Railroad Work Matrix 
    A railroad work matrix is needed for projects requiring
 a
detailed outline of the division of labor and materials to properly
bid out the project to a TxDOT contractor, obtain a proper estimate
from the railroad company and coordinate the project construction
schedule. The railroad work matrix needs to address:
- Track installation and removal responsible party(railroad company or TxDOT contractor).
 - Track tie-ins to live track responsibilities party(railroad company or TxDOT contractor).
 - Responsible party forsupplying the track materials (rail, ties, ballast, subballast).
 - Need forderailers or guardrailand responsible party toprovide and install,if needed.
 - Responsible party toperform site grading and groundwork.
 - Assigned responsible party for providing and installingany drainage features.
 - Responsible party for utility adjustments.
 - Process for material deliveryto the project site.
 - Responsible party for deliveringthe materials.
 - Material(s) stockpile location.
 - Live track closures neededto facilitate construction.
 - Equipment needed on railroad right of way to construct the project.