AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - BRYAN DISTRICT
Last Update: Thursday, May 30, 2013
| ITEMS 3165 2001 TO 3271 2014 |
| Item No |
Description |
Units |
May 31, 2013 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 3165 2001 |
CAM (ASPHALT) PG (76 - 22) |
TON |
|
|
1,978.000 |
1,000.00000 |
1 |
| 3165 2003 |
CAM (AGGREGATE) |
TON |
|
|
24,396.000 |
35.00000 |
1 |
| 3224 2008 |
D - GR HMA (QCQA) TY - B PG64 - 22 |
TON |
|
|
20,927.000 |
62.02682 |
2 |
| 3224 2020 |
D - GR HMA (QCQA) TY - C SAC - A PG64 - 22 |
TON |
|
|
131,292.000 |
65.92975 |
4 |
| 3224 2021 |
D - GR HMA (QCQA) TY - C SAC - B PG64 - 22 |
TON |
|
|
26,892.000 |
63.00000 |
1 |
| 3224 2022 |
D - GR HMA (QCQA) TY - C PG64 - 22 |
TON |
|
|
906.000 |
67.00000 |
1 |
| 3224 2031 |
D - GR HMA (QCQA) TY - C PG76 - 22 |
TON |
|
|
32,448.800 |
63.00000 |
1 |
| 3224 2062 |
D - GR HMA (QCQA) TY - D PG64 - 22 (LEVEL - UP) |
TON |
|
|
11,171.000 |
68.18906 |
2 |
| 3246 2001 |
FGSM (ASPHALT) (TYII SMA PG76 - 22) |
TON |
5.000 |
1,740.00000 |
5.000 |
1,740.00000 |
1 |
| 3246 2002 |
FGSM (AGGR) (TYII SMA) (SAC A) |
TON |
59.000 |
395.00000 |
59.000 |
395.00000 |
1 |
| 3248 2001 |
REMOVING PAVEMENT TEXTURING (INLAY) |
LF |
|
|
41,051.000 |
1.00000 |
1 |
| 3248 2002 |
REM PAVEMENT TEXTURING (PLANE & INLAY) |
LF |
|
|
37,192.000 |
2.00000 |
1 |
| 3269 2002 |
PFC (ASPHALT) PG76 - 22 |
TON |
1,046.000 |
790.00000 |
1,046.000 |
790.00000 |
1 |
| 3269 2006 |
PFC (AGGREGATE) (PG76 MIX) SAC - A |
TON |
15,562.000 |
50.00000 |
15,562.000 |
50.00000 |
1 |
| 3270 2032 |
SUPERPAVE MIXTURES SP - C SAC - B PG64 - 22 |
TON |
1,341.000 |
74.75000 |
1,341.000 |
74.75000 |
1 |
| 3270 2104 |
SUPERPAVE MIXTURES SP - D SAC - B PG64 - 22 |
TON |
6,009.000 |
78.00000 |
6,009.000 |
78.00000 |
1 |
| 3270 2167 |
SUPERPAVE MIXTURES SP - B SAC - B PG64 - 22 |
TON |
4,080.000 |
75.00000 |
4,080.000 |
75.00000 |
1 |
| 3271 2014 |
STONE - MTRX - ASPH SMA - D SAC - A PG76 - 22 |
TON |
5,396.000 |
122.00000 |
5,396.000 |
122.00000 |
1 |