Detail Letting Schedule for Webb County (FY 2022)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Webb County (FY 2022) |
CCSJ: 0018-04-065 |
|||
District: | LAREDO | Let Date: | May 2022 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | F 2022(669) | CSJ: | 0018-04-065 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 1.200 MILES NORTH OF US 83 (NBML) | Fund Cat: | 1 |
Limits To: | 9.906 MILES NORTH OF US 83 | ESTIMATE: | $8,279,884 |
Length: | 8.7 | Actual | $8,989,651 |
District: | LAREDO | Let Date: | May 2022 |
Highway: | BI 35-C | Let Status: | Actual |
Project ID: | F 2022(670) | CSJ: | 0017-17-011 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | NORTH END OF NUECES RIVER BRIDGE | Fund Cat: | 1 |
Limits To: | 0.1 MI N OF IH35/BI35C N INT | ESTIMATE: | $1,042,567 |
Length: | 1.8 | Actual | $1,289,024 |
District: | LAREDO | Let Date: | May 2022 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | F 2022(669) | CSJ: | 0018-02-087 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 4.885 MI N OF WEBB CL (NBML) | Fund Cat: | 1 |
Limits To: | 6.52 MI SOUTH OF FM 133 | ESTIMATE: | $3,699,969 |
Length: | 6.3 | Actual | $4,236,619 |
District: | LAREDO | Let Date: | May 2022 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | F 2022(669) | CSJ: | 0018-03-063 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 9.906 MILES NORTH OF US 83 (NBML) | Fund Cat: | 1 |
Limits To: | MILE MARKER 31 | ESTIMATE: | $1,428,272 |
Length: | 2.5 | Actual | $1,633,942 |
District: | LAREDO | Let Date: | May 2022 |
Highway: | BI 35-C | Let Status: | Actual |
Project ID: | C 18-9-11 | CSJ: | 0018-09-011 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.2 MI N IH 35/BI-35C SOUTH INT | Fund Cat: | 1 |
Limits To: | SOUTH END OF NUECES RIVER BRIDGE | ESTIMATE: | $350,605 |
Length: | 0.8 | Actual | $418,839 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0018-04-065 | ||
---|---|---|---|
Length: | 20.1 | ||
Estimate: | $14,801,297 | ||
Actual: | $16,568,075 | ||
CCSJ: 0018-05-104 |
|||
District: | LAREDO | Let Date: | Feb 2022 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | C 18-5-104 | CSJ: | 0018-05-104 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 1.19 MI SOUTH OF CARRIER RD (SBML) | Fund Cat: | 1 |
Limits To: | MILE MARKER 16 | ESTIMATE: | $3,970,904 |
Length: | 4.5 | Actual | $3,824,923 |
District: | LAREDO | Let Date: | Feb 2022 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | C 18-5-105 | CSJ: | 0018-05-105 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 1.19 MI SOUTH OF CARRIER RD (NBML) | Fund Cat: | 1 |
Limits To: | UNIROYAL INT | ESTIMATE: | $1,487,180 |
Length: | 1.8 | Actual | $1,616,234 |
District: | LAREDO | Let Date: | Feb 2022 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | C 18-6-175 | CSJ: | 0018-06-175 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 0.8 MI NORTH OF US59 CONC SEC (NBML) | Fund Cat: | 1 |
Limits To: | 1.19 MI SOUTH OF CARRIER RD | ESTIMATE: | $2,628,305 |
Length: | 3.2 | Actual | $2,853,361 |
District: | LAREDO | Let Date: | Feb 2022 |
Highway: | BU 59-Z | Let Status: | Actual |
Project ID: | C 542-1-93 | CSJ: | 0542-01-093 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | BUENA VISTA | Fund Cat: | 1 |
Limits To: | IH 35 (SAN DARIO) | ESTIMATE: | $1,135,753 |
Length: | 1.7 | Actual | $1,163,235 |
District: | LAREDO | Let Date: | Feb 2022 |
Highway: | FM 1472 | Let Status: | Actual |
Project ID: | C 2150-4-82 | CSJ: | 2150-04-082 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | 4.2 MILES SOUTH OF SH 255 (SB) | Fund Cat: | 1 |
Limits To: | PAN AMERICAN BLVD | ESTIMATE: | $3,595,959 |
Length: | 9.9 | Actual | $3,703,361 |
District: | LAREDO | Let Date: | Feb 2022 |
Highway: | SS 400 | Let Status: | Actual |
Project ID: | C 3543-1-8 | CSJ: | 3543-01-008 |
Description: | RESURFACE ROADWAY | Handling Code: | |
Limits From: | NORTH ARKANSAS AVENUE | Fund Cat: | 1 |
Limits To: | SL 20 | ESTIMATE: | $874,440 |
Length: | 1.2 | Actual | $884,821 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0018-05-104 | ||
Length: | 22.3 | ||
Estimate: | $13,692,541 | ||
Actual: | $14,045,934 | ||
CCSJ: 0086-01-099 |
|||
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | SH 359 | Let Status: | Approved |
Project ID: | F 2022(924) | CSJ: | 0086-01-099 |
Description: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Handling Code: | |
Limits From: | SL 20 | Fund Cat: | 8 |
Limits To: | CONCORD HILLS BLVD. | ESTIMATE: | $683,452 |
Length: | 0.6 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | IH 35 | Let Status: | Approved |
Project ID: | STP 2022(923)HES | CSJ: | 0018-06-215 |
Description: | INSTALL ILLUMINATION | Handling Code: | |
Limits From: | 0.4 MI N OF KILLAM | Fund Cat: | 8 |
Limits To: | KILLAM | ESTIMATE: | $104,282 |
Length: | 0.3 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | SH 359 | Let Status: | Approved |
Project ID: | STP 2022(923)HES | CSJ: | 0086-01-098 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | SL 20 INTERSECTION | Fund Cat: | 8 |
Limits To: | E.G. RANCH | ESTIMATE: | $99,832 |
Length: | 2.3 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | FM 1472 | Let Status: | Approved |
Project ID: | F 2022(924) | CSJ: | 2150-04-083 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | PAN AMERICAN BLVD | Fund Cat: | 8 |
Limits To: | FLECHA LN | ESTIMATE: | $298,547 |
Length: | 3.8 | Actual | $0 |
Back... | Totals for 0086-01-099 | ||
Length: | 7 | ||
Estimate: | $1,186,114 | ||
Actual: | |||
CCSJ: 0086-16-015 |
|||
District: | LAREDO | Let Date: | Oct 2021 |
Highway: | SL 20 | Let Status: | Actual |
Project ID: | C 86-16-15 | CSJ: | 0086-16-015 |
Description: | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | Handling Code: | |
Limits From: | 0.50 MI NORTH OF LOS PRESIDENTES AVE. | Fund Cat: | 11 |
Limits To: | 0.50 MI SOUTH OF LOS PRESIDENTES AVE. | ESTIMATE: | $733,212 |
Length: | 1.0 | Actual | $877,030 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0086-16-015 | ||
Length: | 1 | ||
Estimate: | $733,212 | ||
Actual: | $877,030 | ||
CCSJ: 0922-00-074 |
|||
District: | LAREDO | Let Date: | Apr 2022 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 922-00-74 | CSJ: | 0922-00-074 |
Description: | REMOVE/REPLACE BRIDGE RAIL | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 11 |
Limits To: | . | ESTIMATE: | $2,446,515 |
Length: | 0.0 | Actual | $2,435,840 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0922-00-074 | ||
Length: | 0 | ||
Estimate: | $2,446,515 | ||
Actual: | $2,435,840 | ||
CCSJ: 0922-33-159 |
|||
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2021(892) | CSJ: | 0922-33-159 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | WORMSER RD AT DOLORES CREEK RELIEF | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $773,875 |
Length: | 0.0 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2021(889) | CSJ: | 0922-33-160 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | WORMSER RD AT DOLORES CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $624,604 |
Length: | 0.0 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2021(896) | CSJ: | 0922-33-162 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | CALLAGHAN RD AT CARRIZITOS CRK BRCH | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $679,493 |
Length: | 0.1 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2022(835) | CSJ: | 0922-33-192 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | CALLAGHAN RD AT CARRIZITOS CREEK BRANCH | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $255,558 |
Length: | 0.1 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2022(277) | CSJ: | 0922-33-193 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | CALLAGHAN RD AT CARRIZITOS CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $471,476 |
Length: | 0.1 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2022(261) | CSJ: | 0922-33-194 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | MINES ROAD AT CHUPADORA CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $629,351 |
Length: | 0.0 | Actual | $0 |
District: | LAREDO | Let Date: | Aug 2022 |
Highway: | CR | Let Status: | Approved |
Project ID: | BR 2022(251) | CSJ: | 0922-33-195 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | CALLAGHAN RD AT CARRIZITOS CRK BRANCH | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $285,897 |
Length: | 0.1 | Actual | $0 |
Back... | Totals for 0922-33-159 | ||
Length: | 0.4 | ||
Estimate: | $3,720,253 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |