Monthly State Let Construction Report For Pharr District As Of Sep 15, 2014 Page 3 Of 3

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHIDALGO
Highway CS
From UNIVERSITY DRIVE AT 6TH STREET
To CANO ST. AT SOUTHERN PACIFIC R.R.
CSJ 0921-02-314
Proj ID STP 2014(145)TE
Work Type RENOVATE EDINBURG TRAIN DEPOT
 
0.100 165450.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BONCO LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-314
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143057
Totals 165450.00 0.00 0.00 0.0

CountyHIDALGO
Highway CS
From IH 2 @ VERMONT AVE
To IH 2 @ MERCEDES MAIN CANAL
CSJ 0921-02-315
Proj ID STP 2014(147)TE
Work Type LANDSCAPE IMPROVEMENTS
 
0.750 544690.00 0.00 0.00 0.0
Work Order 07-22-14
Work Began 00-00-00
Work Completed  
Time Computed 08-07-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-315
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143238
Totals 544690.00 0.00 0.00 0.0

CountyCAMERON
Highway CS
From ON PRIMERA RD, FROM STUART PLACE RD
To US 77
CSJ 0921-06-187
Proj ID STP 2005(292)
Work Type GRAD, BASE, SURF & STRS
 
2.256 5399888.00 0.00 5292839.13 98.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-27-11
Work Began 04-03-12
Work Completed  
Time Computed 10-13-11
Contract Working Days 390
Addl Days Granted 0
Working Days Charged 428
Percent Time Used 109
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-187
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (1.89%)
HIGHWAY TECHNOLOGIES, INC. (1.56%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.18%)
D S TEXAS ICON CONSTRUCTION, LLC (0.11%)
Contract # 08113255
Totals 5399888.00 0.00 5292839.13 98.7

CountyCAMERON
Highway VA
From LOCATED IN VICINITY OF GSA FACILITY
To LOS INDIOS FREE TRADE INT'L BRIDGE
CSJ 0921-06-208
Proj ID BOR 2002(633)
Work Type CONSTRUCT BSIF
 
0.001 6949739.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 262
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-208
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143056
Totals 6949739.75 0.00 0.00 0.0

CountyCAMERON
Highway CR
From CR 830(NELSON RD) .9 MI S OF FM1561
To @ RESACA DE LOS FRESNOS AA08-30-001
CSJ 0921-06-211
Proj ID BR 2005(837)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.123 618001.28 6873.52 597386.73 96.6
CountyWILLACY
Highway CR
From #AA03-33-001 CR333 0.8 M W OF FM490
To MAIN EAST CANAL
CSJ 0921-27-033
Proj ID BR 2010(292)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.114 340905.49 2267.07 93617.02 27.4
CountyWILLACY
Highway CR
From #AA01-58-001 @ OLD W MAIN DRAIN
To .67 MI N OF FM 1762
CSJ 0921-27-034
Proj ID BR 2011(279)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.095 448232.92 26886.61 343883.98 76.7
Work Order 10-24-13
Work Began 11-08-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 80
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-27-033
SOIL-TECH, INC.(0.59%)
LAREDO STRIPING INC. (3.06%)
MUNOZ FOUNDATION DRILLING, INC.(3.68%)
PAVEMENT MARKINGS INC. (0.59%)
MASTERPIECE GRINDING & GROOVING, LLC (0.31%)
TEXAS HIGHWAY SYSTEMS, INC.(1.45%)
ITJR CONTRACTORS, LLC DBA VALCO CONTRACTORS(0.40%)
ACE DRILLING, INC. (1.85%)
RHYNER CONSTRUCTION SERVICES, INC. (0.29%)
DRILL PIER CONSTRUCTION, LLC (0.94%)
Contract # 07133250
Totals 1407139.69 36027.20 1034887.73 73.5

CountyCAMERON
Highway VA
From CITY OF HARLINGEN
To LP 499 TO 25TH ST,25TH ST TO BUS 77
CSJ 0921-06-243
Proj ID STP 2011(241)TE
Work Type PEDESTRIAN AND BICYCLE TRAIL
 
3.600 1485304.38 63978.76 1194977.36 80.4
Work Order 06-26-13
Work Began 07-25-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 330
Addl Days Granted 0
Working Days Charged 226
Percent Time Used 68
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-243
TEXAS HIGHWAY SYSTEMS, INC.(4.31%)
VALLEY STRIPING CORP.(0.54%)
EXTERIOR DESIGNS (2.73%)
D & T CONSTRUCTION, INC. ( 58.14%)
Contract # 04133003
Totals 1485304.38 63978.76 1194977.36 80.4

CountySTARR
Highway CS
From US 83 N ON AVASOLO ST.
To FM 755
CSJ 0921-26-015
Proj ID STP 2006(304)ES
Work Type REHAB PAV & C & G
 
0.678 1371513.37 0.00 1439859.61 99.9
CountySTARR
Highway FM 755
From US 83 NORTH
To 0.235 MI N OF FM 755/AVASOLO INTERS
CSJ 1103-04-025
Proj ID STP 2009(711)ES
Work Type REHAB PAV & ADD C & G
 
0.921 2521180.59 0.00 2649921.11 99.9
Work Order 08-10-09
Work Began 10-20-09
Work Completed  
Time Computed 08-26-09
Contract Working Days 285
Addl Days Granted 162
Working Days Charged 556
Percent Time Used 124
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1103-04-025
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 29.53%)
HIGHWAY TECHNOLOGIES, INC. (0.94%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.17%)
SOIL-TECH, INC.(0.62%)
STAR OPERATIONS, INC.(1.94%)
ANDERSON COLUMBIA CO., INC.( 17.88%)
TEXAS HIGHWAY SYSTEMS, INC.(1.12%)
Contract # 06093220
Totals 3892693.96 0.00 4089780.72 99.9

CountyWILLACY
Highway CR
From CR 156 STR AA01-64-002
To OLD WEST MAIN DRAIN
CSJ 0921-27-035
Proj ID BR 2011(283)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.064 440467.05 0.00 0.00 0.0
CountyWILLACY
Highway CR
From #AA01-74-001 @ WEST MAIN DRAIN
To .05 MI W OF BUS 77
CSJ 0921-27-036
Proj ID BR 2011(282)
Work Type REPLACE BRIDGE & RECONST APPROACHES
 
0.057 385584.40 0.00 0.00 0.0
Work Order 06-23-14
Work Began 00-00-00
Work Completed  
Time Computed 07-09-14
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-27-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143227
Totals 826051.45 0.00 0.00 0.0

CountySTARR
Highway FM 755
From FM 755 REALIGNMENT, US 83 N.
To FM 755
CSJ 1103-04-027
Proj ID CBI 2014(896)
Work Type REALIGN / W PARTIAL WIDENING TO 4 LNS
 
2.400 10733925.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1103-04-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143042
Totals 10733925.48 0.00 0.00 0.0

CountyCAMERON
Highway FM 803
From IH-69E @ RANCHO VIEJO AVENUE
To 0.077 MI N OF SH 100
CSJ 1138-02-015
Proj ID STP 2014(897)MM
Work Type REALIGN & WIDEN TO 4 LANES
 
2.763 10494854.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 560
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1138-02-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143237
Totals 10494854.48 0.00 0.00 0.0

CountyCAMERON
Highway FM 1420 ETC
From WILLACY/CAMERON CL
To FM 508
CSJ 1425-02-015
Proj ID STP 2014(321)
Work Type SEAL COAT
 
40.128 1725815.63 613839.52 1652203.82 95.7
Work Order 11-08-13
Work Began 07-25-14
Work Completed  
Time Computed 11-24-13
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 54
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1425-02-015
INTERSTATE BARRICADES & MARKINGS, INC. ( 13.26%)
Contract # 10133226
Totals 1725815.63 613839.52 1652203.82 95.7

CountySTARR
Highway FM 490
From FM 755
To HIDALGO COUNTY LINE
CSJ 1490-01-013
Proj ID STP 2013(797)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
14.109 3576796.96 6570.00 3362189.93 94.0
Work Order 08-20-13
Work Began 09-24-13
Work Completed  
Time Computed 09-05-13
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 131
Percent Time Used 94
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1490-01-013
VALLEY INFRASTRUCTURE, INC.(4.33%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.79%)
SOIL-TECH, INC.(4.58%)
PAVEMENT MARKINGS INC. (1.85%)
Contract # 06133021
Totals 3576796.96 6570.00 3362189.93 94.0

CountyCAMERON
Highway FM 1847
From FM 106
To FM 2925
CSJ 1801-02-014
Proj ID STP 2013(899)
Work Type REHAB AND WIDEN ROADWAY
 
7.340 3465083.17 451416.91 3256082.12 94.3
Work Order 09-17-13
Work Began 10-28-13
Work Completed  
Time Computed 10-03-13
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 107
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1801-02-014
GO UNDERGROUND, LIMITED LIABILITY COMPANY(4.76%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.13%)
D S TEXAS ICON CONSTRUCTION, LLC (4.51%)
Contract # 07133242
Totals 3465083.17 451416.91 3256082.12 94.3

CountyHIDALGO
Highway FM 3461
From I RD EAST
To FM 1426
CSJ 1802-02-009
Proj ID STP 2013(857)MM
Work Type CONST 4 LN DIV URB
 
0.831 3077777.77 308939.81 2361349.57 79.1
Work Order 08-29-13
Work Began 10-14-13
Work Completed  
Time Computed 09-14-13
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 248
Percent Time Used 145
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 1802-02-009
SHINN & GREGORY, INC.(1.49%)
PAVEMENT MARKINGS INC. (2.06%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.40%)
G & E ESCOBEDO CONSTRUCTION, INC.(0.33%)
Contract # 07133023
Totals 3077777.77 308939.81 2361349.57 79.1

CountyCAMERON
Highway FM 106
From FM 1847 ON GEN BRANT RD, E & S
To FM 510
CSJ 2243-01-009
Proj ID C 2243-1-9
Work Type GR, STRS & SURF
 
11.440 15555190.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2243-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143004
Totals 15555190.89 0.00 0.00 0.0

CountyCAMERON
Highway FM 2480
From FM 3069
To FM 510
CSJ 2366-01-009
Proj ID STP 2012(644)
Work Type REHABILITATE AND RESTORE PAVEMENT
 
4.280 2868112.75 156405.06 291109.42 10.1
Work Order 05-13-14
Work Began 00-00-00
Work Completed  
Time Computed 05-29-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 2
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2366-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143243
Totals 2868112.75 156405.06 291109.42 10.1

CountyJIM HOGG
Highway FM 3073
From FM 649
To SH 16
CSJ 3099-01-008
Proj ID STP 2013(798)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
16.247 5647170.00 454585.52 3362506.38 59.5
Work Order 09-05-13
Work Began 01-29-14
Work Completed  
Time Computed 09-21-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 80
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3099-01-008
ABC EROSION CONTROL, INC.(3.28%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.59%)
FLASHER EQUIPMENT COMPANY(0.34%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.70%)
FOREMOST PAVING, INC.( 36.38%)
Contract # 06133016
Totals 5647170.00 454585.52 3362506.38 59.5