Monthly Local Let Maintenance Report For Bryan District As Of Jun 12, 2017 Page 2 Of 4

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6307-74-001
Proj IDSUP - 630774001
Work TypePICNIC AREA MAINTENANCE
 
0.00134454.3228081.6481.5
Work Order08-01-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6307-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161733
Totals34454.323186.3428081.6481.5

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6308-28-001
Proj IDRMC - 630828001
Work TypeROADSIDE MOWING
 
256.700138446.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-31-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161701
Totals138446.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-29-001
Proj IDRMC - 630829001
Work TypeROADSIDE MOWING
 
225.457258650.7629065.2411.2
Work Order02-09-17
Work Began02-07-17
Work Completed
Time Computed02-13-17
Contract Working Days70
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161702
Totals258650.760.0029065.2411.2

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6308-30-001
Proj IDRMC - 630830001
Work TypeROADSIDE MOWING
 
302.900174929.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-17
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161703
Totals174929.880.000.000.0

CountyBURLESON
HighwayFM0060
FromVARIOUS
ToVARIOUS
CSJ6308-31-001
Proj IDRMC - 630831001
Work TypeROADSIDE MOWING
 
233.630128994.250.000.0
Work Order06-01-17
Work Began05-24-17
Work Completed
Time Computed06-09-17
Contract Working Days41
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161704
Totals128994.250.000.000.0

CountyMILAM
HighwayFM0486
FromVARIOUS
ToVARIOUS
CSJ6308-32-001
Proj IDRMC - 630832001
Work TypeROADSIDE MOWING
 
333.935206653.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-03-17
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161705
Totals206653.050.000.000.0

CountyFREESTONE
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6308-33-001
Proj IDRMC - 630833001
Work TypeROADSIDE MOWING
 
297.500143162.455050.003.5
Work Order03-29-17
Work Began03-29-17
Work Completed
Time Computed04-06-17
Contract Working Days48
Addl Days Granted0
Working Days Charged2
Percent Time Used4
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161706
Totals143162.455050.005050.003.5

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-34-001
Proj IDRMC - 630834001
Work TypeROADSIDE MOWING
 
288.315147689.390.000.0
Work Order04-12-17
Work Began04-12-17
Work Completed
Time Computed04-12-17
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161707
Totals147689.390.000.000.0

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6308-35-001
Proj IDRMC - 630835001
Work TypeROADSIDE MOWING
 
263.500127274.220.000.0
Work Order06-01-17
Work Began05-24-17
Work Completed
Time Computed06-09-17
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161708
Totals127274.220.000.000.0

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6308-36-001
Proj IDRMC - 630836001
Work TypeROADSIDE MOWING
 
220.40097648.488143.708.3
Work Order05-24-17
Work Began05-24-17
Work Completed
Time Computed06-01-17
Contract Working Days35
Addl Days Granted0
Working Days Charged2
Percent Time Used5
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6308-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161709
Totals97648.488143.708143.708.3

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-37-001
Proj IDRMC - 630837001
Work TypeROADSIDE MOWING
 
278.600167318.520.000.0
Work Order05-30-17
Work Began05-10-17
Work Completed
Time Computed06-08-17
Contract Working Days44
Addl Days Granted0
Working Days Charged2
Percent Time Used4
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6308-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161710
Totals167318.520.000.000.0

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6308-55-001
Proj IDSUP - 630855001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010114516.8878237.1168.3
Work Order08-24-16
Work Began08-18-16
Work Completed
Time Computed08-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged287
Percent Time Used78
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161730
Totals114516.889483.6678237.1168.3

CountyLEON
HighwayUS0079
FromON US79
ToAT INTERSECTION WITH FM542
CSJ6308-75-001
Proj IDRMC - 630875001
Work TypeSIGNAL AND ILLUMINATION WORK
 
0.05082485.0063560.0077.0
Work Order02-28-17
Work Began04-27-17
Work Completed
Time Computed05-01-17
Contract Working Days34
Addl Days Granted0
Working Days Charged21
Percent Time Used61
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01171701
Totals82485.0063560.0063560.0077.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6309-22-001
Proj IDSUP - 630922001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00141135.0029494.7671.7
Work Order08-30-16
Work Began09-02-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged272
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161731
Totals41135.003473.8229494.7671.7

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6309-23-001
Proj IDSUP - 630923001
Work TypePICNIC AREA & WEIGH STATION MAINTENANCE
 
0.01025508.7417683.9569.3
Work Order09-06-16
Work Began09-02-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged271
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6309-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161732
Totals25508.742243.9217683.9569.3

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6309-24-001
Proj IDSUP - 630924001
Work TypeBUILDING JANITORIAL
 
0.00118242.5212592.4269.0
Work Order09-06-16
Work Began09-03-16
Work Completed
Time Computed09-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged271
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6309-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161733
Totals18242.521262.2412592.4269.0

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6309-25-001
Proj IDSUP - 630925001
Work TypeREMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.01072981.0050275.8068.8
Work Order09-13-16
Work Began09-13-16
Work Completed
Time Computed09-13-16
Contract Working Days365
Addl Days Granted0
Working Days Charged272
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161734
Totals72981.008109.0050275.8068.8

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6309-26-001
Proj IDSUP - 630926001
Work TypePICNIC/CAR POOL MAINT IN BURLESON COUNTY
 
0.00132332.3223139.4271.5
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged272
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161735
Totals32332.322726.5423139.4271.5

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6309-27-001
Proj IDSUP - 630927001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.00138028.2426976.6470.9
Work Order09-02-16
Work Began09-02-16
Work Completed
Time Computed09-02-16
Contract Working Days365
Addl Days Granted0
Working Days Charged272
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161736
Totals38028.243193.5626976.6470.9

CountyFREESTONE
HighwayFM0488
FromAT RICHLAND CREEK
ToAT RICHLAND CREEK
CSJ6310-85-001
Proj IDBPM - 631085001
Work TypeBRIDGE JOINT REPAIR
 
0.303267641.00249527.8093.2
Work Order04-03-17
Work Began04-03-17
Work Completed
Time Computed04-11-17
Contract Working Days32
Addl Days Granted0
Working Days Charged20
Percent Time Used62
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161712
Totals267641.00104476.50249527.8093.2