Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
March, 2019 (FY 2019) | (see Links) |
SEP 2018 | OCT 2018 | NOV 2018 | DEC 2018 | JAN 2019 | FEB 2019 | MAR 2019 | APR 2019 | MAY 2019 | JUN 2019 | JUL 2019 | AUG 2019 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0910-08-068 | Anderson/ Tyler | CR | Actual | $643,684 | 6 | REPLACE BRIDGE AND APPROACHES | 4.0 |
0200-01-091 | Angelina/ Lufkin | US 69 | Actual | $122,361 | 1 | INSTALL TRAFFIC SIGNAL | 0.0 |
0336-03-071 | Angelina/ Lufkin | SH 103 | Actual | $1,219,821 | 11 | WIDENING EXISTING PAVING FOR ADDITIONAL TURNING LANES | 5.0 |
0017-04-042 | Atascosa/ San Antonio | IH 35 | Actual | $14,318,967 | 1 | BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ON | 5.0 |
0915-13-028 | Atascosa/ San Antonio | CR | Actual | $639,796 | 6 | REPLACE BRIDGE AND APPROACHES | 5.0 |
0184-03-040 | Bell/ Waco | SH 53 | Actual | $1,473,450 | 1 | PREVENTIVE MAINTENANCE | 3.0 |
2452-03-123 | Bexar/ San Antonio | SL 1604 | Actual | $3,967,436 | 1 | BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ON | 0.0 |
0598-02-110 | Brazoria/ Houston | SH 288 | Actual | $2,993,148 | 1 | CONSTRUCT U-TURNS AND ACCELERATION/DECELERATION LANES | 2.5 |
0050-01-086 | Brazos/ Bryan | BS 6-R | Actual | $8,773,603 | 1 | CONCRETE PAVEMENT REPAIR | 0.0 |
2242-02-022 | Chambers/ Beaumont | FM 2354 | Actual | $5,959,869 | 1 | ADD CENTER LEFT TURN LANE AND WIDEN SHOULDERS, ADD NB LEFT | 8.0 |
0367-01-069 | Chambers/ Beaumont | SH 124 | Actual | $1,948,840 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0047-06-165 | Collin/ Dallas | US 75 | Actual | $1,691,452 | 1 | FULL DEPTH CONCRETE REPAIR | 0.0 |
0183-01-045 | Comanche/ Brownwood | SH 36 | Actual | $1,497,744 | 1 | MILL AND OVERLAY | 0.0 |
0903-15-085 | Cooke/ Wichita Falls | CR | Actual | $1,063,507 | 6 | REPLACE BRIDGE AND APPROACHES | 4.0 |
0918-00-287 | Dallas/ Dallas | VA | Actual | $700,409 | 1 | WRONG WAY DRIVING IMPLEMENTATION TO PREVENT WRONG WAY | 0.0 |
0095-13-043 | Dallas/ Dallas | IH 20 | Actual | $28,484,199 | 1 | FULL DEPTH CONCRETE REPAIR AND OVERLAY EB AND WB | 4.0 |
1905-01-009 | Dawson/ Lubbock | FM 2052 | Actual | $3,561,049 | 1 | WIDENING AND RESTORING PAVEMENT | 3.0 |
0941-02-019 | Dewitt/ Yoakum | FM 952 | Actual | $1,199,299 | 6 | REPLACE BRIDGE AND APPROACHES | 4.0 |
0906-00-177 | Ector/ Odessa | VA | Actual | $5,023,104 | 1 | PAVEMENT MARKINGS | 0.0 |
0906-00-176 | Ector/ Odessa | VA | Actual | $505,850 | 1 | PAVEMENT MARKINGS | 0.0 |
0172-05-122 | Ellis/ Dallas | US 287 | Actual | $9,679,974 | 1 | PAVEMENT REPAIR AND OVERLAY | 5.0 |
0909-38-081 | Falls/ Waco | CR | Actual | $1,400,650 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0558-06-016 | Glasscock/ San Angelo | RM 33 | Actual | $5,712,544 | 1 | RESTORATION OF EXISTING ROAD | 3.0 |
0047-18-081 | Grayson/ Paris | US 75 | Actual | $1,838,653 | 1 | REPAIR SLOPE FAILURE AND ROADWAY | 4.0 |
0097-02-039 | Hardeman/ Childress | SH 6 | Actual | $4,678,747 | 1 | REHABILITATION OF EXISTING ROAD | 0.0 |
0912-72-371 | Harris/ Houston | VA | Actual | $8,869,186 | 3 | TURN LNS, AUX LNS, RAISED MEDIANS & GEOMETRIC IMPROVEMENTS | 7.5 |
1062-04-022 | Harris/ Houston | FM 2100 | Actual | $44,177,829 | 2M | WIDEN TO 4-LANE DIVIDED | 9.0 |
0096-09-077 | Harrison/ Atlanta | US 80 | Actual | $427,824 | 8 | IMPROVE TRAFIC SIGNAL | 0.0 |
0632-04-032 | Harrison/ Atlanta | FM 451 | Actual | $5,283,882 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE | 0.0 |
0016-03-119 | Hays/ Austin | IH 35 | Actual | $11,314,433 | 1 | MILL, SEAL AND PFC-C INLAY | 0.0 |
0342-01-074 | Hidalgo/ Pharr | SH 107 | Actual | $20,670,142 | 1 | CONSTRUCT 6 LANE DIVIDED RURAL | 6.0 |
0698-03-095 | Hidalgo/ Pharr | FM 88 | Actual | $1,875,432 | 8 | INSTALL/UPGRADE ROADWAY LIGHTING | 4.0 |
0069-01-057 | Howard/ Abilene | US 87 | Actual | $1,165,075 | 11 | DRAINAGE WORK | 4.5 |
0200-14-086 | Jefferson/ Beaumont | US 69 | Actual | $2,357,356 | 11 | REMOVE EXISTING CONCRETE, RECONSTRUCT | 3.0 |
2249-01-008 | Kaufman/ Dallas | FM 460 | Actual | $1,573,310 | 1 | REHABILITATE EXISTING ROADWAY | 5.0 |
0142-02-029 | Kerr/ San Antonio | IH 10 | Actual | $15,113,463 | 1 | BASE REPAIR, SEALCOAT, OVERLAY & PAVEMENT MARKINGS ON | 0.0 |
0913-29-054 | Lavaca/ Yoakum | CS | Actual | $199,277 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0114-07-036 | Lee/ Austin | US 290 | Actual | $30,993,748 | 1 | RECONSTRUCT EXISTING 4-LN UNDIVIDED ROADWAY TO A 4-LN | 4.5 |
0177-03-104 | Liberty/ Beaumont | US 59 | Actual | $1,639,621 | 11 | PFC MILL AND INLAY | 0.0 |
0074-01-055 | Live Oak/ Corpus Christi | IH 37 | Actual | $1,957,013 | 1 | REHAB AND WIDEN-WEST FRTG LANES ONLY | 0.0 |
0150-04-047 | Llano/ Austin | SH 29 | Actual | $3,688,178 | 11 | CONSTRUCT SUPER 2 PASSING LANES | 7.0 |
0905-00-096 | Lubbock/ Lubbock | VA | Actual | $300,745 | 1 | SAFETY | 0.0 |
0913-21-050 | Matagorda/ Yoakum | CR | Actual | $1,283,355 | 3 | HIGHWAY IMPROVEMENT | 0.0 |
2897-01-017 | Montgomery/ Houston | FM 830 | Actual | $2,642,386 | 1 | FULL DEPTH REPAIR, PAVEMENT MARKINGS AND 2 IN OVERLAY | 6.0 |
1912-02-014 | Montgomery/ Houston | FM 2090 | Actual | $2,387,733 | 1 | FULL DEPTH REPAIR, PAVEMENT MARKINGS AND 2 IN OVERLAY | 5.0 |
1407-01-028 | Nacogdoches/ Lufkin | FM 1275 | Actual | $783,095 | 8 | SAFETY TREAT FIXED OBJECTS | 3.0 |
0006-02-115 | Nolan/ Abilene | IH 20 | Actual | $10,712,998 | 1 | MILL AND FILL WITH SPOT PAVEMENT REPAIR | 5.5 |
0074-06-219 | Nueces/ Corpus Christi | IH 37 | Actual | $10,134,337 | 1 | MILL,UNDERSEAL,OVERLAY AND NOVACHIP | 3.0 |
0916-00-212 | Nueces/ Corpus Christi | VA | Actual | $2,165,860 | 1 | 2019 DISTRICT WIDE SIGN REPLACEMENT | 0.0 |
0030-02-052 | Ochiltree/ Amarillo | US 83 | Actual | $14,178,590 | 11 | OVERLAY | 0.0 |
0030-02-053 | Ochiltree/ Amarillo | US 83 | Actual | $1,949,942 | 11 | IMPROVE TRAFFIC SIGNALS & INTERCONNECT SIGNALS | 0.0 |
0784-04-023 | Orange/ Beaumont | FM 1131 | Actual | $1,003,050 | 8 | MODERNIZE BRIDGE RAIL AND APPROACH GUARDRAIL, SAFETY TREAT | 6.0 |
0313-02-059 | Parker/ Ft Worth | FM 51 | Actual | $6,808,813 | 1 | RESURFACE ROADWAY | 5.0 |
0168-01-030 | Parmer/ Lubbock | US 60 | Actual | $23,320,829 | 1 | REHABILITATION OF EXISTING ROADWAY | 2.0 |
0206-07-062 | Rusk/ Tyler | US 79 | Actual | $2,171,415 | 1 | REHABILITATE AND RESURFACE ROADWAY | 0.0 |
0203-08-016 | Smith/ Tyler | FM 1253 | Actual | $1,185,936 | 8 | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | 0.0 |
0910-16-140 | Smith/ Tyler | CR | Actual | $819,041 | 6 | REPLACE BRIDGE AND APPROACHES | 4.0 |
0910-16-039 | Smith/ Tyler | CS | Actual | $501,859 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0902-90-113 | Tarrant/ Ft Worth | VA | Actual | $3,846,931 | 1 | LONGLINE MULTIPOLYMER STRIPING (60 & 90 MIL); RAISED PVMT | 0.0 |
0363-01-143 | Tarrant/ Ft Worth | SH 26 | Actual | $2,662,513 | 1 | REPAIR BASE FAILURES, MILL, HMAC OVERLAY, PAVEMENT MARKINGS | 0.0 |
0699-01-055 | Taylor/ Abilene | FM 89 | Actual | $1,877,959 | 1 | MILL AND OVERLAY | 0.0 |
1176-02-019 | Titus/ Atlanta | FM 899 | Actual | $1,275,464 | 6 | REPLACE BRIDGE AND APPROACHES | 3.0 |
0010-06-042 | Titus/ Atlanta | US 67 | Actual | $3,235,831 | 8 | SAFETY TREAT FIXED OBJECTS | 0.0 |
0914-00-399 | Travis/ Austin | VA | Actual | $1,944,393 | 1 | FY 2019 NON-SITE SPECIFIC SIGNALS | 2.5 |
0114-11-080 | Waller/ Houston | US 290 | Actual | $280,000 | 8 | INSTALL MEDIAN BARRIER | 0.0 |
0275-12-074 | Wheeler/ Childress | IH 40 | Actual | $4,818,994 | 6 | BRIDGE MAINTENANCE (ADD VEHICLE DEFLECTION WALLS) | 0.0 |
0043-20-021 | Wilbarger/ Wichita Falls | BU 287F | Actual | $518,311 | 8 | INSTALL SIDEWALKS | 5.0 |
0015-08-141 | Williamson/ Austin | IH 35 | Actual | $12,596,512 | 2M | BRIDGE REPLACEMENT | 6.0 |
0015-08-151 | Williamson/ Austin | IH 35 | Actual | $5,094,096 | 1 | MILL, SEAL AND OVERLAY SOUTHBOUND MAIN LANES | 0.0 |
0910-35-033 | Wood/ Tyler | CR | Actual | $389,734 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0401-03-026 | Wood/ Tyler | SH 154 | Actual | $897,151 | 8 | INSTALL PROFILE EDGELINE MARKINGS | 0.0 |
1390-03-005 | Wood/ Tyler | FM 1254 | Actual | $1,673,512 | 6 | REPLACE BRIDGE & APPROACHES | 6.0 |
|