Letting Schedule for Houston District (FY 2019)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Houston District (FY 2019) |
Brazoria | Fort Bend | Galveston | Harris | Montgomery | Waller | | |||||||
Brazoria County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0912-31-291 | VA | Actual | Dec 2018 | $3,632,816 | 3 | CONSTRUCT GREEN TEE TERRACE BIKE AND PEDESTRIAN TRAIL | 0.0 |
0178-03-157 | SH 35 | Actual | Aug 2019 | $122,225 | 10 | EMERGENCY RELIEF | 0.0 |
0111-09-043 | BS 288B | Actual | Jan 2019 | $296,773 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0587-01-066 | FM 1495 | Actual | Aug 2019 | $84,224 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0598-02-110 | SH 288 | Actual | Mar 2019 | $2,993,148 | 1 | CONSTRUCT U-TURNS AND ACCELERATION/DECELERATION LANES | 2.5 |
0912-31-303 | CR | Actual | Aug 2019 | $17,062,000 | 3 | WIDEN ROAD - ADD LANES | 0.0 |
0188-06-055 | SH 36 | Actual | Aug 2019 | $294,500 | 10 | EMERGENCY RELIEF | 0.0 |
0912-31-311 | CR | Actual | Oct 2018 | $33,184,000 | 3 | RECONSTRUCT & WIDEN FROM 2 TO 4 LANES, ADD MEDIAN & | 0.0 |
1003-01-100 | FM 523 | Actual | Aug 2019 | $42,112 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0587-01-065 | FM 1495 | Actual | Aug 2019 | $60,160 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
1003-01-099 | FM 523 | Actual | Aug 2019 | $54,144 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0111-08-122 | BS 288B | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0912-31-296 | CR | Actual | May 2019 | $2,537,069 | 6 | BRIDGE REPLACEMENT | 7.0 |
0586-01-067 | SH 332 | Actual | Oct 2018 | $468,971 | 1 | REMOVE AND REPLACE DRAINAGE STRUCTURE | 0.0 |
0912-31-292 | VA | Actual | Oct 2018 | $1,624,755 | 3 | CONSTRUCT SHADOW CREEK BIKE AND PEDESTRIAN TRAIL | 0.0 |
0587-01-063 | FM 1495 | Actual | Sep 2018 | $1,227,737 | 1 | MILLING, 1.5" ACP OVERLAY AND PAVEMENT MARKINGS | 0.0 |
1414-02-017 | FM 528 | Actual | Aug 2019 | $61,113 | 10 | EMERGENCY RELIEF | 0.0 |
1524-01-083 | SH 288 | Actual | Aug 2019 | $391,837 | 10 | EMERGENCY RELIEF | 0.0 |
Fort Bend County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
3048-01-017 | FM 2977 | Actual | Aug 2019 | $2,421,353 | 1 | SURFACING/ROADWAY RESTORATION | 10.0 |
0188-09-042 | FM 723 | Actual | Aug 2019 | $2,480,312 | 2M | WIDEN ROAD - ADD LANES | 8.5 |
0838-03-024 | FM 361 | Actual | May 2019 | $7,168,365 | 1 | SURFACING/ROADWAY RESTORATION | 7.0 |
0271-05-044 | IH 10 | Actual | Sep 2018 | $349,029 | 1 | INSTALL PAVEMENT MARKINGS | 0.0 |
0188-01-039 | SH 36 | Actual | May 2019 | $770,842 | 1 | SURFACING/ROADWAY RESTORATION | 3.0 |
0027-08-181 | US 90A | Actual | Sep 2018 | $11,000 | 10 | REMOVED DAMAGED CABINET AND INSTALLED NEW CABINET | 0.0 |
2817-01-010 | FM 2759 | Actual | Nov 2018 | $5,461,236 | 1 | ADD 4' SHOULDERS, BASE REPAIR, 1.5" ACP OVERLAY, PAVEMENT | 7.0 |
Galveston County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
1607-01-053 | FM 1764 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0367-03-037 | SH 87 | Actual | Feb 2019 | $7,058,422 | 1 | BASE REPAIR, MILLING AND 1.5" ACP OVERLAY | 0.0 |
0367-06-063 | SH 87 | Actual | Aug 2019 | $902,321 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
3049-01-034 | FM 646 | Actual | Feb 2019 | $11,455 | 10 | REMOVE AND INSTALL NEW CABINET WITH RISER | 0.0 |
0051-09-024 | FM 3005 | Actual | May 2019 | $44,161,821 | 1 | SURFACING/ROADWAY RESTORATION | 7.0 |
0389-11-060 | SL 197 | Actual | Aug 2019 | $302,400 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
1844-02-023 | FM 2351 | Actual | Feb 2019 | $11,455 | 10 | REMOVE AND INSTALL NEW CABINET AND RISER | 0.0 |
0051-03-111 | SH 3 | Actual | Apr 2019 | $1,680,431 | 1 | BASE REPAIR, SEAL COAT, 0 .75 IN TOM-F AND 1 IN TOM-C | 0.0 |
0976-03-108 | FM 518 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET AND RISER | 0.0 |
0976-03-107 | FM 518 | Actual | Feb 2019 | $11,455 | 10 | REMOVE AND INSTALL NEW CABINET AND RISER | 0.0 |
0978-01-040 | FM 517 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0976-04-021 | FM 2094 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0686-02-028 | FM 1765 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0051-04-067 | SH 87 | Actual | Jul 2019 | $8,231,409 | 1 | SURFACING/ROADWAY RESTORATION | 7.0 |
0051-03-115 | SH 3 | Actual | Sep 2018 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0389-06-108 | SH 146 | Actual | Sep 2018 | $2,665,165 | 1 | BASE REPAIR, MILLING, 1" THIN OVER MIXTURE AND 1.5" ACP | 1.5 |
0978-01-041 | FM 517 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0051-03-112 | SH 3 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0367-05-050 | SH 87 | Actual | Jul 2019 | $26,142,000 | 10 | FERRY OPERATION PROJECTS | 0.0 |
1607-01-052 | FM 1764 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0051-09-120 | FM 3005 | Actual | Feb 2019 | $3,307,657 | 1 | BASE REPAIR, MILLING, SEAL COAT, 3/4 INCH TOM-F, 1 INCH | 0.0 |
0912-73-183 | CR | Actual | May 2019 | $5,831,585 | 10 | CONSTRUCT NEW ROADS,PARKING LOTS AND CAMPSITE PULLOUTS FOR | 0.0 |
0912-73-216 | VA | Actual | May 2019 | $3,949,318 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0686-02-027 | FM 1765 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0051-03-118 | SH 3 | Actual | Aug 2019 | $187,200 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0686-01-050 | FM 1765 | Actual | Feb 2019 | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0978-02-080 | FM 517 | Actual | Aug 2019 | $36,096 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0912-73-208 | VA | Tentative | Aug 2019 | $2,454,000 | 3 | CONSTRUCT PARK AND RIDE WITH 400 AUTO AND 40 BUS PARKING | 0.0 |
0912-73-206 | CS | Actual | Aug 2019 | $863,858 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
3595-01-019 | SH 275 | Actual | Aug 2019 | $1,535,207 | 3 | HIGHWAY IMPROVEMENT | 0.0 |
3595-01-021 | SH 275 | Actual | Aug 2019 | $71,968 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0500-04-105 | IH 45 | Actual | Aug 2019 | $148,368,606 | 4 | WIDEN ROAD - ADD LANES | 8.5 |
0912-73-207 | CS | Actual | Aug 2019 | $1,756,000 | 3 | SURFACING/ROADWAY RESTORATION | 0.0 |
Harris County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0912-72-519 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-518 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-429 | CR | Actual | Apr 2019 | $27,150 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-517 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-430 | CR | Actual | Apr 2019 | $28,528 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-520 | CS | Actual | Apr 2019 | $18,536 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-432 | CR | Actual | Apr 2019 | $17,201 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-522 | CS | Actual | Apr 2019 | $21,036 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-433 | CR | Actual | Apr 2019 | $17,245 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-434 | CR | Actual | Apr 2019 | $17,252 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-521 | CS | Actual | Apr 2019 | $18,536 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-431 | CR | Actual | Apr 2019 | $28,817 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-516 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-505 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-501 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-506 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-435 | CR | Actual | Apr 2019 | $17,252 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-442 | CR | Actual | Apr 2019 | $16,379 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-439 | CR | Actual | Apr 2019 | $17,252 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-440 | CR | Actual | Apr 2019 | $15,434 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-441 | CR | Actual | Apr 2019 | $18,737 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-438 | CR | Actual | Apr 2019 | $17,289 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-513 | CS | Actual | Apr 2019 | $18,536 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-512 | CS | Actual | Apr 2019 | $21,036 | 10 | REMOVE DAMAGED TRAFFIC SIGNAL AND INSTALL NEW SIGNAL | 0.0 |
0912-72-515 | CS | Actual | Apr 2019 | $22,463 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-514 | CS | Actual | Apr 2019 | $18,536 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-511 | CS | Actual | Apr 2019 | $18,536 | 10 | REMOVE DAMAGED TRAFFIC SIGNAL AND INSTALL NEW SIGNAL | 0.0 |
0912-72-508 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-507 | CS | Actual | Apr 2019 | $18,536 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-510 | CS | Actual | Apr 2019 | $18,536 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-509 | CS | Actual | Apr 2019 | $22,463 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-428 | CR | Actual | Apr 2019 | $22,100 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-00-549 | VA | Actual | Dec 2018 | $4,438,000 | 3 | TRAVEL DEMAND MANAGEMENT, MARKETING, OUTREACH AND PUBLIC | 0.0 |
0912-00-532 | VA | Actual | Dec 2018 | $2,055,278 | 1 | INSTALL NEW TRAFFIC SIGNALS | 0.0 |
2941-02-055 | FM 2920 | Actual | Nov 2018 | $8,623,632 | 1 | BASE REPAIR, 1.25 INCH MILLING, THIN OVERLAY MIX, METAL | 0.0 |
0271-07-322 | IH 10 | Actual | Jan 2019 | $682,889 | 1 | INSTALL STRIPING | 0.0 |
0177-07-114 | IH 69 | Actual | Jan 2019 | $1,106,323 | 1 | BRIDGE DECK REPLACEMENT | 0.0 |
0912-72-417 | VA | Actual | Dec 2018 | $5,252,500 | 3 | CONSTRUCT GEOMETRIC IMPROVEMENTS AND TRAFFIC SIGNAL & | 0.0 |
0912-72-445 | CR | Actual | Feb 2019 | $29,056 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-374 | CR | Actual | Oct 2018 | $12,738,812 | 3 | WIDEN ROADWAY AND INSTALL SIX RAIL CROSSINGS | 0.0 |
0912-72-372 | VA | Actual | Oct 2018 | $5,253,750 | 3 | CONSTRUCT GEOMETRIC IMPROVEMENTS AND TRAFFIC SIGNAL & | 0.0 |
0912-72-448 | CR | Actual | Feb 2019 | $30,176 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-00-597 | VA | Actual | Nov 2018 | $125,000 | 10 | ENGINEERING DESIGN/STUDY | 0.0 |
0389-05-124 | SH 146 | Actual | Nov 2018 | $2,153,827 | 1 | REMOVE MEDIAN RAIL W/FENCING & REPL W/ CONC TRAFFIC BARRIER | 0.0 |
0912-72-416 | VA | Actual | Oct 2018 | $6,653,750 | 3 | CONSTRUCT GEOMETRIC IMPROVEMENTS AND TRAFFIC SIGNAL & | 0.0 |
1685-05-121 | SH 6 | Actual | Jan 2019 | $22,463 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
1685-05-110 | SH 6 | Actual | Jan 2019 | $3,002,721 | 10 | CONSTRUCT SIDEWALKS | 7.0 |
0912-72-500 | CS | Actual | Jan 2019 | $21,036 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0271-15-090 | IH 610 | Actual | Feb 2019 | $1,096,630 | 3 | UPGRADE STORM SEWERS | 0.0 |
0027-13-212 | IH 69 | Actual | Feb 2019 | $5,319,884 | 1 | UPGRADE HIGH MAST & UNDERPASS LIGHTING | 0.0 |
3256-01-113 | SL 8 | Actual | Jan 2019 | $18,536 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-499 | CS | Actual | Jan 2019 | $22,463 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-00-596 | VA | Actual | Jan 2019 | $2,082,499 | 3 | CONDUCT 9 LIVABLE CENTER STUDIES (NON-LETTING) | 0.0 |
0912-00-530 | VA | Actual | Jan 2019 | $3,000,000 | 1 | ITS SUPPORT | 0.0 |
0500-03-594 | IH 45 | Actual | Jan 2019 | $1,772,367 | 1 | MILLING, 2 ACP OVERLAY, PAVEMENT MARKINGS AND GUARDFENCE | 0.0 |
0912-72-498 | CS | Actual | Jan 2019 | $22,463 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-497 | CS | Actual | Jan 2019 | $18,536 | 10 | REMOVED DAMAGED CABINET, INSTALLED NEW CABINET | 0.0 |
0912-70-145 | CS | Actual | Jan 2019 | $18,536 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
0912-72-314 | VA | Actual | Sep 2018 | $6,019,462 | 3 | CONSTRUCT MULTI-USE PATH | 7.0 |
0178-09-029 | SS 5 | Actual | Apr 2019 | $21,036 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
0271-16-148 | IH 610 | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0500-03-621 | IH 45 | Actual | Apr 2019 | $21,036 | 10 | EMERGENCY RELIEF | 0.0 |
0051-02-101 | SH 3 | Actual | Apr 2019 | $12,726,941 | 1 | ADD BIKE LANES, MILLING W/ ASPHALT OVERLAY, PAVEMENT | 8.0 |
0110-06-146 | IH 45 | Actual | Apr 2019 | $18,536 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
0177-07-116 | IH 69 | Actual | Apr 2019 | $21,036 | 10 | EMERGENCY RELIEF | 0.0 |
0598-01-103 | SH 288 | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-425 | CR | Actual | Apr 2019 | $17,201 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-426 | CR | Actual | Apr 2019 | $27,150 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-427 | CR | Actual | Apr 2019 | $28,268 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-363 | CS | Actual | Apr 2019 | $16,233,336 | 3 | RECON ROADWAY INCLUDING CURB, GUTTER SIDEWALKS, LANDSCAPING, | 9.0 |
0912-72-423 | CR | Actual | Apr 2019 | $16,626 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-424 | CR | Actual | Apr 2019 | $17,201 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-00-552 | VA | Actual | Sep 2018 | $15,000,000 | 3 | CLEAN CITIES/CLEAN VEHICLES PROGRAM (ENGINE/VEHICLE | 0.0 |
0508-01-368 | IH 10 | Actual | Sep 2018 | $10,771,028 | 10 | REMOVED UNDERWATER DEBRIS | 0.0 |
0271-16-140 | IH 610 | Actual | Sep 2018 | $125,776,787 | 1 | RECONSTRUCT MAINLANES, FRONTAGE ROAD AND CONSTRUCT OVERPASS | 8.0 |
0912-70-125 | CR | Actual | Sep 2018 | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755624C) | 0.0 |
0912-70-124 | CR | Actual | Sep 2018 | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755622N) | 0.0 |
0912-00-554 | VA | Actual | Sep 2018 | $2,000,000 | 7 | REGIONAL ITS INFRASTRUCTURE - HARDWARE/SOFTWARE, UTILITIES | 0.0 |
0912-72-449 | CR | Actual | Feb 2019 | $17,252 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-371 | VA | Actual | Mar 2019 | $8,869,186 | 3 | TURN LNS, AUX LNS, RAISED MEDIANS & GEOMETRIC IMPROVEMENTS | 7.5 |
1062-04-022 | FM 2100 | Actual | Mar 2019 | $44,177,829 | 2M | WIDEN TO 4-LANE DIVIDED | 9.0 |
0028-02-096 | US 90 | Actual | Apr 2019 | $18,536 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-450 | CR | Actual | Feb 2019 | $20,435 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-453 | CR | Actual | Feb 2019 | $28,268 | 10 | REMOVE AND REPLACE TRAFFIC SIGNALL CONTROLLER CABINET | 0.0 |
0912-72-539 | CR | Actual | Feb 2019 | $914,454 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-523 | CS | Actual | Apr 2019 | $22,463 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
1685-05-131 | SH 6 | Actual | Aug 2019 | $18,520 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-340 | CS | Actual | Jul 2019 | $13,802,148 | 3 | WIDEN ROAD - ADD LANES | 6.0 |
0981-01-116 | FM 528 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0912-70-093 | CS | Actual | Jul 2019 | $4,190,235 | 6 | BRIDGE REPLACEMENT | 8.0 |
3510-05-043 | SH 99 | Actual | Aug 2019 | $11,773,279 | 3 | INSTALL/UPGRADE ROADWAY LIGHTING | 0.0 |
3256-03-099 | SL 8 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0981-01-115 | FM 528 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-373 | CS | Actual | Jul 2019 | $14,590,643 | 3 | SURFACING/ROADWAY RESTORATION | 11.0 |
0981-01-111 | NASA 1 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
1062-04-058 | FM 2100 | Actual | Jul 2019 | $22,119,617 | 2M | WIDEN ROAD - ADD LANES | 9.0 |
0981-01-114 | FM 528 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0981-01-113 | NASA 1 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0981-01-112 | NASA 1 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
3510-05-045 | SH 99 | Actual | Aug 2019 | $4,084,577 | 3 | LANDSCAPE DEVELOPMENT | 0.0 |
3510-05-042 | SH 99 | Actual | May 2019 | $207,059 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
0271-14-237 | IH 610 | Actual | Jun 2019 | $767,095 | 6 | BRIDGE MAINTENANCE | 0.0 |
1812-01-023 | FM 1942 | Actual | May 2019 | $3,829,630 | 1 | SURFACING/ROADWAY RESTORATION | 7.0 |
0027-13-234 | IH 69 | Actual | Jun 2019 | $1,057,721 | 6 | BRIDGE MAINTENANCE | 0.0 |
0028-01-098 | BU 90-U | Actual | Jun 2019 | $2,200,398 | 1 | DRAINAGE IMPROVEMENTS | 5.0 |
0027-13-222 | IH 69 | Actual | Jun 2019 | $3,952,820 | 1 | INSTALL/UPGRADE ROADWAY LIGHTING | 0.0 |
0389-13-061 | SH 146 | Actual | Jun 2019 | $1,863,990 | 6 | BRIDGE MAINTENANCE | 0.0 |
0271-14-235 | IH 610 | Actual | Jul 2019 | $1,559,230 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
3510-06-017 | SH 99 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
3510-06-016 | SH 99 | Actual | Aug 2019 | $11,455 | 10 | EMERGENCY RELIEF | 0.0 |
3256-02-095 | SL 8 | Actual | Jun 2019 | $1,794,587 | 1 | SURFACING/ROADWAY RESTORATION | 3.5 |
0050-09-095 | US 290 | Actual | Jul 2019 | $2,139,748 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0110-05-132 | IH 45 | Actual | Jul 2019 | $1,733,904 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0720-03-134 | SH 249 | Actual | May 2019 | $3,632,253 | 2M | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 0.0 |
0500-03-631 | IH 45 | Actual | Aug 2019 | $1,138,297 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
3256-01-114 | SL 8 | Actual | Apr 2019 | $21,036 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0508-01-371 | IH 10 | Actual | Aug 2019 | $6,177,976 | 10 | EMERGENCY RELIEF | 0.0 |
0720-03-137 | SH 249 | Actual | May 2019 | $2,328,969 | 8 | HAZARD ELIMINATION & SAFETY | 2.5 |
0508-01-367 | IH 10 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
1685-05-120 | SH 6 | Actual | Apr 2019 | $21,036 | 10 | REPLACE TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS, AND | 0.0 |
0912-72-526 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
0912-72-525 | CS | Actual | Apr 2019 | $18,536 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-524 | CS | Actual | Apr 2019 | $22,463 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-529 | CR | Actual | Apr 2019 | $17,202 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-528 | CS | Actual | Apr 2019 | $22,463 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
0912-72-527 | CS | Actual | Apr 2019 | $21,036 | 10 | REPLACED TRAFFIC SIGNAL CABINET, ELECTRICAL COMPONENTS AND | 0.0 |
0508-01-372 | IH 10 | Actual | Aug 2019 | $300,141 | 10 | EMERGENCY RELIEF | 0.0 |
0051-02-107 | SH 3 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0110-05-131 | IH 45 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0177-06-087 | IH 69 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0976-01-040 | FM 865 | Actual | Aug 2019 | $150,845 | 8 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0028-01-102 | BU 90-U | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0028-01-103 | BU 90-U | Actual | Aug 2019 | $1,302,428 | 10 | EMERGENCY RELIEF | 0.0 |
0912-72-566 | VA | Actual | Aug 2019 | $2,679,709 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0500-03-624 | IH 45 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0271-16-150 | IH 610 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
0912-70-131 | CS | Actual | May 2019 | $18,536 | 10 | EMERGENCY RELIEF | 0.0 |
0912-00-476 | VA | Actual | Aug 2019 | $5,503,750 | 3 | COMMUTE SOLUTIONS PROGRAM | 0.0 |
0720-03-142 | SH 249 | Actual | Aug 2019 | $11,455 | 10 | EMERGENCY RELIEF | 0.0 |
0271-14-238 | IH 610 | Actual | Aug 2019 | $1,579,490 | 10 | EMERGENCY RELIEF | 0.0 |
Montgomery County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
3538-01-035 | SH 242 | Actual | May 2019 | $41,207,493 | 2M | WIDEN ROAD - ADD LANES | 8.5 |
3538-01-052 | SH 242 | Actual | May 2019 | $441,763 | 1 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0177-05-113 | IH 69 | Actual | Sep 2018 | $1,602,335 | 1 | CONSTRUCT DETENTION POND | 7.5 |
0523-10-043 | FM 1488 | Actual | Dec 2018 | $703,503 | 1 | ADD RIGHT TURN LANE | 0.0 |
0177-05-117 | IH 69 | Actual | Aug 2019 | $219,322 | 10 | EMERGENCY RELIEF | 0.0 |
0338-04-081 | SH 105 | Actual | Aug 2019 | $11,000 | 10 | EMERGENCY RELIEF | 0.0 |
3538-01-053 | SH 242 | Actual | Jul 2019 | $608,798 | 6 | BRIDGE MAINTENANCE | 0.0 |
0912-37-235 | CR | Actual | Jun 2019 | $250,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0912-37-236 | CR | Actual | Jun 2019 | $250,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0110-02-027 | SH 75 | Actual | Jul 2019 | $4,974,350 | 6 | BRIDGE REPLACEMENT | 6.0 |
2897-01-017 | FM 830 | Actual | Mar 2019 | $2,642,386 | 1 | FULL DEPTH REPAIR, PAVEMENT MARKINGS AND 2 IN OVERLAY | 6.0 |
1912-01-023 | FM 2090 | Actual | Aug 2019 | $11,455 | 10 | EMERGENCY RELIEF | 0.0 |
1416-03-019 | FM 1486 | Actual | Aug 2019 | $55,360 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
3538-01-036 | SH 242 | Actual | Aug 2019 | $66,192,353 | 2M | WIDEN ROAD - ADD LANES | 8.5 |
1912-02-015 | FM 2090 | Actual | Aug 2019 | $30,080 | 10 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
1912-02-014 | FM 2090 | Actual | Mar 2019 | $2,387,733 | 1 | FULL DEPTH REPAIR, PAVEMENT MARKINGS AND 2 IN OVERLAY | 5.0 |
Waller County |
|||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description | DBE Goal |
0912-56-052 | VA | Actual | Oct 2018 | $1,276,594 | 3 | CONSTRUCT INTERSECTION IMPROVEMENTS, SIDEWALKS, PEDESTRIAN | 6.0 |
0114-11-080 | US 290 | Actual | Mar 2019 | $280,000 | 8 | INSTALL MEDIAN BARRIER | 0.0 |
0944-02-011 | FM 362 | Actual | Aug 2019 | $728,451 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
1418-01-012 | FM 1489 | Actual | Jan 2019 | $1,444,822 | 1 | 1.5 IN ACP OVERLAY | 0.0 |
|