AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - TYLER DISTRICT

Last Update: Thursday, November 20, 2014
ITEMS 247 2042 TO 275 2019
Items Items Bid Code Range
0100 - 0192
0247 - 0275
0305 - 0360
0400 - 0496
0500 - 0560
0610 - 0690
0712 - 0740
1014 - 1122
3127 - 3272
5369 - 5369
6005 - 6834
8020 - 8995
9033 - 9033
247 2042 - 275 2019
Item No Description Units November 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
247 2042 FL BS (CMP IN PLC) (TY A GR 2) (FNAL POS CY     3,107.000 76.00000 1
247 2241 FL BS (CMP IN PLACE) (TY A GR 2) (14") SY     263,342.000 24.00000 1
247 2322 FL BS (CMP IN PLC) (TY D GR 2) (8") SY     142,548.000 14.00000 1
247 2336 FL BS (CMP IN PLC) (TY A GR 2) (10") SY     15,436.000 20.30000 1
247 2342 FL BS (CMP IN PLACE) (TY A GR 2) (8") SY     189,690.000 17.00000 1
247 2388 FL BS (CMP IN PLC) (TY A GR 5) (6") SY     117,014.000 10.50000 1
251 2176 REWORK BASE MTL (TY B) (9") (DENS CONT) SY     149,997.000 4.00000 1
260 2001 LIME (HYDRATED LIME (DRY) ) TON     1,711.000 156.48687 5
260 2002 LIME (HYDRATED LIME (SLURRY) ) TON     738.000 150.00000 1
260 2006 LIME TRT (EXST MATL) (6") SY     138,250.000 1.60000 1
260 2027 LIME TRT (EXST MATL) (8") SY     86,006.000 2.42471 2
260 2073 LIME TRT (SUBGRADE) (8") SY     42,782.000 2.53558 3
275 2001 CEMENT TON     5,407.850 150.84345 9
275 2002 CEMENT TREAT (EXIST MATL) (6") SY     328,467.230 2.97305 3
275 2010 CEMENT TREAT (SUBGRADE) (8") SY     112,388.000 1.65390 4
275 2011 CEMENT TREAT (EXIST MATL) (8") SY     89,332.000 2.41648 2
275 2019 CEMENT TREAT (SUBGRADE) (6") SY     1,476.000 3.75000 1