Monthly Local Let Maintenance Report For Wichita Falls District As Of Oct 16, 2017 Page 2 Of 3

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARCHER
HighwayUS0281
FromVARIOUR LOCATIONS IN
ToARCHER COUNTY
CSJ6305-51-001
Proj IDSUP - 630551001
Work TypePICNIC AREA MAINTENANCE
 
0.00131675.0027422.5086.5
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged456
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6305-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160331
Totals31675.002030.0027422.5086.5

CountyCLAY
HighwayUS0287
FromVARIOUS LOCATIONS IN
ToCLAY COUNTY
CSJ6305-52-001
Proj IDSUP - 630552001
Work TypePICNIC/LANDSCAPE MAINTENANCE
 
0.00183507.5065347.5078.2
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged457
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6305-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160332
Totals83507.504636.0065347.5078.2

CountyWICHITA
HighwayUS0082
FromWFS AREA OFFICE
ToIN WICHITA FALLS
CSJ6305-57-001
Proj IDSUP - 630557001
Work TypeJANITORIAL SERVICES
 
0.00132984.4020454.0062.0
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged457
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6305-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160334
Totals32984.401320.6020454.0062.0

CountyWILBARGER
HighwayUS0183
FromVARIOUS LOCATIONS IN
ToWICHITA & WILBARGER COUNTY
CSJ6305-59-001
Proj IDSUP - 630559001
Work TypeGROUND MAINTENANCE
 
0.00168689.8043503.5463.3
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged399
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6305-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160335
Totals68689.802289.6643503.5463.3

CountyCLAY
HighwayUS0287
FromHENRIETTA MAINTENANCE OFFICE
ToHENRIETTA
CSJ6305-72-001
Proj IDSUP - 630572001
Work TypeGROUNDS MAINTENANCE
 
0.0016201.365942.9795.8
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged457
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6305-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160337
Totals6201.36516.785942.9795.8

CountyCOOKE
HighwayIH0035
FromVARIOUS
To.
CSJ6308-14-001
Proj IDSUP - 630814001
Work TypeJANITORIAL AND GROUNDS
 
0.001319192.50172713.7554.1
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged366
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160302
Totals319192.5013117.50172713.7554.1

CountyWICHITA
HighwayIH0044
FromVARIOUS
To.
CSJ6308-15-001
Proj IDSUP - 630815001
Work TypeJANITORIAL AND GROUNDS
 
0.001167673.6090423.2054.1
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged395
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160301
Totals167673.606986.4090423.2054.1

CountyMONTAGUE
HighwayUS0082
FromWICHITA FALLS
ToMAINTENANCE/ENGINEER COMPLEX
CSJ6308-63-001
Proj IDSUP - 630863001
Work TypeGROUNDS MAINTENANCE
 
0.00111743.605227.1644.5
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6308-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160331
Totals11743.60556.245227.1644.5

CountyARCHER
HighwayUS0082
FromVARIOUS LOCATION IN ARCHER BAYLOR
ToYOUNG & THROCKMORTON COUNTY
CSJ6308-64-001
Proj IDRMC - 630864001
Work TypeROUTINE STREET SWEEPING
 
0.001184123.0091226.5049.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-06-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged230
Percent Time Used63
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160301
Totals184123.008097.5091226.5049.5

CountyMONTAGUE
HighwayUS0081
FromMAINTENANCE OFFICE IN
ToBOWIE
CSJ6310-55-001
Proj IDSUP - 631055001
Work TypeGROUNDS MAINTENANCE
 
0.0015760.003600.0062.5
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged275
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6310-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160331
Totals5760.00480.003600.0062.5

CountyMONTAGUE
HighwaySH0175
FromGROUNDS MAINTENANCE IN
ToNOCONA
CSJ6310-56-001
Proj IDSUP - 631056001
Work TypeGROUNDS MAINTENANCE
 
0.0016840.003990.0058.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged275
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6310-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160332
Totals6840.00570.003990.0058.3

CountyMONTAGUE
HighwayUS0081
FromJANITORIAL SERVICES AT
ToBOWIE MAINTENANCE OFFICE
CSJ6311-37-001
Proj IDSUP - 631137001
Work TypeJANITORIAL MAINTENANCE
 
0.00121000.009625.0045.8
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged333
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6311-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160333
Totals21000.00875.009625.0045.8

CountyMONTAGUE
HighwaySH0175
FromJANITORIAL SERVICES AT
ToNOCONA MAINTENANCE OFFICE
CSJ6311-38-001
Proj IDSUP - 631138001
Work TypeJANITORIAL MAINTENANCE
 
0.00121000.009625.0045.8
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged333
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6311-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160334
Totals21000.00875.009625.0045.8

CountyARCHER
HighwayUS0082
FromVARIOUS LOCATIONS IN ARCHER
ToCLAY AND WICHITA COUNTY
CSJ6311-59-001
Proj IDRMC - 631159001
Work TypeRIGHT OF WAY MOWING
 
0.001185999.04112139.5260.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-07-17
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged22
Percent Time Used30
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170301
Totals185999.0438280.00112139.5260.2

CountyMONTAGUE
HighwayUS0287
FromVARIOUS ROADWAY IN CLAY
ToCOOKE AND MONTAGUE
CSJ6311-60-001
Proj IDRMC - 631160001
Work TypeRIGHT OF WAY MOWING
 
0.001131406.0052712.0040.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-15-17
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged23
Percent Time Used35
Contractor(s)
ARNOLDO CHAVEZ WELDING
SUBCONTRACTOR(S) FOR CCSJ: 6311-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170302
Totals131406.000.0052712.0040.1

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToWICHITA AND WILBARGER COUNTY
CSJ6311-61-001
Proj IDRMC - 631161001
Work TypeRIGHT OF WAY MOWING
 
0.001147340.8085379.6059.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged23
Percent Time Used41
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170303
Totals147340.800.0085379.6059.9

CountyCOOKE
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToCOOKE COUNTY
CSJ6311-62-001
Proj IDRMC - 631162001
Work TypeRIGHT OF WAY MOWING
 
0.001162212.0596135.5559.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged48
Percent Time Used67
Contractor(s)
ARNOLDO CHAVEZ WELDING
SUBCONTRACTOR(S) FOR CCSJ: 6311-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170304
Totals162212.050.0096135.5559.2

CountyYOUNG
HighwaySH0016
FromVARIOUS ROADWAYS IN
ToYOUNG COUNTY
CSJ6311-63-001
Proj IDRMC - 631163001
Work TypeRIGHT OF WAY MOWING
 
0.001177231.70101764.1957.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-17
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged11
Percent Time Used15
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170305
Totals177231.700.00101764.1957.4

CountyCLAY
HighwaySH0079
FromVARIOUS ROADWAYS IN
ToCLAY COUNTY
CSJ6311-64-001
Proj IDRMC - 631164001
Work TypeRIGHT OF WAY MOWING
 
0.001172499.00103026.8059.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-14-17
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged18
Percent Time Used26
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170306
Totals172499.000.00103026.8059.7

CountyMONTAGUE
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToCOOKE_AND MONTAGUE COUNTY
CSJ6311-65-001
Proj IDRMC - 631165001
Work TypeRIGHT OF WAY MOWING
 
0.001152512.9191424.1959.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-09-17
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged36
Percent Time Used50
Contractor(s)
EDDIE G. TYLER
SUBCONTRACTOR(S) FOR CCSJ: 6311-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170307
Totals152512.910.0091424.1959.9