Last Update: Monday, November 17, 2008
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMADISON
Highway IH0045
From VARIOUS
To VARIOUS
CSJ 6022-06-001
Proj ID RMC - 602206001
Work Type SMALL ROADSIDE SIGN ASSEMBLIES
 
0.001 72029.89 0.00 72029.89 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-98
Work Began 11-01-98
Work Completed  
Time Computed 08-17-98
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 288
Percent Time Used 78
Contractor(s)
ARGO COATINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6022-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05981701
Totals 72029.89 0.00 72029.89 99.9

CountyMILAM
Highway FM1600
From VARIOUS HIGHWAYS IN MILAM COUNTY
To .
CSJ 6035-98-001
Proj ID RMC - 603598001
Work Type LITTER PICKUP
 
0.001 65658.23 0.00 8696.22 13.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-99
Work Began 04-15-99
Work Completed  
Time Computed 04-15-99
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 9
Contractor(s)
M&M
SUBCONTRACTOR(S) FOR CCSJ: 6035-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01991702
Totals 65658.23 0.00 8696.22 13.2

CountyMILAM
Highway US0079
From VARIOUS REST AREAS IN MILAM COUNTY
To VARIOUS REST AREAS IN MILAM COUNTY
CSJ 6039-14-001
Proj ID RMC - 603914001
Work Type PICNIC AREA MAINTENANCE
 
0.001 21012.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN TRUBEE DISTRIBUTOR
SUBCONTRACTOR(S) FOR CCSJ: 6039-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02991712
Totals 21012.00 0.00 0.00 0.0

CountyROBERTSON
Highway US0190
From VARIOUS HIGHWAYS IN ROBERTSON COUNTY
To .
CSJ 6041-85-001
Proj ID RMC - 604185001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 47305.55 0.00 718.67 1.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-25-99
Work Began 06-28-99
Work Completed  
Time Computed 07-06-99
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 3
Contractor(s)
RIGGINS LANDSCAPING
SUBCONTRACTOR(S) FOR CCSJ: 6041-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03991706
Totals 47305.55 0.00 718.67 1.5

CountyLEON
Highway US0079
From EAST SIDE OF US 79
To 0.1 MILES NORTH OF FM 3
CSJ 6043-03-001
Proj ID RMC - 604303001
Work Type INSTALLATION OF CHAINLINK FENCE
 
0.001 10137.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-21-99
Work Began 00-00-00
Work Completed  
Time Computed 10-21-99
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAGLE SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6043-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06991703
Totals 10137.16 0.00 0.00 0.0

CountyROBERTSON
Highway FM0979
From FM 2293
To FM 46 IN OWENSVILLE
CSJ 6059-88-001
Proj ID RMC - 605988001
Work Type SPOT BASE REPAIR
 
16.971 22998.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PAVING & DESIGN
SUBCONTRACTOR(S) FOR CCSJ: 6059-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10001701
Totals 22998.70 0.00 0.00 0.0

CountyMADISON
Highway US0190
From VARIOUS
To VARIOUS
CSJ 6060-17-001
Proj ID RMC - 606017001
Work Type TREE PRUNING & TRIMMING & BRUSH REMOVAL
 
0.001 47250.00 0.00 4500.00 9.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-31-01
Work Began 02-12-01
Work Completed  
Time Computed 02-12-01
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 58
Contractor(s)
RUTLAND CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6060-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12001701
Totals 47250.00 0.00 4500.00 9.5

CountyMADISON
Highway SH0090
From VARIOUS
To VARIOUS
CSJ 6072-89-001
Proj ID RMC - 607289001
Work Type REMOVAL OF TREES IN STATE RIGHTS OF WAY
 
0.001 30500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-02
Work Began 00-00-00
Work Completed  
Time Computed 05-13-02
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PAVING & DESIGN
SUBCONTRACTOR(S) FOR CCSJ: 6072-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08011702
Totals 30500.00 0.00 0.00 0.0

CountyROBERTSON
Highway FM0046
From VARIOUS
To .
CSJ 6108-57-001
Proj ID RMC - 610857001
Work Type TREE & BRUSH REMOVAL
 
0.001 24227.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-29-04
Work Began 00-00-00
Work Completed  
Time Computed 10-07-04
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BALDERAS CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6108-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01041704
Totals 24227.00 0.00 0.00 0.0

CountyWASHINGTON
Highway FM0390
From VARIOUS
To VARIOUS
CSJ 6144-10-001
Proj ID RMC - 614410001
Work Type CLEANING AND SEALING CRACKS
 
86.900 158634.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6144-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09061701
Totals 158634.20 0.00 0.00 0.0

CountyMILAM
Highway FM1915
From VARIOUS
To VARIOUS
CSJ 6147-50-001
Proj ID RMC - 614750001
Work Type DRIFTWOOD AND DEBRIS REMOVAL
 
0.100 125892.00 0.00 49601.40 39.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-06-06
Work Began 11-13-06
Work Completed  
Time Computed 11-13-06
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 719
Percent Time Used 98
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6147-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08061709
Totals 125892.00 0.00 49601.40 39.3

CountyBURLESON
Highway FM0060
From VARIOUS
To VARIOUS
CSJ 6152-82-001
Proj ID RMC - 615282001
Work Type CLEANING & SEALING CRACKS
 
79.000 204287.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6152-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09061710
Totals 204287.67 0.00 0.00 0.0

CountyLEON
Highway SH0075
From VARIOUS
To VARIOUS
CSJ 6161-74-001
Proj ID RMC - 616174001
Work Type GUARD FENCE REPAIR
 
0.010 170650.00 0.00 59955.00 37.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-07
Work Began 10-08-07
Work Completed  
Time Computed 10-08-07
Contract Working Days 365
Addl Days Granted 60
Working Days Charged 390
Percent Time Used 91
Contractor(s)
STAVCO
SUBCONTRACTOR(S) FOR CCSJ: 6161-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06071703
Totals 170650.00 0.00 59955.00 37.9

CountyWASHINGTON
Highway US0290
From VARIOUS
To VARIOUS
CSJ 6161-95-001
Proj ID RMC - 616195001
Work Type GUARD FENCE REPAIR
 
0.100 193100.00 0.00 52436.50 27.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-11-07
Work Began 12-11-07
Work Completed  
Time Computed 12-18-07
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 319
Percent Time Used 87
Contractor(s)
CLEANSERVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6161-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10071701
Totals 193100.00 0.00 52436.50 27.1

CountyMADISON
Highway FM1452
From VARIOUS
To VARIOUS
CSJ 6164-59-001
Proj ID RMC - 616459001
Work Type TREE & BRUSH CONTROL
 
100.000 180000.00 0.00 151200.00 84.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-04-07
Work Began 09-11-07
Work Completed  
Time Computed 09-11-07
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 95
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD
SUBCONTRACTOR(S) FOR CCSJ: 6164-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07071706
Totals 180000.00 0.00 151200.00 84.0

CountyWALKER
Highway IH0045
From MONTGOMERY COUNTY LINE
To SH 30
CSJ 6165-32-001
Proj ID RMC - 616532001
Work Type CABLE BARRIER REPAIR
 
15.990 217360.00 0.00 52810.00 25.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-08
Work Began 03-24-08
Work Completed  
Time Computed 03-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 222
Percent Time Used 60
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6165-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02081707
Totals 217360.00 0.00 52810.00 25.0

CountyROBERTSON
Highway US0079
From VARIOUS
To VARIOUS
CSJ 6173-36-001
Proj ID RMC - 617336001
Work Type GUARD FENCE REPAIR
 
0.100 174281.00 0.00 69050.00 46.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-08
Work Began 03-21-08
Work Completed  
Time Computed 04-04-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 225
Percent Time Used 61
Contractor(s)
MERKEL CONSTRUCTION CO INC
SUBCONTRACTOR(S) FOR CCSJ: 6173-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01081701
Totals 174281.00 0.00 69050.00 46.4

CountyGRIMES
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6173-39-001
Proj ID RMC - 617339001
Work Type GUARD FENCE REPAIR
 
0.100 108366.00 0.00 24653.50 25.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-08
Work Began 03-25-08
Work Completed  
Time Computed 03-25-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 221
Percent Time Used 60
Contractor(s)
MERKEL CONSTRUCTION CO INC
SUBCONTRACTOR(S) FOR CCSJ: 6173-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02081701
Totals 108366.00 0.00 24653.50 25.2

CountyBRAZOS
Highway FM0974
From VARIOUS
To VARIOUS
CSJ 6173-69-001
Proj ID SUP - 617369001
Work Type BUILDING JANITORIAL
 
0.010 31049.25 0.00 12970.08 45.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-07
Work Began 12-06-07
Work Completed  
Time Computed 12-06-07
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 331
Percent Time Used 90
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6173-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11071773
Totals 31049.25 0.00 12970.08 45.9

CountyBRAZOS
Highway SH0006
From VARIOUS
To VARIOUS
CSJ 6173-94-001
Proj ID SUP - 617394001
Work Type REMOVAL & DISPOSAL OF SCRAP WHOLE TIRES
 
0.010 64849.05 0.00 48997.06 86.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-07
Work Began 12-03-07
Work Completed  
Time Computed 12-03-07
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6173-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11071723
Totals 64849.05 0.00 48997.06 86.6