Monthly State Let Construction Report For Pharr District As Of Nov 9, 2016 Page 3 Of 3

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHIDALGO
Highway CR
From STR # AA02-29-002_@ DRAINAGE DITCH
To ON MILE 17 1/2 RD
CSJ 0921-02-290
Proj ID BR 2012(432)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.070 425689.80 58270.00 343694.90 80.7
CountyCAMERON
Highway CR
From STR # AA08-28-001_@ DRAINAGE DITCH
To KORNEGAY RD
CSJ 0921-06-248
Proj ID BR 2012(283)
Work Type REPLACE BRIDGE & APPROACHES
 
0.078 471252.00 0.00 301358.25 63.9
CountyCAMERON
Highway CR
From CCWID # 2 CANAL ON LINE 20 ROAD
To .5 MI E OF NELSON RD
CSJ 0921-06-249
Proj ID BR 2012(284)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.112 474294.95 12187.35 391424.35 82.5
Work Order 10-21-15
Work Began 00-00-00
Work Completed  
Time Computed 11-20-15
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 170
Percent Time Used 70
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-248
HIGHWAY BARRICADES AND SERVICES, LLC (0.84%)
SHINN & GREGORY, INC.(8.16%)
PAVEMENT MARKINGS INC. (0.90%)
SOIL-TECH, INC.(2.80%)
CERTIFIED PLACERS LLC(0.44%)
D & T CONSTRUCTION, INC. (6.13%)
Contract # 05153210
Totals 1371236.75 70457.35 1036477.50 75.5

CountyHIDALGO
Highway CS
From CHAPIN RD.
To CANTON RD.
CSJ 0921-02-316
Proj ID STP 2014(146)TE
Work Type CONST. JACKSON RD HIKE & BIKE TRAIL
 
2.780 2059444.65 0.00 2054183.74 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-20-15
Work Began 00-00-00
Work Completed  
Time Computed 05-06-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 171
Percent Time Used 97
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-316
EARTH IRRIGATION & LANDSCAPING, INC. ( 11.54%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.72%)
SOIL-TECH, INC.(1.43%)
IZAGUIRRE CONSTRUCTION (3.56%)
TEXAS HIGHWAY SYSTEMS, INC.(0.94%)
TENSOSHADE, LLC(2.22%)
ROB"S CONTRACTING SOLUTIONS(2.71%)
Contract # 12143217
Totals 2059444.65 0.00 2054183.74 99.7

CountyHIDALGO
Highway CS
From WITHIN THE CITY OF PHARR, OWASSA RD
To MILITARY HIGHWAY
CSJ 0921-02-324
Proj ID STP 2014(093)TE
Work Type CITY OF PHARR BIKE ACCESS IMPR.
 
22.000 487777.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-324
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163030
Totals 487777.00 0.00 0.00 0.0

CountyHIDALGO
Highway VA
From DISTRICT WIDE
To VARIOUS LOCATIONS
CSJ 0921-02-339
Proj ID BR 2016(126)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.100 1398543.35 0.00 1210478.96 86.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 199
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 91
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-339
SCOTT DERR PAINTING CO (0.16%)
EXTERIOR DESIGNS (1.30%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.27%)
BEAVER CONTRACTORS, LLC( 13.02%)
GUERRA CONSTRUCTION COMPANY(4.29%)
Contract # 10153014
Totals 1398543.35 0.00 1210478.96 86.5

CountyHIDALGO
Highway VA
From COUNTYWIDE
To VARIOUS LOCATIONS ON IH-2 & IH-69C
CSJ 0921-02-347
Proj ID C 921-2-347
Work Type REHAB CONTINOUOUS ILLUMINATION
 
0.100 2161095.30 0.00 0.00 0.0
CountyCAMERON
Highway VA
From COUNTYWIDE
To VARIOUS LOCATIONS ON IH-2 & IH-69E
CSJ 0921-06-300
Proj ID C 921-6-300
Work Type REHAB CONTINOUS ILLUMINATION
 
10.200 569144.20 0.00 0.00 0.0
CountyCAMERON
Highway VA
From COUNTYWIDE
To VARIOUS LOCATIONS ON IH-69E
CSJ 0921-06-301
Proj ID C 921-6-301
Work Type REHAB CONTINOUS ILLUMINATION
 
1.000 444310.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 371
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-347
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163234
Totals 3174549.50 0.00 0.00 0.0

CountyCAMERON
Highway VA
From LOCATED IN VICINITY OF GSA FACILITY
To LOS INDIOS FREE TRADE INT'L BRIDGE
CSJ 0921-06-208
Proj ID BOR 2002(633)
Work Type CONSTRUCT BSIF
 
0.001 6949739.75 86400.00 5344973.61 79.0
Work Order 09-30-14
Work Began 02-24-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 262
Addl Days Granted 0
Working Days Charged 395
Percent Time Used 150
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-208
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 19.23%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.35%)
LAREDO STRIPING INC. (2.93%)
SOIL-TECH, INC.(3.52%)
RIO GRANDE REBAR PLACING, LTD. (0.90%)
PRIMATE CONSTRUCTION, INC. (1.07%)
RGV ALLIANCE CONSTRUCTION, L.L.C.(0.26%)
MUNOZ FOUNDATION DRILLING, INC.(0.10%)
BURNS BUILDING CONSTRUCTION, INC.(3.19%)
METRO ELECTRIC, INC. (3.66%)
Contract # 08143056
Totals 6949739.75 86400.00 5344973.61 79.0

CountyCAMERON
Highway CS
From LINEAR PARK (HARRISON & 7TH ST)
To FORT BROWN HISTORIC LANDMARK
CSJ 0921-06-270
Proj ID STP 2014(101)TE
Work Type EXPAND HIKE & BIKE TRAIL
 
2.540 899908.10 0.00 588904.33 65.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-28-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 75
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-270
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163244
Totals 899908.10 0.00 588904.33 65.4

CountyCAMERON
Highway CS
From LOS FRESNOS WEST SCHOOL CONNECTION
To W OF OLEANDER ST TO W OF LONG HORN
CSJ 0921-06-286
Proj ID STP 1602(198)TP
Work Type CONSTRUCT SIDEWALKS
 
0.100 265005.00 0.00 0.00 0.0
CountyCAMERON
Highway CS
From LOS FRESNOS SOUTH RES CONNECTION
To FROM ALVAREZ COURT TO SH 100
CSJ 0921-06-287
Proj ID STP 1602(198)TP
Work Type CONSTRUCT SIDEWALKS
 
0.100 147710.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 93
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-286
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163024
Totals 412715.00 0.00 0.00 0.0

CountyWILLACY
Highway CR
From CR 156 STR AA01-64-002
To OLD WEST MAIN DRAIN
CSJ 0921-27-035
Proj ID BR 2011(283)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.064 440467.05 0.00 112853.78 25.6
CountyWILLACY
Highway CR
From #AA01-74-001 @ WEST MAIN DRAIN
To .05 MI W OF BUS 77
CSJ 0921-27-036
Proj ID BR 2011(282)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.057 385584.40 0.00 375380.82 97.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-23-14
Work Began 11-24-14
Work Completed  
Time Computed 07-09-14
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 33
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-27-035
RIO GRANDE REBAR PLACING, LTD. (0.51%)
LAREDO STRIPING INC. (2.58%)
SOIL-TECH, INC.(1.92%)
PAVEMENT MARKINGS INC. (0.59%)
Contract # 04143227
Totals 826051.45 0.00 488234.60 59.1

CountySTARR
Highway FM 755
From FM 755 REALIGNMENT, US 83 N.
To FM 755
CSJ 1103-04-027
Proj ID CBI 2014(896)
Work Type REALIGN / W PARTIAL WIDENING TO 4 LNS
 
2.400 10733925.48 292903.67 6276716.12 59.2
Work Order 10-28-14
Work Began 01-27-15
Work Completed  
Time Computed 11-13-14
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 442
Percent Time Used 116
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1103-04-027
HIGHWAY BARRICADES AND SERVICES, LLC (1.09%)
J & P TRUCKING AND HAULING (5.17%)
D S TEXAS ICON CONSTRUCTION, LLC (0.73%)
CERTIFIED PLACERS LLC(0.98%)
W. W. FOUNDATION DRILLING, LTD.(4.64%)
DUSTROL, INC.(0.20%)
LAREDO STRIPING INC. (0.48%)
Contract # 09143042
Totals 10733925.48 292903.67 6276716.12 59.2

CountyCAMERON
Highway FM 803
From IH-69E @ RANCHO VIEJO AVENUE
To 0.077 MI N OF SH 100
CSJ 1138-02-015
Proj ID STP 2014(897)MM
Work Type REALIGN & WIDEN TO 4 LANES
 
2.763 10494854.48 54862.35 8705899.10 82.9
Work Order 12-17-14
Work Began 02-09-15
Work Completed  
Time Computed 01-02-15
Contract Working Days 560
Addl Days Granted 10
Working Days Charged 438
Percent Time Used 76
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1138-02-015
SOIL-TECH, INC.(2.09%)
RHYNER CONSTRUCTION SERVICES, INC. (0.49%)
LAREDO STRIPING INC. (0.68%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.76%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (1.96%)
RIO GRANDE REBAR PLACING, LTD. (0.21%)
Contract # 09143237
Totals 10494854.48 54862.35 8705899.10 82.9

CountyHIDALGO
Highway FM 3461
From I RD EAST
To FM 1426
CSJ 1802-02-009
Proj ID STP 2013(857)MM
Work Type CONST 4 LN DIV URB
 
0.831 3077777.77 0.00 3087026.20 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 10-14-13
Work Completed  
Time Computed 09-14-13
Contract Working Days 171
Addl Days Granted 5
Working Days Charged 295
Percent Time Used 167
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 1802-02-009
SHINN & GREGORY, INC.(1.49%)
PAVEMENT MARKINGS INC. (2.06%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.40%)
G & E ESCOBEDO CONSTRUCTION, INC.(0.33%)
Contract # 07133023
Totals 3077777.77 0.00 3087026.20 99.9

CountyHIDALGO
Highway FM 1925
From FM 681
To FM 2220
CSJ 1803-01-037
Proj ID STP 2016(127)
Work Type REHABILITATE ROADWAY
 
5.523 8117383.10 495271.72 1412943.89 17.4
Work Order 11-24-15
Work Began 02-02-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 16
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1803-01-037
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (0.78%)
GO UNDERGROUND, LIMITED LIABILITY COMPANY(7.11%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.18%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.74%)
D&S TEXAS ICON CONSTRUCTION(2.53%)
Contract # 10153209
Totals 8117383.10 495271.72 1412943.89 17.4

CountyHIDALGO
Highway FM 1925
From 0.13 MI. EAST OF KENYON RD
To 0.21 MI. EAST OF FM 907
CSJ 1803-02-028
Proj ID C 1803-2-28
Work Type GRAD, BASE & SURF
 
1.060 2891653.04 0.00 1533240.00 53.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 35
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 1803-02-028
SALAZAR UTILITY CONSTRUCTION INC.(2.49%)
GULF COAST CONTRACTORS, INC. (0.39%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.94%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.46%)
Contract # 07153234
Totals 2891653.04 0.00 1533240.00 53.0

CountyHIDALGO
Highway FM 2220 ETC
From SH 107
To 0.21 MI N OF MI 5 RD.
CSJ 2094-01-059
Proj ID STP 2017(050)
Work Type SEAL COAT
 
38.218 1601730.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2094-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163216
Totals 1601730.75 0.00 0.00 0.0

CountyCAMERON
Highway FM 106
From FM 1847 ON GEN BRANT RD, E & S
To FM 510
CSJ 2243-01-009
Proj ID C 2243-1-9
Work Type GR, STRS & SURF
 
11.440 15555190.89 692331.80 5460524.74 35.1
Work Order 10-28-14
Work Began 00-00-00
Work Completed  
Time Computed 11-09-15
Contract Working Days 420
Addl Days Granted 29
Working Days Charged 244
Percent Time Used 54
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2243-01-009
ALTUS TRAFFIC MANAGEMENT LLC (0.39%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (DONNA) (0.29%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.46%)
HURFCO INDUSTRIES, INC. DBA HURRICANE FENCE COMPANY(3.11%)
J & P TRUCKING AND HAULING ( 17.32%)
LAREDO STRIPING INC. (0.37%)
Contract # 09143004
Totals 15555190.89 692331.80 5460524.74 35.1

CountyHIDALGO
Highway SH 364
From SH 495 N
To FM 1924
CSJ 2966-01-009
Proj ID C 2966-1-9
Work Type GRADING, STRUCTURES & SURFACING
 
2.000 6848709.56 0.00 1118977.17 16.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 02-16-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 5
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2966-01-009
GULF COAST CONTRACTORS, INC. (0.92%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.25%)
MUSTANG COLT SERVICES, INC.(4.14%)
Contract # 11153214
Totals 6848709.56 0.00 1118977.17 16.3