AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - BRYAN DISTRICT

Last Update: Monday, March 31, 2014
ITEMS 400 2001 TO 460 2022
Items Items Bid Code Range
0100 - 0180
0247 - 0276
0305 - 0368
0400 - 0496
0500 - 0560
0610 - 0687
0740 - 0784
0800 - 0800
1018 - 1122
2128 - 2151
3246 - 3271
4116 - 4641
5172 - 5434
6007 - 6834
7380 - 7380
8020 - 8898
400 2001 - 460 2022
460 2024 - 476 2002
479 2001 - 496 2296
Item No Description Units March 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
400 2001 STRUCT EXCAV CY     29.000 18.00000 1
400 2003 STRUCT EXCAV (PIPE) CY     631.000 4.60000 1
400 2004 STRUCT EXCAV (BRIDGE) CY     10.000 75.00000 1
400 2005 CEM STABIL BKFL CY 112.000 150.00000 1,254.500 105.61371 9
400 2006 CUT & RESTORING PAV SY     282.000 126.23404 5
401 2001 FLOWABLE BACKFILL CY     242.000 200.97107 3
402 2001 TRENCH EXCAVATION PROTECTION LF 136.000 10.00000 2,535.000 9.98785 6
403 2001 TEMPORARY SPL SHORING SF 258.000 150.00000 796.000 69.63568 4
407 2001 SHEET PILING (PZ - 27) SF 2,238.000 52.00000 39,824.000 40.67437 2
407 2005 SHEET PILING (PZ - 22) SF     230.000 85.00000 1
416 2001 DRILL SHAFT (18 IN) LF     294.000 51.80952 3
416 2002 DRILL SHAFT (24 IN) LF     1,083.000 106.41274 3
416 2003 DRILL SHAFT (30 IN) LF     745.000 130.00000 2
416 2004 DRILL SHAFT (36 IN) LF 180.000 210.00000 1,440.000 185.21667 5
416 2018 DRILL SHAFT (SIGN MTS) (24 IN) LF     26.000 92.00000 1
416 2029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 128.000 150.00000 198.000 151.06061 2
416 2032 DRILL SHAFT (TRF SIG POLE) (36 IN) LF     139.000 226.60432 4
416 2034 DRILL SHAFT (TRF SIG POLE) (48 IN) LF     154.000 351.00000 3
420 2003 CL C CONC (ABUT) CY 70.900 750.00000 251.600 829.82909 5
420 2004 CL C CONC (BENT) CY     284.500 825.47487 4
420 2006 CL C CONC (RAIL FOUNDATION) CY     36.200 928.31492 3
420 2011 CL C CONC (RETAINING WALL) CY     9.000 655.00000 1
420 2013 CL C CONC (MISC) CY 31.000 400.00000 254.000 751.18110 2
420 2019 CL C CONC (CAP) CY     62.400 770.00000 1
420 2020 CL C CONC (CRASHWALL) CY     100.700 488.00000 1
420 2021 CL C CONC (COPING) CY     1.200 1,500.00000 1
420 2022 CL E CONC (SEAL) CY     7.500 225.00000 1
420 2029 CL S CONC (SLAB) CY 15.300 650.00000 163.600 675.05807 3
420 2033 CL S CONC (APPR SLAB) CY     217.000 416.84332 2
420 2034 CL S CONC (BRIDGE SDWLK) CY     189.600 520.00000 1
420 2051 CL C CONC (COLUMN) CY     36.400 781.75824 2
420 2065 CL A CONC (STEPS) CY     46.800 1,480.00000 1
420 2086 CL A CONC (MISC) (4") SY     20.000 185.00000 1
420 2090 CL A CONC (COLLAR) EA     69.000 601.59420 2
422 2001 REINF CONC SLAB SF 1,820.000 12.00000 18,280.000 16.59311 3
423 2001 RETAINING WALL (MSE) SF     600.000 60.00000 1
423 2006 RETAINING WALL (CONC BLOCK) SF     7,660.000 39.00000 1
423 2009 RETAINING WALL (SOIL NAILED) (FACIA) SF     19,912.000 46.52862 2
425 2014 PRESTR CONC SLAB BEAM (4SB12) LF     354.000 110.00000 1
425 2015 PRESTR CONC SLAB BEAM (5SB12) LF 172.500 200.00000 703.500 139.61620 2
425 2017 PRESTR CONC SLAB BEAM (5SB15) LF     742.120 167.00000 1
425 2064 PRESTR CONC GIRDER (TX28) LF 277.940 185.00000 3,116.050 141.28142 2
425 2065 PRESTR CONC GIRDER (TX34) LF     2,253.200 119.09018 2
427 2002 CONCRETE PAINT FINISH SF     21,694.000 .50000 1
427 2011 CONCRETE PAINT (FAUX STONE) SF     20,145.400 1.46343 2
428 2001 CONC SURF TREAT (CLASS I) SY     1,451.000 2.90000 1
429 2007 CNC STR REP (HORIZONTAL) SF     46.500 120.00000 1
430 2002 CL C CONC FOR EXT STR (ABUT) CY     92.200 830.00000 1
430 2006 CL C CONC FOR EXT STRU (CULV) (10'X 10') LF     126.000 665.00000 1
430 2007 CL C CONC FOR EXT STRU (CULV) (6'X 6') LF     57.000 320.00000 1
430 2025 CL C CONC FOR EXT STRU (CULV) (7'X 7') LF     36.000 410.00000 1
430 2034 CL C CONC FOR EXT STR (CULV) (10'X7') LF     160.000 555.00000 1
430 2051 CL C CONC FOR EXT STR (CULV) 5' X 2' LF     26.000 290.00000 1
430 2055 CL S CONC FOR EXT STR (APPR SLAB) CY     133.200 505.00000 1
430 2141 CL C CONC FOR EXT STR (CULV) (2 - 10'X10' LF 283.000 1,250.00000 283.000 1,250.00000 1
430 2158 CL S CONC FOR EXT STR (SLAB) SF     22,100.000 18.00000 1
432 2001 RIPRAP (CONC) (4 IN) CY     1,215.600 346.05956 7
432 2002 RIPRAP (CONC) (5 IN) CY 22.000 475.00000 116.000 461.37931 4
432 2012 RIPRAP (STONE TY F) (GROUT) (8 IN) CY     25.000 91.80000 1
432 2015 RIPRAP (STONE COMMON) (DRY) (6 IN) CY     4.800 225.00000 1
432 2016 RIPRAP (STONE COMMON) (DRY) (8 IN) CY     25.000 160.00000 1
432 2019 RIPRAP (STONE PROTECTION) (12 IN) CY     12.000 250.00000 1
432 2021 RIPRAP (STONE PROTECTION) (18 IN) CY 673.000 130.00000 2,080.000 100.76827 5
432 2033 RIPRAP (STONE COMMON) (DRY) (12 IN) CY     16.000 250.00000 1
432 2039 RIPRAP (MOW STRIP) (4 IN) CY 32.000 400.00000 998.500 435.39810 13
432 2040 RIPRAP (MOW STRIP) (5 IN) CY     19.000 425.00000 1
432 2041 RIPRAP (STONE COMMON) (DRY) (18 IN) CY 22.000 175.00000 22.000 175.00000 1
432 2048 RIPRAP (CONC) (FLUME) CY     167.000 453.59281 2
432 2084 RIPRAP (CONC) (CL B) (4") CY 5.600 1,000.00000 5.600 1,000.00000 1
438 2001 CLEAN EXIST JOINTS LF     169.000 3.20000 1
438 2004 CLEAN AND SEAL JOINTS LF     816.000 22.84314 2
442 2037 STR STL (BRIDGE DECK FRAMING) LB     52,443.000 2.10000 1
442 2047 STRUCTURAL STEEL (MISCELLANEOUS BRIDGE) LB     5,682.000 4.44266 2
442 2048 STRUCTURAL STEEL (MISC NON - BRIDGE) LB     13,716.000 3.64399 2
446 2002 CLEAN & PAINT EXIST STR (SYSTEM II) LS     1.000 215,000.00000 1
450 2018 RAIL (TY C411) LF     857.000 112.00000 1
450 2057 RAIL (EXIST RAIL MODIFICATION) LF     277.000 65.00000 1
450 2076 RAIL (HANDRAIL) (TY E) LF     324.000 200.00000 1
450 2080 RAIL (TY T221) LF     595.000 60.00000 1
450 2111 RAIL (PARAPET) LF     37.000 340.00000 1
450 2142 RAIL (TY 221) (SPL) LF     568.000 270.00000 1
450 2154 RAIL (TY T1W) LF     676.000 150.00000 1
450 2161 RAIL (TY T223) LF 314.000 95.00000 1,392.000 83.13864 4
450 2186 RAIL (SIDE - MOUNTED) (STEEL) (RETROFIT) LF     132.000 285.00000 1
450 2194 RAIL (TY T223) (RAC - R) LF     286.000 314.50000 1
450 2641 RAIL (TY T131RC) LF 408.600 125.00000 408.600 125.00000 1
450 2642 RAIL (T131RC) (RETROFIT) LF     560.000 93.80000 1
452 2002 REMOV RAIL (METAL ELEMENTS) LF 380.000 11.00000 666.000 11.42943 2
454 2005 ARMOR JOINT (WITH SEAL) LF 46.000 75.00000 496.000 69.32661 5
454 2006 HEADER TYPE EXPANSION JOINT LF     329.000 126.72948 2
454 2008 JOINT SEALANT LF     169.000 10.50000 1
459 2009 GABION MATTRESSES (GALV) (6 IN) SY     859.000 52.00000 1
460 2003 CMP (GAL STL 18 IN) LF 46.000 60.00000 214.000 36.44860 2
460 2004 CMP (GAL STL 24 IN) LF     165.000 35.00000 1
460 2005 CMP (GAL STL 30 IN) LF     8.000 175.00000 1
460 2007 CMP (GAL STL 36 IN) LF     188.000 45.00000 1
460 2008 CMP (GAL STL 42 IN) LF     30.000 60.00000 1
460 2015 CMP AR (GAL STL DES 3) LF     56.000 40.00000 1
460 2018 CMP AR (GAL STL DES 6) LF     82.000 50.00000 1
460 2022 CMP (GAL STL BIT COAT 12 IN) LF 131.000 60.00000 131.000 60.00000 1