Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWICHITA
Highway IH0044
From VARIOUS LOCATION IN WICHITA
To CLAY, ARCHER & WILBARGER CO.
CSJ 6251-51-001
Proj ID SUP - 625151001
Work Type LITTER PICKUP & REMOVAL
 
0.001 232767.83 12436.33 12436.33 5.3
Work Order 11-01-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6251-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11120331
Totals 232767.83 12436.33 12436.33 5.3