Section 3: Project Design Phase
Exhibit A and Support Documentation
The district produces or uses a consultant to produce an Exhibit
A, which is a 30%
or more Plans, Specifications and Estimates
(PS&E)
detailing the work to be performed within railroad right of way.
Depending on the scope of work involved, various support documents require
review and approval by the railroad company.Further guidance on how to develop an Exhibit A is provided
in Chapter 7.
Underpass Plans
Underpass projects are generally more complicated than all
other types of projects and require
multiple
stages
of submittals:- Project concept/schematic.
- Proposed track shoofly designs must be reviewed and approved by the railroad company before bridge plan submittal.
- 30% plans (Exhibit A).
- 60% plans.
- 100% plans (Exhibit B).
Required Documents
Below is a list of required documents that may be needed for
design approval
and/or
for the C&M Agreement:- Overpass (new or modification):
- Exhibit A,30% or more PS&E.
- Exhibit B, 100% Plans.
- Railroad Scope of Work (RR SOW).
- Design Conformance to Railroad Guidelines (DCRG) Report, if applicable.
- Metes and bounds property descriptionor area map.
- Boring logs,if applicable.
- 5% theoretical cost estimate,if applicable.
- Hydraulic analysis,if applicable.
- Overhead checklist (CPKCprojects only).
- Railroad Work Matrix,if applicable.
- Underpass (new or modification):
- All items for overpass required documentation.
- Typical Selection Report (TSR),if applicable.
- Cooper E-80 loading calculations,if applicable.
- Shoofly track design.
- At grade crossing (new or modification):
- Exhibit A,30% or more PS&E / Railroad Scope of Work (RR SOW).
- Metes and bounds property descriptionor area map.
- Railroad Work Matrix,if applicable.
- Traffic signal preemption:
- Exhibit A,30% or more PS&E.
- Preemption Form (TxDOT Form 2304).
- Traffic signal timing dataand phasing diagram.
- Signed preemption request.
- Culverts, drainage pipes, or conduits on or over railroad right of way:
- Exhibit A,30% or more PS&E.
- Pipeline or wireline license request form.
- Hydraulic analysis,if applicable.
- Cooper E-80 loading calculations,if applicable.
- Railroad Work Matrix,if applicable.
- Jointusage (ditch, sidewalk, etc.) or longitudinal encroachments:
- Exhibit A,30% or more PS&E.
- Hydraulic analysis,if applicable.
- Railroad Work Matrix,if applicable.
Design and C&M Agreement Approval Documents
A brief description of each type of document is
available to determine current examples and procedures on the .
Design Conformance to Railroad Guidelines (DCRG) Report
A DCRG
report details how the proposed
overpass design meets or does not meet railroad company design guidelines. DCRG
reports
include:- Brief description of project and need.
- If overpass spans railroad right of way (bridge bents outside of right of way).
- Angle the overpass crosses the rail line.
- Vertical clearance.
- Horizontal clearance.
- Lighting for railroad.
- Fencing on bridge.
- Utilities and any relocations.
- Excavation and demolition work.
- Preparation work on railroad right of way (tree removal, etc.).
- If drill shaft locations are within zone of railroad live load surcharge, and if shoring will be required.
- How drainage is blocked from falling on railroad right of way.
- Where future tracks may be placed.
- Need for crash walls, assuming future tracks are in place.
- Photos.
Metes and Bounds Property Description
A legal property description to define the railroad right
of way encumbered by the construction project, complete with description
and map of parcels. Area encumbered may also include area needed
temporarily for project construction.
Area Map
Area Map
The Union Pacific Railroad, BNSF Railway and several shortline
railroads will accept an area map to document the area needed by
the project in place of a metes and bounds property description. The
area map is comprised of a CAD drawing, tied into state plane coordinates,
or a latitude/longitude, and used by the affected railroad for their
GIS mapping.
The railroad will generally only allow an area needed for
the proposed crossing. This would include edge of road to edge of
road for at-grade crossings and edge of sidewalk to edge of sidewalk
for pathway projects. For bridge projects, an additional 20-foot-wide
strip outside of the edge of bridge will be the limit.
Photos
Photos should show area where the project will occur and clarify
if any
commercial billboards or signboards
located
on railroad right of way will need to be relocated. Photos should
be from an actual site visit and not taken from online images.5% Theoretical Cost Estimate
In certain cases, where an existing at-grade public crossing
with active warning devices is being replaced with a bridge and
federal funds are used, the railroad or another
local
government
will need to participate in the project funding.
See Title 23, Code of Federal Regulations, Section
646.210
for details. This theoretical cost will be based on the following design
criteria:- The approach roadway geometry will be designed using the minimum design criteria allowed for the functional class and annual average daily traffic (AADT) of the subject roadway (i.e., minimum k-values, design speed, grades, vertical clearance, etc.). Approach roadway for the theoretical structure will terminate as soon as the grade has returned to existing roadway profile.
- The bridge length will be the minimum length possible to fully span the railroad right of way. Any other features that would need to be spanned based on actual conditions (ie., other roadways, waterways, etc.) are not considered.Only a bridge overpass will be considered for the theoretical structure, even if an underpass is ultimately proposed for the actual project.
- The bridge superstructure type for the theoretical structure will be the same as for the proposed bridge span crossing the railroad right of way.
- The width of the theoretical structure will be the same as the proposed bridge width if the number of lanesremainsthe same as the number of lanes on the existing grade crossing. If the proposed bridge has more lanes than the existing grade crossing, the theoretical structure will be the width of the proposed bridge minus the width of the number of extra lanes for the proposed bridge.
- If retaining walls are used for the proposed bridge to limit the amount of embankment, retaining walls will be used for the theoretical structure.
- Other design features required for the proposed structure, such as culverts, illumination, attenuators, riprap, etc., will be included with the theoretical structure.
The geometry of the theoretical structure will be presented
as a .pdf file which contains an elevation view showing vertical
geometry of the structure and approaches, and a typical section
showing the theoretical bridge cross-section.
The bridge
engineer will prepare
an estimate in spreadsheet form
based on the quantities for the theoretical structure. Costs for
each item associated with the theoretical structure should be similar
to a current project estimate. If no current project estimate is
available, use the most recent
statewide average
low bid unit prices.If the highway or rail line is relocated to eliminate the
at-grade crossing, the 5% theoretical cost will be the lesser of:
- Actual cost of relocation project.
- Estimated cost of relocation project.
- Estimated cost of a theoretical overpass as described above.
Upon substantial completion of the project, RRD
is notified by the district, and a letter is sent to the railroad
for payment. The payment is received and processed by FIN. These
funds are typically used to offset the federal obligation of the
project by the same amount. Substantial completion is typically
when the at-grade crossing is closed, and traffic moved to the grade
separated structure.
Hydraulic Analysis
An analysis showing contours and direction of water flow with calculations.
Review the guidelines in the Design Division's .
Overhead Checklist
Also known as the overhead grade separation data sheet, this
form gives a general description of design features on overpass
projects, including horizontal and vertical clearances, fencing,
and lighting.
Railroad Work Matrix
A railroad work matrix is needed for projects requiring
a
detailed outline of the division of labor and materials to properly
bid out the project to a TxDOT contractor, obtain a proper estimate
from the railroad company and coordinate the project construction
schedule. The railroad work matrix needs to address:
- Track installation and removal responsible party(railroad company or TxDOT contractor).
- Track tie-ins to live track responsibilities party(railroad company or TxDOT contractor).
- Responsible party forsupplying the track materials (rail, ties, ballast, subballast).
- Need forderailers or guardrailand responsible party toprovide and install,if needed.
- Responsible party toperform site grading and groundwork.
- Assigned responsible party for providing and installingany drainage features.
- Responsible party for utility adjustments.
- Process for material deliveryto the project site.
- Responsible party for deliveringthe materials.
- Material(s) stockpile location.
- Live track closures neededto facilitate construction.
- Equipment needed on railroad right of way to construct the project.
Typical Selection Report (TSR)
Used on underpass projects, the TSR identifies materials and
construction methods to be used on the railroad bridge proposed
to be built or modified by TxDOT or local governments. In the rare case
that an underpass bridge is being developed on a new road alignment
or a road alignment with an existing at-grade crossing, the method
will typically involve an at-grade shoofly track alignment that
routes the railroad around the footprint of the proposed structure
to allow for its construction. If this method is performed in a
cut excavation, longitudinal shoring will likely be required under
the influence of railroad live load.
More commonly, a railroad underpass replaces an existing underpass
structure due to deficient vertical or horizontal clearance in conjunction
with a safety or added capacity project. In this case, three options
are
available,
considering maintenance of rail traffic.- Option 1:Build the proposed underpass adjacent to the existing underpass and develop a revised railroad alignment that ties into the approaching railroad alignment. The railroad company may be open to this option if there is already a horizontal curve at this location or if the design speeds are low enough that a jog in the railroad alignment is acceptable. For tangent existing track alignments, the railroad company typically does not approve of providing such a permanent realignment.
- Option 2:Build the proposed underpass on the same alignment as the existing and construct a bypass shoofly alignment with a temporary bridge structure (if maintenance of highway traffic is required). This temporary bridge structure can be of lower cost open deck construction with shorter spans and vertical clearance less than the final ultimate condition for the short duration of its usage. Phasing of the lower roadway construction should be considered in developing the temporary shoofly bridge and new mainline bridge layouts. A subset of the second option involves building a permanent bypass shoofly alignment. This is only entertained if it proves more cost effective overall than a temporary structure and if the railroad company cost participates in providing what effectively is provision for a future second track.
- Option 3:Construct a “roll-in” where the replacement structure is built near or adjacent to the existing bridge and physically lifted or slid into place on new substructures in a short duration process thatreduces the timeof complete closure of the railroad (usually 72 hours maximum). While the “roll-in” technique cancreatesignificant cost savings in avoiding a temporary structure and approach track alignment, it also carries measurable construction risk considering the delay potential to the railroad company. TxDOT has had limited success in achieving railroad company approval of “roll-in” replacements, and they should only be pursued if early coordination with the railroad company is undertaken and if the railroad line has limited traffic.
Structure selection should consider the railroad company’s
preferred structure selection if feasible. Refer to railroad company
published guidelines for preferred structure types. Generally, railroad companies
prefer multi-girder steel deck girder bridges due to weight savings
(ease of removal replacement) and ease of repair. TxDOT preference
is multi-girder composite prestressed girder bridges due to construction
cost savings, but these have limited span capability and higher
vertical clearance requirements in railroad company guidelines.
In the case of replacements involving limited vertical clearance
or long span applications, a through plate girder bridge may be
needed to minimize structure depth below the rail or span roadways
with a large number of lanes and/or clear zone. The designer should
be aware this is the railroad company’s least favorable structure
type due to its fracture critical nature and expense. Clear safety improvements
or cost savings (e.g., avoiding a pump station or major railroad
grade raise) will need to be demonstrated to successfully gain railroad
company approval of a through girder structure. Ballasted deck structures
are required for all underpass projects over a roadway, and TxDOT
preference is for a composite concrete deck in lieu of a steel plate
deck if railroad company approval can be obtained and target vertical
clearance is achievable.
Preemption Form (TxDOT Form 2304)
This form
is used to determine
the amount
of advanced preemption time needed from the railroad company for
a traffic signal interconnected
to an at-grade
crossing. See Form 2304 and 2304-I for instructions on
how to fill out the form in TxDOT E-Forms.
Traffic Signal Timing Data
If traffic signal controller is existing, data should be downloaded
from controller to show minimum green, yellow change and red clearance
times during normal and preemption phases as well as delay time
and track clearance green time. If traffic signal controller is
not existing, show proposed times to be programmed into controller.
Pipeline or Wireline License Request Form
The Pipeline or Wireline License Request Form
is
provided to the railroad company to clarify the exact location where
pipe or wire will be installed, material used for pipe or conduit
and product
the line will carry.Cooper E-80 Loading Calculations
Cooper E-80 Loading Calculations for underpass bridges,
retaining
walls
or culverts under a track are used
to
verify the proposed element meets Cooper E-80 standard.Design Approval Process
After the
project
documents have been
approved by the district, the district railroad coordinator forwards
them to the assigned RRD
contract specialist
who then coordinates the review of these documents with the proper
division personnel. Division reviews include:- Bridge design.
- Grade crossing warning devices.
- Traffic signal preemption.
- Track design.
- Hydraulics.
- Pedestrian elements.
- Landscape architecture.
- Utility application.
After all comments have been resolved from the divisions,
the
RRD
contract specialist forwards the documents
to the railroad company for review.For follow-up comments, the district will work with
the railroad company point of contact.
Preemption Request Form
The railroad may
require a signed
preemption
request form. The form lists the type and amount of preemption
,
the preemption circuits requested on the project, and
the number and gage of the conductor wire
.This form will be signed by the government entity
maintaining the traffic signal after construction. The district
will coordinate signatures. The signed preemption request form needs
to be included with the Exhibit A in the final agreement packet.
Design Approval Expiration
Design approval from railroad companies typically lasts for
three years. If a project has
been approved but
pulled
from letting, the Exhibit A and support materials will need to be
reviewed again if three years have lapsed
.Railroad Company Cost Estimates
Construction projects will require an estimate from the railroad
company for labor and materials provided by the railroad company
on the project. Construction activities requiring a railroad company
cost estimate:
- Flagging.
- Preliminary and construction engineering.
- Constructioninspection.
- Planking or replanking.
- Installation, relocation, or removal of grade crossing warning devices.
- Railroad circuitry adjustments.
- Installation or adjustment ofrailroaddrainage structures under tracks.
- Relocatingrailroadutilities on railroad right of way.
- Licensing fee for C&M Agreement and Right of Entry Agreement.
Prior to drafting a C&M Agreement,
RRD
will
review the estimates to verify:- Project location and description information is correct.
- Estimates are accurate given comparable recent projects.
- Quantities of major items match design shown in Exhibit A. Major items for grade crossing warning devices include gates, cabins, mast flashers, cantilevers, foundations, signs and flashing light pairs. On planking projects,major items includelength and size of crossing surface panels and rail and tie quantities.
- Profit is notbilledby a railroad company.
- A maximum 5% overhead rate isbilledif an audited rate does not exist for a contractor or railroad company. FHWA approved additive rates are used by railroad companies as indicated on the railroad estimate.
Any railroad wireline diagrams should also be verified for:
- Correct location of shunt placement given any preemption time requested and speed of fastest train on each track.
- Location of warning devices matches design in Exhibit A.
- Warning devices and flashing lights match design in Exhibit A.
- Gate and cantilever lengths match Exhibit A.
- Cabin location matches Exhibit A.
- Distances between cabin, warning devices, roadway, and rail match Exhibit A.
- Roadway design (number of lanes, medians, shoulders, and widths of these items) matches Exhibit A.
- If needed, phased implementation shown to match Exhibit A.
With proper supporting documentation, federal
railroad reimbursement policy permits TxDOT to pay the actual cost
of railroad work, even if it is more than the project cost estimate.
See Chapter 9, Construction and Inspection Process,
Section 4, Invoices.