Construction updates
Construction on the Big 6 project began on Dec. 1, 2025.
Current activity
Lane closures
Thursday, November 19
- Northbound frontage road between Harvey Road and University Drive – Single-lane Closure – 6 a.m. – 3 p.m.
- The northbound frontage road right lane will be closed for street cleaning operations.
- Eastbound University between SH 6 frontage road and Veterans Parkway – Single-lane Closure – 6 a.m. – 3 pm.
- The eastbound University Drive right lane will be closed for street sweeping.
- Northbound mainlanes between Harvey Mitchell Parkway and Harvey Road – Full Closure – 7:30 p.m. – 6:30 a.m.
- All traffic must exit through the Harvey Mitchell Parkway exit ramp and may re-enter the mainlanes using the entrance ramp just south of Harvey Road. Additionally, the northbound entrance ramp just south of Harvey Mitchell Parkway and Southwest Parkway will be closed.
- Southbound mainlanes between University Drive and Harvey Mitchell Parkway – Single-lane Closure – 7:30 p.m. – 6:30 a.m.
- The southbound mainlanes left lane will be closed for paving operations.
- Northbound frontage road between Harvey Road and University Drive – Single-lane Closure – 7:30 p.m. – 6:30 a.m.
- The northbound frontage road left lane will be closed for earthwork operations. Additionally, the exit ramp and the entrance ramp just south of University Drive will be closed. Traffic may re-enter the mainlanes just south of Briarcrest Drive.
Friday, November 20
- Northbound frontage road between Harvey Road and University Drive – Single-lane Closure – 6 a.m. – 3 p.m.
- The northbound frontage road right lane will be closed for street cleaning operations.
- Eastbound University between SH 6 frontage road and Veterans Parkway – Single-lane Closure – 6 a.m. – 3 pm.
- The eastbound University Drive right lane will be closed for street sweeping.
- Northbound mainlanes between Harvey Mitchell Parkway and Harvey Road – Full Closure – 7:30 p.m. – 6:30 a.m.
- All traffic must exit through the Harvey Mitchell Parkway exit ramp and may re-enter the mainlanes using the entrance ramp just south of Harvey Road. Additionally, the northbound entrance ramp just south of Harvey Mitchell Parkway and Southwest Parkway will be closed.
- Southbound mainlanes between University Drive and Harvey Mitchell Parkway – Single-lane Closure – 7:30 p.m. – 6:30 a.m.
- The southbound mainlanes left lane will be closed for paving operations.
- Northbound frontage road between Harvey Road and University Drive – Single-lane Closure – 7:30 p.m. – 6:30 a.m.
- The northbound frontage road left lane will be closed for earthwork operations. Additionally, the exit ramp and the entrance ramp just south of University Drive will be closed. Traffic may re-enter the mainlanes just south of Briarcrest Drive.
Saturday, November 21
- Northbound frontage road between Harvey Road and University Drive – Single-lane Closure – 6 a.m. – 3 p.m.
- The northbound frontage road right lane will be closed for street cleaning operations.
- Eastbound University between SH 6 frontage road and Veterans Parkway – Single-lane Closure – 6 a.m. – 3 pm.
- The eastbound University Drive right lane will be closed for street sweeping.
Looking ahead
Here's what can be expected in the next six months:
- Two main lanes in each direction will be maintained throughout construction
- Majority of the work will be on the main lanes
- Construction of temporary pavement and retaining walls