Monthly Local Let Maintenance Report For Wichita Falls District As Of Jan 11, 2017 Page 3 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA
HighwayIH0044
FromVARIOUS LOCATIONS IN ARCHER CLAY
ToWICHITA & WILBARGER COUNTY
CSJ6305-86-001
Proj IDSUP - 630586001
Work TypeLITTER PICKUP & REMOVAL
 
0.001132335.9061713.8246.6
Work Order06-27-16
Work Began00-00-00
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged185
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6305-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160338
Totals132335.9010593.5861713.8246.6

CountyYOUNG
HighwayUS0380
FromGRAHAM MAINTENANCE COMPLEX
ToGRAHAM
CSJ6307-63-001
Proj IDSUP - 630763001
Work TypeJANITORIAL SERVICES
 
0.00121270.003750.0017.6
Work Order08-01-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6307-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160331
Totals21270.00750.003750.0017.6

CountyCOOKE
HighwayIH0035
FromVARIOUS
To.
CSJ6308-14-001
Proj IDSUP - 630814001
Work TypeJANITORIAL AND GROUNDS
 
0.001319192.5039789.7512.4
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged62
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160302
Totals319192.5013117.5039789.7512.4

CountyWICHITA
HighwayIH0044
FromVARIOUS
To.
CSJ6308-15-001
Proj IDSUP - 630815001
Work TypeJANITORIAL AND GROUNDS
 
0.001167673.6020559.2012.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged91
Percent Time Used12
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160301
Totals167673.600.0020559.2012.5

CountyMONTAGUE
HighwayUS0082
FromWICHITA FALLS
ToMAINTENANCE/ENGINEER COMPLEX
CSJ6308-63-001
Proj IDSUP - 630863001
Work TypeGROUNDS MAINTENANCE
 
0.00111743.60878.567.4
Work Order10-01-16
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6308-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160331
Totals11743.60278.12878.567.4

CountyARCHER
HighwayUS0082
FromVARIOUS LOCATION IN ARCHER BAYLOR
ToYOUNG & THROCKMORTON COUNTY
CSJ6308-64-001
Proj IDRMC - 630864001
Work TypeROUTINE STREET SWEEPING
 
0.001184123.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160301
Totals184123.000.000.000.0

CountyMONTAGUE
HighwayUS0081
FromMAINTENANCE OFFICE IN
ToBOWIE
CSJ6310-55-001
Proj IDSUP - 631055001
Work TypeGROUNDS MAINTENANCE
 
0.0015760.00480.008.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6310-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160331
Totals5760.00240.00480.008.3

CountyMONTAGUE
HighwaySH0175
FromGROUNDS MAINTENANCE IN
ToNOCONA
CSJ6310-56-001
Proj IDSUP - 631056001
Work TypeGROUNDS MAINTENANCE
 
0.0016840.00570.008.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6310-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160332
Totals6840.00285.00570.008.3

CountyMONTAGUE
HighwayUS0081
FromJANITORIAL SERVICES AT
ToBOWIE MAINTENANCE OFFICE
CSJ6311-37-001
Proj IDSUP - 631137001
Work TypeJANITORIAL MAINTENANCE
 
0.00121000.001750.008.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6311-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160333
Totals21000.00875.001750.008.3

CountyMONTAGUE
HighwaySH0175
FromJANITORIAL SERVICES AT
ToNOCONA MAINTENANCE OFFICE
CSJ6311-38-001
Proj IDSUP - 631138001
Work TypeJANITORIAL MAINTENANCE
 
0.00121000.001750.008.3
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6311-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160334
Totals21000.00875.001750.008.3

CountyARCHER
HighwayUS0281
FromVARIOUS LOCATIONS IN
ToARCHER CLAY & WILBARGER COUNTY
CSJ6312-86-001
Proj IDRMC - 631286001
Work TypeDEAD TREE REMOVAL TREE TRIM/BRUSH
 
0.001232320.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALARCON CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12160301
Totals232320.000.000.000.0

page 1 | page 2 | page 3