Monthly Local Let Maintenance Report For Wichita Falls District As Of Jun 12, 2017 Page 3 Of 3

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE
HighwaySH0175
FromJANITORIAL SERVICES AT
ToNOCONA MAINTENANCE OFFICE
CSJ6311-38-001
Proj IDSUP - 631138001
Work TypeJANITORIAL MAINTENANCE
 
0.00121000.006125.0029.1
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6311-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160334
Totals21000.00875.006125.0029.1

CountyARCHER
HighwayUS0082
FromVARIOUS LOCATIONS IN ARCHER
ToCLAY AND WICHITA COUNTY
CSJ6311-59-001
Proj IDRMC - 631159001
Work TypeRIGHT OF WAY MOWING
 
0.001185999.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170301
Totals185999.040.000.000.0

CountyMONTAGUE
HighwayUS0287
FromVARIOUS ROADWAY IN CLAY
ToCOOKE AND MONTAGUE
CSJ6311-60-001
Proj IDRMC - 631160001
Work TypeRIGHT OF WAY MOWING
 
0.001131406.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARNOLDO CHAVEZ WELDING
SUBCONTRACTOR(S) FOR CCSJ: 6311-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170302
Totals131406.000.000.000.0

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToWICHITA AND WILBARGER COUNTY
CSJ6311-61-001
Proj IDRMC - 631161001
Work TypeRIGHT OF WAY MOWING
 
0.001147340.8013996.809.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170303
Totals147340.8013996.8013996.809.4

CountyCOOKE
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToCOOKE COUNTY
CSJ6311-62-001
Proj IDRMC - 631162001
Work TypeRIGHT OF WAY MOWING
 
0.001162212.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARNOLDO CHAVEZ WELDING
SUBCONTRACTOR(S) FOR CCSJ: 6311-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170304
Totals162212.050.000.000.0

CountyYOUNG
HighwaySH0016
FromVARIOUS ROADWAYS IN
ToYOUNG COUNTY
CSJ6311-63-001
Proj IDRMC - 631163001
Work TypeRIGHT OF WAY MOWING
 
0.001177231.7034484.5219.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-17
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170305
Totals177231.7034484.5234484.5219.4

CountyCLAY
HighwaySH0079
FromVARIOUS ROADWAYS IN
ToCLAY COUNTY
CSJ6311-64-001
Proj IDRMC - 631164001
Work TypeRIGHT OF WAY MOWING
 
0.001172499.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170306
Totals172499.000.000.000.0

CountyMONTAGUE
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToCOOKE_AND MONTAGUE COUNTY
CSJ6311-65-001
Proj IDRMC - 631165001
Work TypeRIGHT OF WAY MOWING
 
0.001152512.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-09-17
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EDDIE G. TYLER
SUBCONTRACTOR(S) FOR CCSJ: 6311-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170307
Totals152512.910.000.000.0

CountyBAYLOR
HighwayUS0183
FromVARIOUS ROADWAYS IN
ToBAYLOR COUNTY
CSJ6311-66-001
Proj IDRMC - 631166001
Work TypeRIGHT OF WAY MOWING
 
0.001155952.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-07-17
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170308
Totals155952.000.000.000.0

CountyTHROCKMORTON
HighwayUS0380
FromVARIOUS ROADWAYS IN
ToTHROCKMORTON COUNTY
CSJ6311-67-001
Proj IDRMC - 631167001
Work TypeRIGHT OF WAY MOWING
 
0.00179600.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170309
Totals79600.500.000.000.0

CountyWILBARGER
HighwayUS0183
FromVARIOUS ROADWAYS IN
ToWILBARGER COUNTY
CSJ6311-68-001
Proj IDRMC - 631168001
Work TypeRIGHT OF WAY MOWING
 
0.001162133.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6311-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170310
Totals162133.010.000.000.0

CountyWICHITA
HighwayFM0369
FromVARIOUS ROADWAYS IN ARCHER
ToCLAY AND WICHITA COUNTY
CSJ6311-69-001
Proj IDRMC - 631169001
Work TypeRIGHT OF WAY MOWING
 
0.001152254.9524700.6516.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-22-17
Work Completed
Time Computed00-00-00
Contract Working Days46
Addl Days Granted0
Working Days Charged3
Percent Time Used6
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170311
Totals152254.9524700.6524700.6516.2

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6313-86-001
Proj IDRMC - 631386001
Work TypeTRUCK MOUNTED ATTENUATORS (TMA)
 
0.001169980.0072326.6142.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-23-17
Work Completed
Time Computed00-00-00
Contract Working Days184
Addl Days Granted0
Working Days Charged70
Percent Time Used38
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170301
Totals169980.0027451.8072326.6142.5

CountyMONTAGUE
HighwayUS0081
FromWICHITA COUNTY LINE
ToWISE COUNTY LINE
CSJ6316-35-001
Proj IDRMC - 631635001
Work TypeDELINEATOR INSTALLATION
 
0.001157741.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L. UNITED BUILDING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6316-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170301
Totals157741.000.000.000.0

CountyCOOKE
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToCOOKE COUNTY
CSJ6317-29-001
Proj IDSUP - 631729001
Work TypeJANITORIAL/GRDS/LANDSCAPE SERVICES
 
0.00154962.744429.348.0
Work Order05-01-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days488
Addl Days Granted0
Working Days Charged31
Percent Time Used6
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6317-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170331
Totals54962.744429.344429.348.0

CountyARCHER
HighwaySH0079
FromMAINTENANCE OFFICE
ToACHER CITY
CSJ6318-36-001
Proj IDSUP - 631836001
Work TypeJANITORIAL/GROUNDS SERVICES
 
0.00119206.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-30-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days457
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170332
Totals19206.580.000.000.0