Detail Letting Schedule for Caldwell County (FY 2014)

Last Update: Monday, May 20, 2013
Caldwell County (FY 2014)

CCSJ: 0914-22-056

District: Austin Let Date: MAY 2014
Highway: CR Let Status: Tentative
Project ID: BR 2013(194) CSJ: 0914-22-055
Description: REPLACE BRIDGE & APPROACHES Handling
Code:
 
Limits From: ON OAK GROVE RD (CR 127) AT Fund Cat: 6
Limits To: W FORK PLUM CRK (STR AA02-28-002) Estimate: $307,700
Length: 0.1 Miles Actual:  
 
District: Austin Let Date: MAY 2014
Highway: CR Let Status: Tentative
Project ID: BR 2013(195) CSJ: 0914-22-056
Description: REPLACE BRIDGE & APPROACHES Handling
Code:
 
Limits From: ON OAK GROVE RD AT W FORK PLUM CRK Fund Cat: 6
Limits To: (STR AA02-28-001) Estimate: $413,700
Length: 0.1 Miles Actual:  
 
District: Austin Let Date: MAY 2014
Highway: CR Let Status: Tentative
Project ID: CC 914-22-62 CSJ: 0914-22-062
Description: REPLACE STRUCTURE & APPROACHES Handling
Code:
 
Limits From: ON OAK GROVE ROAD (CR 127) @ Fund Cat: 3
Limits To: TRIBUTARY TO WEST FORK PLUM CREEK Estimate: $105,500
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0914-22-056
Length: 0.2 Miles
Estimate: $826,900
Actual:  

CCSJ: 0914-22-059

District: Austin Let Date: MAY 2014
Highway: CR Let Status: Tentative
Project ID: BR 2013(196) CSJ: 0914-22-059
Description: REPLACE BRIDGE & APPROACHES Handling
Code:
 
Limits From: ON SEAWILLOW RD (CR 205) AT Fund Cat: 6
Limits To: SIXMILE BRANCH DRAW (AA02-06-001) Estimate: $283,100
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0914-22-059
Length: 0.1 Miles
Estimate: $283,100
Actual:  

CCSJ: 0914-22-061

District: Austin Let Date: MAY 2014
Highway: VA Let Status: Tentative
Project ID:   CSJ: 0914-22-061
Description: CALDWELL COUNTY STPMM SET - ASIDE Handling
Code:
LS
Limits From: VARIOUS IN CALDWELL COUNTY Fund Cat: 7
Limits To: SET-ASIDE FOR PROJECTS Estimate: $2,120,648
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0914-22-061
Length: 0.1 Miles
Estimate: $2,120,648
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract