Monthly State Let Construction Report For Pharr District As Of Jan 11, 2017 Page 3 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwayCS
FromCITY OF EDINBURG, EISENHOWER ELEM
To& MEMORIAL MIDDLE SCHOOL
CSJ0921-02-258
Proj IDSTP 1102(186)SRS
Work TypeSIDEWALK, CROSSWALK, BIKE RACKS
 
13.0432667755.202706309.5799.9
Work Order11-09-12
Work Began12-11-12
Work Completed
Time Computed11-25-12
Contract Working Days240
Addl Days Granted0
Working Days Charged230
Percent Time Used95
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-258
STAR OPERATIONS, INC. (17.31)
VALLEY STRIPING CORP. (3.07)
ACE DRILLING, INC. (0.43)
Contract #09123221
Totals2667755.200.002706309.5799.9

CountyHIDALGO
HighwayCS
FromCITY OF EDINBURG,
ToCANO-GONZALEZ ELEMENTARY
CSJ0921-02-266
Proj IDSTP 1102(187)SRS
Work TypeSIDEWALKS, CROSSWALKS, BIKE RACKS
 
1.6004251199.444086605.9696.1
Work Order08-02-13
Work Began12-02-13
Work Completed
Time Computed08-18-13
Contract Working Days465
Addl Days Granted0
Working Days Charged373
Percent Time Used80
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-266
VALLEY STRIPING CORP. (2.39)
STAR OPERATIONS, INC. (11.14)
Contract #05133221
Totals4251199.440.004086605.9696.1

CountyHIDALGO
HighwayCR
FromSTR # AA02-29-002_@ DRAINAGE DITCH
ToON MILE 17 1/2 RD
CSJ0921-02-290
Proj IDBR 2012(432)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.070425689.80349111.3982.0
CountyCAMERON
HighwayCR
FromSTR # AA08-28-001_@ DRAINAGE DITCH
ToKORNEGAY RD
CSJ0921-06-248
Proj IDBR 2012(283)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.078471252.00369827.7578.4
CountyCAMERON
HighwayCR
FromCCWID # 2 CANAL ON LINE 20 ROAD
To.5 MI E OF NELSON RD
CSJ0921-06-249
Proj IDBR 2012(284)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.112474294.95442020.8093.1
Work Order10-21-15
Work Began00-00-00
Work Completed
Time Computed11-20-15
Contract Working Days240
Addl Days Granted0
Working Days Charged194
Percent Time Used80
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-290
HIGHWAY BARRICADES AND SERVICES, LLC (0.84)
SHINN & GREGORY, INC. (8.16)
PAVEMENT MARKINGS INC. (0.90)
SOIL-TECH, INC. (2.80)
CERTIFIED PLACERS LLC (0.44)
D & T CONSTRUCTION, INC. (6.13)
PENHALL COMPANY (AUSTIN) (0.75)
Contract #05153210
Totals1371236.7582475.991160959.9484.6

CountyHIDALGO
HighwayCS
FromCHAPIN RD.
ToCANTON RD.
CSJ0921-02-316
Proj IDSTP 2014(146)TE
Work TypeCONST. JACKSON RD HIKE & BIKE TRAIL
 
2.7802059444.652054183.7499.7
Work Order04-20-15
Work Began00-00-00
Work Completed
Time Computed05-06-15
Contract Working Days175
Addl Days Granted0
Working Days Charged171
Percent Time Used97
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-316
EARTH IRRIGATION & LANDSCAPING, INC. (11.54)
HIGHWAY BARRICADES AND SERVICES, LLC (2.72)
SOIL-TECH, INC. (1.43)
IZAGUIRRE CONSTRUCTION (3.56)
TEXAS HIGHWAY SYSTEMS, INC. (0.94)
TENSOSHADE, LLC (2.22)
ROB"S CONTRACTING SOLUTIONS (2.71)
Contract #12143217
Totals2059444.650.002054183.7499.7

CountyHIDALGO
HighwayCS
FromWITHIN THE CITY OF PHARR, OWASSA RD
ToMILITARY HIGHWAY
CSJ0921-02-324
Proj IDSTP 2014(093)TE
Work TypeCITY OF PHARR BIKE ACCESS IMPR.
 
22.000487777.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days101
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-324
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163030
Totals487777.000.000.000.0

CountyHIDALGO
HighwayVA
FromDISTRICT WIDE
ToVARIOUS LOCATIONS
CSJ0921-02-339
Proj IDBR 2016(126)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.1001398543.351326088.6795.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-15
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged206
Percent Time Used103
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-339
SCOTT DERR PAINTING CO (0.16)
EXTERIOR DESIGNS (1.30)
HIGHWAY BARRICADES AND SERVICES, LLC (0.27)
BEAVER CONTRACTORS, LLC (13.02)
GUERRA CONSTRUCTION COMPANY (4.29)
Contract #10153014
Totals1398543.350.001326088.6795.1

CountyHIDALGO
HighwayVA
FromCOUNTYWIDE
ToVARIOUS LOCATIONS ON IH-2 & IH-69C
CSJ0921-02-347
Proj IDC 921-2-347
Work TypeREHAB CONTINOUOUS ILLUMINATION
 
0.1002161095.3019939.980.9
CountyCAMERON
HighwayVA
FromCOUNTYWIDE
ToVARIOUS LOCATIONS ON IH-2 & IH-69E
CSJ0921-06-300
Proj IDC 921-6-300
Work TypeREHAB CONTINOUS ILLUMINATION
 
10.200569144.200.000.0
CountyCAMERON
HighwayVA
FromCOUNTYWIDE
ToVARIOUS LOCATIONS ON IH-69E
CSJ0921-06-301
Proj IDC 921-6-301
Work TypeREHAB CONTINOUS ILLUMINATION
 
1.000444310.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days371
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-347
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163234
Totals3174549.500.0019939.980.6

CountyCAMERON
HighwayVA
FromLOCATED IN VICINITY OF GSA FACILITY
ToLOS INDIOS FREE TRADE INT'L BRIDGE
CSJ0921-06-208
Proj IDBOR 2002(633)
Work TypeCONSTRUCT BSIF
 
0.0016949739.755354645.6179.2
Work Order09-30-14
Work Began02-24-15
Work Completed
Time Computed10-16-14
Contract Working Days262
Addl Days Granted0
Working Days Charged395
Percent Time Used150
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-208
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (19.23)
HIGHWAY BARRICADES AND SERVICES, LLC (0.35)
LAREDO STRIPING INC. (2.93)
SOIL-TECH, INC. (3.52)
RIO GRANDE REBAR PLACING, LTD. (0.90)
PRIMATE CONSTRUCTION, INC. (1.07)
RGV ALLIANCE CONSTRUCTION, L.L.C. (0.26)
MUNOZ FOUNDATION DRILLING, INC. (0.10)
BURNS BUILDING CONSTRUCTION, INC. (3.19)
METRO ELECTRIC, INC. (3.66)
Contract #08143056
Totals6949739.750.005354645.6179.2

CountyCAMERON
HighwayCS
FromLINEAR PARK (HARRISON & 7TH ST)
ToFORT BROWN HISTORIC LANDMARK
CSJ0921-06-270
Proj IDSTP 2014(101)TE
Work TypeEXPAND HIKE & BIKE TRAIL
 
2.540899908.10708271.9478.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-16
Work Began05-18-16
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted10
Working Days Charged132
Percent Time Used88
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-270
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02163244
Totals899908.100.00708271.9478.7

CountyCAMERON
HighwayCS
FromLOS FRESNOS WEST SCHOOL CONNECTION
ToW OF OLEANDER ST TO W OF LONG HORN
CSJ0921-06-286
Proj IDSTP 1602(198)TP
Work TypeCONSTRUCT SIDEWALKS
 
0.100265005.000.000.0
CountyCAMERON
HighwayCS
FromLOS FRESNOS SOUTH RES CONNECTION
ToFROM ALVAREZ COURT TO SH 100
CSJ0921-06-287
Proj IDSTP 1602(198)TP
Work TypeCONSTRUCT SIDEWALKS
 
0.100147710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days93
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-286
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163024
Totals412715.000.000.000.0

CountyWILLACY
HighwayCR
FromCR 156 STR AA01-64-002
ToOLD WEST MAIN DRAIN
CSJ0921-27-035
Proj IDBR 2011(283)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.064440467.05112853.7825.6
CountyWILLACY
HighwayCR
From#AA01-74-001 @ WEST MAIN DRAIN
To.05 MI W OF BUS 77
CSJ0921-27-036
Proj IDBR 2011(282)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.057385584.40375380.8297.3
Work Order06-23-14
Work Began11-24-14
Work Completed
Time Computed07-09-14
Contract Working Days184
Addl Days Granted0
Working Days Charged61
Percent Time Used33
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-27-035
RIO GRANDE REBAR PLACING, LTD. (0.51)
LAREDO STRIPING INC. (2.58)
SOIL-TECH, INC. (1.92)
PAVEMENT MARKINGS INC. (0.59)
Contract #04143227
Totals826051.450.00488234.6059.1

CountySTARR
HighwayFM 755
FromFM 755 REALIGNMENT, US 83 N.
ToFM 755
CSJ1103-04-027
Proj IDCBI 2014(896)
Work TypeREALIGN/W PARTIAL WIDENING TO 4 LNS
 
2.40010733925.486550495.8162.2
Work Order10-28-14
Work Began01-27-15
Work Completed
Time Computed11-13-14
Contract Working Days380
Addl Days Granted0
Working Days Charged479
Percent Time Used126
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1103-04-027
HIGHWAY BARRICADES AND SERVICES, LLC (1.09)
J & P TRUCKING AND HAULING (5.17)
D S TEXAS ICON CONSTRUCTION, LLC (0.73)
CERTIFIED PLACERS LLC (0.98)
W. W. FOUNDATION DRILLING, LTD. (4.64)
DUSTROL, INC. (0.20)
LAREDO STRIPING INC. (0.48)
Contract #09143042
Totals10733925.48155100.236550495.8162.2

CountyCAMERON
HighwayFM 803
FromIH-69E @ RANCHO VIEJO AVENUE
To0.077 MI N OF SH 100
CSJ1138-02-015
Proj IDSTP 2014(897)MM
Work TypeREALIGN & WIDEN TO 4 LANES
 
2.76310494854.488894183.2784.7
Work Order12-17-14
Work Began02-09-15
Work Completed
Time Computed01-02-15
Contract Working Days560
Addl Days Granted10
Working Days Charged479
Percent Time Used84
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1138-02-015
SOIL-TECH, INC. (2.09)
RHYNER CONSTRUCTION SERVICES, INC. (0.49)
LAREDO STRIPING INC. (0.68)
HIGHWAY BARRICADES AND SERVICES, LLC (1.76)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (1.96)
RIO GRANDE REBAR PLACING, LTD. (0.21)
Contract #09143237
Totals10494854.48185284.178894183.2784.7

CountyHIDALGO
HighwayFM 1925
FromFM 681
ToFM 2220
CSJ1803-01-037
Proj IDSTP 2016(127)
Work TypeREHABILITATE ROADWAY
 
5.5238117383.102624615.4632.3
Work Order11-24-15
Work Began02-02-16
Work Completed
Time Computed12-24-15
Contract Working Days420
Addl Days Granted0
Working Days Charged104
Percent Time Used24
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1803-01-037
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (0.78)
GO UNDERGROUND, LIMITED LIABILITY COMPANY (7.11)
HIGHWAY BARRICADES AND SERVICES, LLC (2.18)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.74)
D&S TEXAS ICON CONSTRUCTION (2.53)
Contract #10153209
Totals8117383.10453983.162624615.4632.3

CountyHIDALGO
HighwayFM 1925
From0.13 MI. EAST OF KENYON RD
To0.21 MI. EAST OF FM 907
CSJ1803-02-028
Proj IDC 1803-2-28
Work TypeGRAD,BASE & SURF
 
1.0602891653.042007082.5069.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-15
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged117
Percent Time Used53
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 1803-02-028
SALAZAR UTILITY CONSTRUCTION INC. (2.49)
GULF COAST CONTRACTORS, INC. (0.39)
HIGHWAY BARRICADES AND SERVICES, LLC (1.94)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.46)
Contract #07153234
Totals2891653.040.002007082.5069.4

CountyHIDALGO
HighwayFM 2220 ETC
FromSH 107
To0.21 MI N OF MI 5 RD.
CSJ2094-01-059
Proj IDSTP 2017(050)
Work TypeSEAL COAT
 
38.2181601730.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2094-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163216
Totals1601730.750.000.000.0

CountyCAMERON
HighwayFM 106
FromFM 1847 ON GEN BRANT RD, E & S
ToFM 510
CSJ2243-01-009
Proj IDC 2243-1-9
Work TypeGR, STRS & SURF
 
11.44015555190.896452770.0041.4
Work Order10-28-14
Work Began00-00-00
Work Completed
Time Computed11-09-15
Contract Working Days420
Addl Days Granted29
Working Days Charged283
Percent Time Used63
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2243-01-009
ALTUS TRAFFIC MANAGEMENT LLC (0.39)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (DONNA) (0.29)
HIGHWAY BARRICADES AND SERVICES, LLC (0.46)
HURFCO INDUSTRIES, INC. DBA HURRICANE FENCE COMPANY (3.11)
J & P TRUCKING AND HAULING (17.32)
LAREDO STRIPING INC. (0.37)
Contract #09143004
Totals15555190.89426188.076452770.0041.4

CountyHIDALGO
HighwaySH 364
FromSH 495 N
ToFM 1924
CSJ2966-01-009
Proj IDC 2966-1-9
Work TypeGRADING, STRUCTURES & SURFACING
 
2.0006848709.561554648.3522.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-15
Work Began02-16-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged62
Percent Time Used15
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2966-01-009
GULF COAST CONTRACTORS, INC. (0.92)
HIGHWAY BARRICADES AND SERVICES, LLC (1.25)
MUSTANG COLT SERVICES, INC. (4.14)
Contract #11153214
Totals6848709.560.001554648.3522.6

page 1 | page 2 | page 3