Underpass Plans
    Underpass projects are generally more complicated than all
other types of projects and require 
multiple
 stages
of submittals:- Project concept/schematic.
 - Proposed track shoofly designs must be reviewed and approved by the railroad company before bridge plan submittal.
 - 30% plans (Exhibit A).
 - 60% plans.
 - 100% plans (Exhibit B).