AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - TYLER DISTRICT

Last Update: Tuesday, November 29, 2016
ITEMS 100 6002 TO 193 6006
Items Items Bid Code Range
0100 - 0193
0247 - 0275
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0688
0730 - 0780
1002 - 1010
3002 - 3002
4014 - 4045
5040 - 5040
6001 - 6121
9051 - 9054
100 6002 - 193 6006
Item No Description Units November 30, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 6002 PREPARING ROW STA     803.220 1,759.17158 12
100 6003 PREPARING ROW (TREE) (5" TO 12" DIA) EA     60.000 250.00000 1
104 6009 REMOVING CONC (RIPRAP) SY     20.000 35.00000 1
104 6017 REMOVING CONC (DRIVEWAYS) SY     4,394.000 12.25080 7
104 6021 REMOVING CONC (CURB) LF     5,183.000 6.50000 1
104 6022 REMOVING CONC (CURB AND GUTTER) LF     2,050.000 7.82927 2
105 6005 REMOVING STAB BASE AND ASPH PAV (3") SY     3,135.000 4.00000 1
105 6011 REMOVING STAB BASE AND ASPH PAV (2" - 6" SY     14,898.000 4.43502 5
105 6019 REMOVING STAB BASE & ASPH PAV (14") SY     1,311.000 8.00000 1
105 6041 REMOVING STAB BASE AND ASPH PAV (8") SY     19,486.000 3.53414 2
105 6074 REMOVING STAB BASE AND ASPH PAV (4") SY     67,603.000 2.25000 1
106 6002 OBLITERATING ABANDONED ROAD SY     2,651.000 6.75000 1
110 6001 EXCAVATION (ROADWAY) CY     636,396.000 3.57099 12
110 6003 EXCAVATION (SPECIAL) CY     1,152.000 12.68403 2
112 6001 SUBGRADE WIDENING (ORD COMP) STA     402.380 160.00000 1
132 6005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     3,032.000 17.18701 3
132 6006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     573,479.000 4.13164 6
132 6017 EMBANKMENT (VEHICLE) (ORD COMP) (TY A) CY     1,083.000 18.72392 2
132 6019 EMBANKMENT (VEHICLE) (ORD COMP) (TY B) CY     17,822.000 16.01925 2
132 6021 EMBANKMENT (VEHICLE) (ORD COMP) (TY C) CY     4,895.000 24.32891 4
134 6001 BACKFILL (TY A) STA     337.100 770.00000 1
134 6002 BACKFILL (TY B) STA     420.000 245.00000 1
134 6003 BACKFILL (TY C) STA     846.040 405.04657 4
150 6001 BLADING STA     420.000 75.00000 1
158 6002 SPEC EXCAV WORK (BACKHOE) HR     60.000 50.00000 1
158 6003 SPEC EXCAV WORK (HYD EXCAVATOR) HR     240.000 152.50000 2
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY     624,979.000 .87613 9
160 6005 FURNISHING AND PLACING TOPSOIL CY     623.000 25.00000 1
161 6012 GENERAL USE COMPOST CY     356.000 36.79000 1
162 6002 BLOCK SODDING SY 81.000 10.00000 55,760.000 4.16733 5
162 6004 MULCH SODDING SY     12,160.000 4.25000 1
164 6005 BROADCAST SEED (PERM) (URBAN) (SANDY) SY 1,698.000 1.00000 1,698.000 1.00000 1
164 6009 BROADCAST SEED (TEMP) (WARM) SY     61,494.500 .21254 5
164 6011 BROADCAST SEED (TEMP) (COOL) SY     61,494.500 .21209 5
164 6013 STRAW / HAY MLCH SEED (PERM) (RURAL) (SANDY SY     613,180.000 .32694 10
164 6015 STRAW / HAY MLCH SEED (PERM) (RURAL) (CLAY) SY     44,892.000 .52000 1
164 6017 STRAW / HAY MLCH SEED (PERM) (URBAN) (SANDY SY     119,533.000 .32000 1
164 6045 STRAW OR HAY MULCHING SY     2,783.000 1.79000 1
164 6047 STRAW / HAY MLCH SEED (TEMP) (WARM) SY     435,599.000 .21417 5
164 6049 STRAW / HAY MLCH SEED (TEMP) (COOL) SY     440,692.000 .22037 6
164 6054 BOND FBR MTRX SEED (PERM) (RURAL) (SAND) SY     6,785.000 1.30906 2
164 6055 BONDED FBR MTRX SEED (TEMP) (WARM) SY     5,298.000 1.18381 2
164 6056 BONDED FBR MTRX SEED (TEMP) (COOL) SY     5,298.000 1.18381 2
164 6070 BOND FBR MTRX SEED (PERM) (URBAN) (SAND SY     2,651.000 1.80000 1
168 6001 VEGETATIVE WATERING MG 5.000 1.00000 18,736.970 10.45583 19
169 6004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY     4,378.000 2.28346 4
170 6001 IRRIGATION SYSTEM LS     1.000 25,000.00000 1
170 6006 IRRIGATION SYSTEM LOCATION A LS     1.000 31,100.00000 1
170 6007 IRRIGATION SYSTEM LOCATION B LS     1.000 31,100.00000 1
170 6008 IRRIGATION SYSTEM LOCATION C LS     1.000 31,100.00000 1
192 6002 PLANT MATERIAL (1 - GAL) EA 438.000 15.00000 3,902.000 8.74795 3
192 6003 PLANT MATERIAL (3 - GAL) EA     2,193.000 17.51636 2
192 6004 PLANT MATERIAL (5 - GAL) EA 406.000 35.00000 935.000 27.15912 3
192 6014 PLANT SOIL MIX CY     356.000 43.00000 1
192 6015 LANDSCAPE EDGE LF     2,749.000 14.50000 1
192 6016 PLANT BED PREPARATION SY 611.000 18.00000 5,792.000 4.48810 3
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA     35.000 155.93000 1
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 9.000 300.00000 53.000 300.41660 3
192 6025 PLANT MATERIAL (45 GAL) (TREE) EA     4.000 327.50000 1
192 6067 LANDSCAPE EDGE (TYPE I) LF 229.000 12.00000 229.000 12.00000 1
192 6068 LANDSCAPE EDGE (TYPE II) LF 89.000 35.00000 89.000 35.00000 1
193 6006 VEGETATIVE WATERING MG 168.000 20.00000 168.000 20.00000 1