Monthly Local Let Maintenance Report For Wichita Falls District As Of Jul 11, 2014 Page 2 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTAGUE
Highway US0082
From VARIOUS LOCATIONS AROUND
To NOCONA IN MONTAGUE COUNTY
CSJ 6257-18-001
Proj ID SUP - 625718001
Work Type PICNIC AREA MAINTENANCE
 
0.001 54223.00 2322.00 30100.00 55.5
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6257-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05130334
Totals 54223.00 2322.00 30100.00 55.5

CountyARCHER
Highway SH0079
From ARCHER MAINTENANCE OFFICE
To ARCHER CITY
CSJ 6258-54-001
Proj ID SUP - 625854001
Work Type JANITORIAL SERVICES
 
0.001 22280.00 830.00 11620.00 52.1
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6258-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05130335
Totals 22280.00 830.00 11620.00 52.1

CountyCLAY
Highway US0287
From HENRIETTA MAINTENANCE OFFICE
To IN CLAY COUNTY
CSJ 6258-55-001
Proj ID SUP - 625855001
Work Type JANITORIAL SERVICES
 
0.001 22280.00 830.00 11620.00 52.1
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6258-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05130336
Totals 22280.00 830.00 11620.00 52.1

CountyTHROCKMORTON
Highway US0380
From THROCKMORTON MAINTENANCE OFFICE
To IN THROCKMORTON COUNTY
CSJ 6258-56-001
Proj ID SUP - 625856001
Work Type JANITORIAL SERVICES
 
0.001 22280.00 830.00 12605.00 56.5
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6258-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05130337
Totals 22280.00 830.00 12605.00 56.5

CountyCOOKE
Highway IH0035
From VARIOUS LOCATIONS IN
To COOKE COUNTY
CSJ 6262-58-001
Proj ID SUP - 626258001
Work Type LANDSCAPE MAINTENANCE
 
0.001 30388.08 2532.34 10129.36 33.3
Work Order 08-01-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 334
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6262-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130331
Totals 30388.08 2532.34 10129.36 33.3

CountyCOOKE
Highway IH0035
From VARIOUS
To -
CSJ 6263-90-001
Proj ID SUP - 626390001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 126800.96 0.00 75875.28 59.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6263-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130332
Totals 126800.96 0.00 75875.28 59.8

CountyBAYLOR
Highway SH0114
From VARIOUS LOCATIONS IN BAYLOR, ARCHER
To THROCKMORTON AND YOUNG COUNTIES
CSJ 6264-42-001
Proj ID RMC - 626442001
Work Type CLEANING / SEALING CRACKS - HOT POUR
 
0.001 196283.37 0.00 202827.78 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 03-10-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 39
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6264-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140301
Totals 196283.37 0.00 202827.78 99.9

CountyWILBARGER
Highway US0287
From VARIOUS LOCATIONS IN ARCHER, CLAY, COOKE
To MONTAGUE, WICHITA, AND WILBARGER COUNTY
CSJ 6264-43-001
Proj ID RMC - 626443001
Work Type CLEANING / SEALING CRACKS - HOT POUR
 
0.001 215692.09 0.00 200362.64 92.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 72
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6264-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140302
Totals 215692.09 0.00 200362.64 92.8

CountyWICHITA
Highway IH0044
From VARIOUS LOCATIONS IN WICHITA
To AND WILBARGER COUNTY
CSJ 6266-28-001
Proj ID RMC - 626628001
Work Type ROUTINE STREET SWEEPING & DEBRIS REMOVAL
 
0.001 195374.60 13852.80 68176.36 34.8
Work Order 00-00-00
Work Began 03-24-14
Work Completed  
Time Computed 03-24-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 23
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6266-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140303
Totals 195374.60 13852.80 68176.36 34.8

CountyCOOKE
Highway IH0035
From VARIOUS LOCATION IN COOKE ARCHER BAYLOR
To CLAY THROCKMORTON YOUNG & MONTAGUE CO.
CSJ 6266-29-001
Proj ID RMC - 626629001
Work Type ROUTINE STREET SWEEPING
 
0.001 194520.00 0.00 9964.50 5.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 04-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 20
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6266-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140304
Totals 194520.00 0.00 9964.50 5.1

CountyMONTAGUE
Highway US0081
From NEAR BOWIE TO
To NEAR WISE COUNTY LINE
CSJ 6267-23-001
Proj ID RMC - 626723001
Work Type FULL DEPTH PAVEMENT REPAIR
 
0.001 188384.31 0.00 211142.72 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 29
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140301
Totals 188384.31 0.00 211142.72 99.9

CountyARCHER
Highway US0082
From VARIOUS LOCATIONS IN ARCHER
To CLAY AND WICHITA COUNTY
CSJ 6267-52-001
Proj ID RMC - 626752001
Work Type RIGHT OF WAY MOWING
 
0.001 112674.90 0.00 27797.64 24.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-19-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 23
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6267-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140301
Totals 112674.90 0.00 27797.64 24.6

CountyMONTAGUE
Highway US0287
From VARIOUS ROADEWAYS IN MONTAGUE
To AND CLAY COUNTIES
CSJ 6267-53-001
Proj ID RMC - 626753001
Work Type RIGHT OF WAY MOWING
 
0.001 102504.24 0.00 16299.34 15.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-16-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 13
Contractor(s)
EDDIE G. TYLER
SUBCONTRACTOR(S) FOR CCSJ: 6267-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140303
Totals 102504.24 0.00 16299.34 15.9

CountyWICHITA
Highway US0287
From VARIOUS LOCATIONS IN WICHITA
To AND WILBARGER COUNTY
CSJ 6267-54-001
Proj ID RMC - 626754001
Work Type RIGHT OF WAY MOWING
 
0.001 119206.05 0.00 25212.27 21.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-18-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 18
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140304
Totals 119206.05 0.00 25212.27 21.1

CountyCOOKE
Highway US0082
From VARIOUS ROADWAYS IN
To COOKE COUNTY
CSJ 6267-55-001
Proj ID RMC - 626755001
Work Type RIGHT OF WAY MOWING
 
0.001 89718.09 0.00 30057.36 33.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-05-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 17
Contractor(s)
JAIME ARREGUIN
SUBCONTRACTOR(S) FOR CCSJ: 6267-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140305
Totals 89718.09 0.00 30057.36 33.5

CountyYOUNG
Highway SH0016
From VARIOUS ROADWAYS IN
To YOUNG COUNTY
CSJ 6267-56-001
Proj ID RMC - 626756001
Work Type RIGHT OF WAY MOWING
 
0.001 118300.00 0.00 58894.91 49.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 10
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6267-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140306
Totals 118300.00 0.00 58894.91 49.7

CountyCLAY
Highway SH0079
From VARIOUS ROADWAYS
To IN CLAY COUNTY
CSJ 6267-57-001
Proj ID RMC - 626757001
Work Type RIGHT OF WAY MOWING
 
0.001 139967.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140307
Totals 139967.26 0.00 0.00 0.0

CountyMONTAGUE
Highway US0082
From VARIOUS ROADWAYS IN MONTAUGE
To AND COOKE COUNTY
CSJ 6267-58-001
Proj ID RMC - 626758001
Work Type RIGHT OF WAY MOWING
 
0.001 80548.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAIME ARREGUIN
SUBCONTRACTOR(S) FOR CCSJ: 6267-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140308
Totals 80548.40 0.00 0.00 0.0

CountyBAYLOR
Highway US0183
From VARIOUS ROADWAYS IN
To BAYLOR COUNTY
CSJ 6267-59-001
Proj ID RMC - 626759001
Work Type RIGHT OF WAY MOWING
 
0.001 84460.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6267-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02140309
Totals 84460.00 0.00 0.00 0.0

CountyTHROCKMORTON
Highway US0380
From VARIOUS ROADWAYS IN
To THROCKMORTON COUNTY
CSJ 6267-60-001
Proj ID RMC - 626760001
Work Type RIGHT OF WAY MOWING
 
0.001 63996.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-24-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RORIE CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6267-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140304
Totals 63996.75 0.00 0.00 0.0