AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - TYLER DISTRICT

Last Update: Thursday, November 20, 2014
ITEMS 500 2001 TO 560 2034
Items Items Bid Code Range
0100 - 0192
0247 - 0275
0305 - 0360
0400 - 0496
0500 - 0560
0610 - 0690
0712 - 0740
1014 - 1122
3127 - 3272
5369 - 5369
6005 - 6834
8020 - 8995
9033 - 9033
500 2001 - 560 2034
Item No Description Units November 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS     24.000 381,379.78333 24
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO     258.000 4,100.98062 24
508 2002 CONSTRUCTING DETOURS SY     27,210.000 78.00000 1
508 2005 CONSTRUCTING DETOURS (EBSS) SY     1,476.000 30.00000 1
512 2011 PORT CTB (DES SOURCE) (SAFETY SH) (TY 2) LF     300.000 24.00000 1
512 2017 PORT CTB (DES SOURCE) (LOW PROF) (TY 1) LF     4,010.000 6.00000 1
512 2018 PORT CTB (DES SOURCE) (LOW PROF) (TY 2) LF     40.000 6.00000 1
512 2020 PORT CTB (MOVE) (SAFETY SH) (TY 2) LF     3,900.000 20.00000 1
512 2026 PORT CTB (MOVE) (LOW PROF) (TY 1) LF     1,490.000 2.00000 1
512 2027 PORT CTB (MOVE) (LOW PROF) (TY 2) LF     20.000 2.00000 1
512 2029 PORT CTB (STKPL) (SAFETY SH) (TY 2) LF     300.000 24.00000 1
512 2035 PORT CTB (STKPL) (LOW PROF) (TY 1) LF     4,010.000 3.50000 1
512 2036 PORT CTB (STKPL) (LOW PROF) (TY 2) LF     40.000 3.50000 1
528 2006 COLORED TEXTURED CONC (5") SY     725.000 100.00000 1
529 2004 CONC CURB & GUTTER (TY II) LF     25,214.000 11.97417 4
529 2006 CONC CURB (MONO) (TY II) LF     1,430.000 7.83077 2
530 2010 DRIVEWAYS (CONC) SY     3,659.600 62.61561 7
530 2011 DRIVEWAYS (ACP) SY     12,685.000 25.28782 3
530 2015 TURNOUTS (SURF TREAT) EA     187.000 35.00000 1
530 2038 DRIVEWAYS (CONC) (HES) SY     71.000 105.77465 2
531 2005 CURB RAMPS (TY 1) EA     16.000 1,500.00000 2
531 2010 CURB RAMPS (TY 7) EA     8.000 1,000.00000 1
531 2015 CONC SIDEWALKS (4") SY     404.000 36.00000 1
531 2035 CONCRETE SIDEWALKS (5') (4") LF     12,133.000 19.00000 1
533 2006 SHOULDER TEXTURING (MILLED) (ASPHALT) LF     839,185.840 .13231 5
536 2004 CONC DIRECTIONAL ISLAND SY     25.000 76.00000 1
540 2001 MTL W - BEAM GD FEN (TIM POST) LF     12,263.100 17.00582 5
540 2005 TERMINAL ANCHOR SECTION EA     1.000 1,100.00000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     24.000 1,350.00000 4
540 2012 MTL BEAM GD FEN TRANS (TL2) EA     36.000 813.33333 4
540 2044 DOWNSTREAM ANCHOR TERMINAL (DAT) SECTION EA     6.000 975.00000 2
540 2046 MTL BM GD FEN TRANS (NON - SYM) EA     2.000 800.00000 1
542 2001 REMOVING METAL BEAM GUARD FENCE LF     14,684.500 1.71489 6
542 2002 REMOVING TERMINAL ANCHOR SECTION EA     8.000 137.50000 2
544 2001 GUARDRAIL END TREATMENT (INSTALL) EA     61.000 2,064.26230 8
544 2003 GUARDRAIL END TREATMENT (REMOVE) EA     23.000 127.39130 2
544 2004 GDRAIL END TRT (INST) (WOOD POST) (TY I) EA     25.000 1,968.00000 2
545 2095 CRASH CUSH ATTEN (INSTL) (S) (N) (TL3) EA     4.000 9,000.00000 1
545 2100 CRASH CUSHION ATTENUATOR (MOVE & RESET EA     52.000 2,200.00000 1
545 2101 CRASH CUSHION ATTENUATOR (REMOVE) EA     4.000 250.00000 1
552 2001 WIRE FENCE (TY A) LF     1,103.000 9.23731 2
552 2003 WIRE FENCE (TY C) LF     969.000 13.00103 4
552 2005 GATE (TY 1) EA     1.000 500.00000 1
552 2008 WIRE FENCE (WATER GAP) LF     37.000 65.00000 1
556 2008 PIPE UNDERDRAINS (TY 8) (6") LF     1,000.000 22.00000 1
556 2010 PIPE UNDERDRAINS (TY 5, 6, 7 OR 8) (6") LF     1,000.000 27.00000 1
560 2011 MAILBOX INSTALL - S (TWG - POST) TY 2 FND EA     36.000 178.00000 2
560 2013 MAILBOX INSTALL - D (TWG - POST) TY 2 FND EA     1.000 215.00000 1
560 2021 MAILBOX INSTALL - S (TWG - POST) TY 2 FND - TB EA     180.000 164.50000 4
560 2022 MAILBOX INSTALL - D (TWG - POST) TY 2 FND - TB EA     14.000 191.78571 3
560 2023 MAILBOX INSTALL - M (TWG - POST) TY 2 FND - TB EA     9.000 329.44444 3
560 2032 MAILBOX INSTALLTION (SINGLE) INSTALL ONL EA     117.000 149.74359 2
560 2033 MAILBOX INSTALLTION (DOUBLE) INSTALL ONL EA     22.000 177.27273 2
560 2034 MAILBOX INSTLTION (MULTIPLE) INSTALL ONL EA     11.000 215.00000 1