67782.00 59.0
Work Order 12-15-15
Work Began 12-15-15
Work Completed  
Time Computed 12-15-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151730
Totals 114774.68 0.00 67782.00 59.0

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6297-81-001
Proj ID SUP - 629781001
Work Type LITTER PICKUP
 
0.010 362632.36 25104.95 332479.34 91.6
Work Order 01-06-16
Work Began 12-11-15
Work Completed  
Time Computed 01-06-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 356
Percent Time Used 97
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151731
Totals 362632.36 25104.95 332479.34 91.6

CountyLEON
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6297-82-001
Proj ID SUP - 629782001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 122540.04 0.00 88530.03 72.2
Work Order 12-15-15
Work Began 12-15-15
Work Completed  
Time Computed 12-15-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151732
Totals 122540.04 0.00 88530.03 72.2

CountyBURLESON
Highway SH0021
From VARIOUS
To VARIOUS
CSJ 6297-83-001
Proj ID SUP - 629783001
Work Type LITTER PICKUP
 
0.010 99797.28 25450.94 99807.78 99.9
Work Order 12-15-15
Work Began 12-15-15
Work Completed  
Time Computed 12-15-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151733
Totals 99797.28 25450.94 99807.78 99.9

CountyMILAM
Highway US0077
From VARIOUS
To VARIOUS
CSJ 6297-84-001
Proj ID SUP - 629784001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 142813.23 12328.93 135549.38 94.9
Work Order 01-27-16
Work Began 12-15-15
Work Completed  
Time Computed 01-27-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151734
Totals 142813.23 12328.93 135549.38 94.9

CountyFREESTONE
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6297-85-001
Proj ID SUP - 629785001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 70433.96 27468.50 58629.54 83.2
Work Order 01-11-16
Work Began 12-15-15
Work Completed  
Time Computed 01-11-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151735
Totals 70433.96 27468.50 58629.54 83.2

CountyROBERTSON
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6297-86-001
Proj ID SUP - 629786001
Work Type LITTER PICKUP AND DISPOSAL
 
0.010 113641.47 0.00 85212.42 74.9
Work Order 12-16-15
Work Began 12-15-15
Work Completed  
Time Computed 12-16-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151736
Totals 113641.47 0.00 85212.42 74.9

CountyWALKER
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6297-87-001
Proj ID SUP - 629787001
Work Type LITTER PICKUP
 
0.010 110721.50 0.00 93404.16 84.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-16
Work Began 12-15-15
Work Completed  
Time Computed 10-20-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151737
Totals 110721.50 0.00 93404.16 84.3

CountyMADISON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6297-88-001
Proj ID SUP - 629788001
Work Type LITTER PICKUP
 
0.010 91278.32 0.00 54828.68 60.0
Work Order 01-07-16
Work Began 12-15-15
Work Completed  
Time Computed 01-07-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151738
Totals 91278.32 0.00 54828.68 60.0

CountyGRIMES
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6297-89-001
Proj ID SUP - 629789001
Work Type LITTER PICKUP
 
0.010 129614.14 30704.91 122822.22 100.0
Work Order 01-06-16
Work Began 12-15-15
Work Completed 11-30-16
Time Computed 01-07-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 352
Percent Time Used 96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11151739
Totals 129614.14 30704.91 122822.22 100.0

CountyBRAZOS
Highway SH0047
From SH 47 SB @ FM 1179
To SH 47 SB @ FM 1179
CSJ 6298-06-001
Proj ID BPM - 629806001
Work Type BRIDGE DECK REPAIR
 
0.001 19999.00 0.00 29599.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-20-16
Work Began 04-23-16
Work Completed 04-24-16
Time Computed 04-23-16
Contract Working Days 3
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 33
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03161703
Totals 19999.00 0.00 29599.00 100.0

CountyWALKER
Highway SH0030
From VARIOUS
To VARIOUS
CSJ 6299-04-001
Proj ID RMC - 629904001
Work Type SPOT PAVEMENT MARKINGS
 
0.001 211930.00 20546.20 121456.70 57.3
Work Order 04-04-16
Work Began 04-04-16
Work Completed  
Time Computed 04-08-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 237
Percent Time Used 32
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03161705
Totals 211930.00 20546.20 121456.70 57.3

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6299-26-001
Proj ID SUP - 629926001
Work Type DISTRICT COMPLEX BUILDING JANITORIAL
 
0.001 83312.16 5364.08 69804.17 83.7
Work Order 02-10-16
Work Began 02-01-16
Work Completed  
Time Computed 02-10-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01161730
Totals 83312.16 5364.08 69804.17 83.7

CountyWALKER
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6299-27-001
Proj ID SUP - 629927001
Work Type BUILDING JANITORIAL
 
0.010 20227.12 1673.82 15994.28 79.0
Work Order 02-08-16
Work Began 02-01-16
Work Completed  
Time Computed 02-08-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01161731
Totals 20227.12 1673.82 15994.28 79.0

CountyLEON
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6299-55-001
Proj ID SUP - 629955001
Work Type BUILDING JANITORIAL
 
0.010 12349.62 998.19 8761.89 70.9
Work Order 02-10-16
Work Began 02-10-16
Work Completed  
Time Computed 02-10-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 295
Percent Time Used 80
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01161732
Totals 12349.62 998.19 8761.89 70.9

CountyBRAZOS
Highway FM0974
From VARIOUS
To VARIOUS
CSJ 6299-56-001
Proj ID SUP - 629956001
Work Type REMOVAL & DISPOSAL OF SCRAP TIRE & FRAG
 
0.010 89228.39 0.00 77206.74 86.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-16
Work Began 02-11-16
Work Completed  
Time Computed 02-11-16
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 294
Percent Time Used 80
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01161733
Totals 89228.39 0.00 77206.74 86.5