Monthly State Let Construction Report For Pharr District As Of Aug 12, 2014 Page 2 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHIDALGO
Highway US 281
From FM 162
To FM 490
CSJ 0255-07-128
Proj ID STP 2012(793)MM
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.372 12040791.34 88801.70 9277596.04 77.0
CountyHIDALGO
Highway US 281
From FM 2812
To FM 162
CSJ 0255-07-129
Proj ID C 255-7-129
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.173 7776379.96 200390.87 4390289.09 56.4
Work Order 10-18-12
Work Began 11-05-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 396
Percent Time Used 99
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-128
STAR OPERATIONS, INC.(0.59%)
LAREDO STRIPING INC. (3.21%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.30%)
WEST TEXAS RUMBLE STRIP(0.03%)
D S TEXAS ICON CONSTRUCTION, LLC (0.95%)
ANDERSON COLUMBIA CO., INC.( 27.10%)
CERTIFIED PLACERS LLC(0.19%)
PRIMATE CONSTRUCTION, INC. (0.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00%)
M & M INDUSTRIAL PAINTING(0.05%)
NORTH TEXAS REBAR, LLC (0.06%)
GULF COAST CONTRACTORS, INC. (0.07%)
Contract # 08123207
Totals 19817171.30 289192.57 13667885.13 68.9

CountyKENEDY
Highway US 77
From 0.87 MI S OF LA PARRA AVE
To 0.71 MI N OF LA PARRA AVE
CSJ 0327-02-050
Proj ID NH 2012(626)
Work Type CONSTRUCT OVERPASS
 
1.578 10282198.94 117341.61 10481453.33 99.9
Work Order 08-10-12
Work Began 09-10-12
Work Completed  
Time Computed 08-27-12
Contract Working Days 340
Addl Days Granted 20
Working Days Charged 360
Percent Time Used 100
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-02-050
HIGHWAY BARRICADES AND SERVICES, LLC (0.69%)
TEXAS DIAMOND CONSTRUCTION (1.68%)
LAREDO STRIPING INC. (1.88%)
SOIL-TECH, INC.(1.12%)
MCALLEN CONSTRUCTION, INC. ( 21.52%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.04%)
RIO GRANDE REBAR PLACING, LTD. (0.30%)
WEBBER BARRIER SERVICES, LLC.(0.53%)
HOUSTON SAWING & DRILLING(0.05%)
SCOTT DERR PAINTING CO, LLC(0.07%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
HURRICANE FENCE COMPANY(0.62%)
Contract # 06123223
Totals 10282198.94 117341.61 10481453.33 99.9

CountyKENEDY
Highway US 77
From KLEBERG/KENEDY COUNTY LINE
To 12.298 MI S OF KLEBERG/ KENEDY CL
CSJ 0327-02-051
Proj ID NH 2014(021)
Work Type MILL & OVERLAY N.B. & S.B. ROADWAYS
 
12.298 7854465.72 2373967.57 7111579.01 90.5
CountyKENEDY
Highway US 77
From 11.700 MI S OF KLEBERG/KENNEDY CL
To 12.28 MI S OF KLEBERG/KENEDY CL
CSJ 0327-03-046
Proj ID NH 2014(021)
Work Type MILL & OVERLAY N.B. & S.B. ROADWAYS
 
0.580 218933.50 0.00 201779.30 92.1
Work Order 01-06-14
Work Began 01-30-14
Work Completed  
Time Computed 01-27-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 73
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-02-051
A BROTHERS MILLING, LLC(1.28%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.44%)
SOIL-TECH, INC.(0.28%)
WEST TEXAS RUMBLE STRIP(0.20%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.31%)
Contract # 09133209
Totals 8073399.22 2373967.57 7313358.31 90.5

CountyWILLACY
Highway US 77
From FM 1018
To 0.3 MILES N OF FM 498
CSJ 0327-10-053
Proj ID NH 1102(173)
Work Type CONSTRUCT MAINLANES
 
3.335 11158184.54 -38473.99 10616264.76 97.6
CountyWILLACY
Highway US 77
From 0.3 MILES N OF FM 498
To FM 3168
CSJ 0327-10-054
Proj ID NH 1102(173)
Work Type CONSTRUCT OVERPASS AND MAINLANES
 
4.399 14602597.36 1671277.14 13766993.95 94.2
Work Order 08-30-11
Work Began 09-09-11
Work Completed  
Time Computed 09-15-11
Contract Working Days 473
Addl Days Granted 0
Working Days Charged 573
Percent Time Used 121
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-053
STAR OPERATIONS, INC.(2.01%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.04%)
CABCOS CONTRACTORS LLC (2.33%)
HIGHWAY TECHNOLOGIES, INC. (0.60%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(1.24%)
SHINN & GREGORY, INC.(0.84%)
CERTIFIED PLACERS LLC(0.24%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
EXTERIOR DESIGNS (0.98%)
GUERRA CONSTRUCTION COMPANY(0.67%)
MCALLEN CONSTRUCTION, INC. ( 16.81%)
SOIL-TECH, INC.(0.84%)
LAREDO STRIPING INC. (1.22%)
RIO GRANDE REBAR PLACING, LTD. (0.08%)
D S TEXAS ICON CONSTRUCTION, LLC (0.33%)
TEXAS CORDIA CONSTRUCTION, LLC (0.50%)
FOUR-B PAVING, INC.(0.21%)
SCOTT DERR PAINTING CO, LLC(0.05%)
Contract # 07113201
Totals 25760781.90 1632803.15 24383258.71 95.7

CountyCAMERON
Highway SH 100 ETC
From 0.138 MI EAST OF US 77
To FM 803
CSJ 0331-01-040
Proj ID STP 2014(023)
Work Type SEAL COAT
 
58.978 2737444.27 803601.25 1359120.30 49.6
Work Order 01-06-14
Work Began 00-00-00
Work Completed  
Time Computed 01-22-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 8
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-040
INTERSTATE BARRICADES & MARKINGS, INC. ( 13.58%)
CHEROKEE SERVICES(0.22%)
Contract # 09133010
Totals 2737444.27 803601.25 1359120.30 49.6

CountyCAMERON
Highway SH 100 ETC
From 1.5 MI WEST OF FM 510
To HARDING BLVD. (1.7 MI E OF FM 510)
CSJ 0331-02-050
Proj ID STP 2014(363)HESG
Work Type CENTERLINE TEXTURING
 
81.251 740429.05 0.00 0.00 0.0
Work Order 02-13-14
Work Began 00-00-00
Work Completed  
Time Computed 03-03-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-02-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143005
Totals 740429.05 0.00 0.00 0.0

CountyHIDALGO
Highway FM 681
From FM 681 (N) @ FM 2221
To SH 107
CSJ 0669-01-043
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
1.784 12345193.52 271253.69 4797974.58 38.8
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF SH 364 (LA HOMA)
To .25 MI W OF MOOREFIELD RD
CSJ 0862-01-037
Proj ID STP 2013(040)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.574 2333144.96 0.00 174575.00 7.4
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF MOOREFIELD RD
To FM 681
CSJ 0862-01-047
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
0.338 2162777.75 0.00 185025.60 8.5
Work Order 08-19-13
Work Began 00-00-00
Work Completed  
Time Computed 09-04-13
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 20.85%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29%)
SOIL-TECH, INC.(1.94%)
PAVEMENT MARKINGS INC. (1.01%)
VALLEY INFRASTRUCTURE, INC.( 10.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76%)
Contract # 06133203
Totals 16841116.23 271253.69 5157575.18 30.6

CountyCAMERON
Highway SH 550
From 0.70 MI N OF FM 3248
To OLD PORT ISABEL RD
CSJ 0684-01-066
Proj ID STP 2009(662)ES
Work Type CONST TOLLED MNLNS & FRTGE ACCESS
 
1.060 8113949.40 0.00 8305236.05 99.9
CountyCAMERON
Highway SH 550
From OLD PORT ISABEL RD, ON NEW LOC
To SH 48
CSJ 3622-01-001
Proj ID STP 2009(662)ES
Work Type CONSTR TOLLED M.L. & FRT ACCESS
 
2.866 26047792.00 0.00 25877046.38 99.9
Work Order 05-13-10
Work Began 08-02-10
Work Completed  
Time Computed 05-29-10
Contract Working Days 390
Addl Days Granted 67
Working Days Charged 655
Percent Time Used 143
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3622-01-001
BOOTHE BROTHERS PAVING COMPANY, INC. (0.47%)
CHICO TRUCKING CO., INC. (1.68%)
STAR OPERATIONS, INC.(3.75%)
GUERRA CONSTRUCTION COMPANY(0.68%)
CERTIFIED PLACERS LLC(0.54%)
HIGHWAY TECHNOLOGIES, INC. (0.34%)
JAVALINA CONSTRUCTION SOUTH, INC.(0.03%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
HJC FARMS, INC.(0.21%)
WEBBER BARRIER SERVICES, INC.(3.17%)
WRANGLER CONTRACTING (0.25%)
MCALLEN CONSTRUCTION, INC. ( 11.45%)
ROVAN MARINE, LLC(5.85%)
SOIL-TECH, INC.(0.23%)
S & S PAINTING (0.31%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(0.22%)
CORRPRO COMPANIES, INC.(0.07%)
CABCOS CONTRACTORS LLC (0.82%)
R & M CONCRETE & FENCING (0.07%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
ROVAN, LLC (3.28%)
FOREMOST PAVING, INC.(0.36%)
EROSION PREVENTION PRODUCTS(0.26%)
TEXAS DIAMOND CONSTRUCTION (0.05%)
Contract # 03103002
Totals 34161741.40 0.00 34182282.43 99.9

CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI N OF MILE 16 N
CSJ 0698-03-084
Proj ID STP 2012(699)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.249 2681776.78 86.25 940297.68 35.0
CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI. N. OF MIE 16 N
CSJ 0698-03-086
Proj ID RW 0698-3-86
Work Type ROW ACQUISITION
 
0.249 467213.71 15918.90 416778.91 89.2
Work Order 01-03-13
Work Began 04-09-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 132
Percent Time Used 80
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-084
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.44%)
VALLEY STRIPING CORP.(1.43%)
Contract # 09123235
Totals 3148990.49 16005.15 1357076.59 43.0

CountyHIDALGO
Highway FM 1427
From 1.9 MI SOUTH OF US 83
To 0.03 MI SOUTH BUS 83
CSJ 0862-02-018
Proj ID STP 2012(665)
Work Type REHAB PAVEMENT & WIDEN TO 40'
 
4.571 3777777.77 4571.94 3730042.00 100.0
Work Order 08-28-12
Work Began 02-19-13
Work Completed 06-25-14
Time Computed 09-13-12
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 278
Percent Time Used 99
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0862-02-018
PAVEMENT MARKINGS INC. (3.02%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.69%)
Contract # 07123211
Totals 3777777.77 4571.94 3730042.00 100.0

CountyHIDALGO
Highway FM 493
From CHAMPION ST.
To US 281
CSJ 0863-01-047
Proj ID HP 2014(907)
Work Type RECONSTRUCT & ADD SHOULDERS
 
5.681 11333645.32 0.00 0.00 0.0
CountyHIDALGO
Highway FM 493
From BUSINESS 83
To CHAMPION AVE
CSJ 0863-01-053
Proj ID HP 2014(907)
Work Type OVERLAY
 
0.768 579679.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 480
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143208
Totals 11913324.88 0.00 0.00 0.0

CountyHIDALGO
Highway FM 494
From SUNSET LANE
To COLORADO ST
CSJ 0864-01-065
Proj ID STP 2013(897)MM
Work Type SIGNAL RETIMING & ADD LANES @ US 83
 
1.710 787777.77 59282.14 759973.10 96.4
Work Order 01-06-14
Work Began 00-00-00
Work Completed  
Time Computed 01-22-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 63
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0864-01-065
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 11.91%)
VALLEY STRIPING CORP.( 10.98%)
Contract # 08133238
Totals 787777.77 59282.14 759973.10 96.4

CountyHIDALGO
Highway CS
From MILE 2 WEST, FROM MILE 12 NORTH
To .44 MI NORTH OF US 83
CSJ 0921-02-170
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
4.750 4729717.44 264096.28 511672.98 10.8
CountyHIDALGO
Highway CS
From ON MILE 2 NORTH,.44 MI N OF US 83
To US 83
CSJ 0921-02-307
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
0.440 744320.06 0.00 101200.00 13.5
Work Order 06-26-13
Work Began 00-00-00
Work Completed  
Time Computed 07-12-13
Contract Working Days 480
Addl Days Granted 6
Working Days Charged 36
Percent Time Used 7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-170
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 12.90%)
SOIL-TECH, INC.(6.29%)
PAVEMENT MARKINGS INC. (0.92%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.48%)
Contract # 04133203
Totals 5474037.50 264096.28 612872.98 11.1

CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-171
Proj ID HP 2008(134)
Work Type CONSTR 2 LN RDWY W / 4 LA TRANS
 
3.000 4309680.38 1160.38 3294232.25 80.4
CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-288
Proj ID HP 1102(318)
Work Type ROW ACQ.; UTL. ADJ.
 
3.000 849420.66 0.00 641277.75 75.4
Work Order 08-25-11
Work Began 10-11-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 478
Percent Time Used 149
Contractor(s)
CONTINENTAL CASUALTY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-171
HIGHWAY TECHNOLOGIES, INC. (0.69%)
SOIL-TECH, INC.(1.28%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.74%)
PAVEMENT MARKINGS INC. (0.98%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.99%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.56%)
VALLEY INFRASTRUCTURE, INC.( 33.21%)
Contract # 07113251
Totals 5159101.04 1160.38 3935510.00 79.6

CountyHIDALGO
Highway VA
From US CUSTOMS PORT OF ENTRY EXIT
To US 281
CSJ 0921-02-173
Proj ID BOR 2002(632)
Work Type CONSTRUCT BSIF
 
1.350 20116428.45 7287.16 17388720.51 86.6
Work Order 08-25-11
Work Began 10-18-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 380
Addl Days Granted 115
Working Days Charged 517
Percent Time Used 104
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173
BULLARD CONSTRUCTION, INC. ( 19.38%)
HIGHWAY TECHNOLOGIES, INC. (1.61%)
HURRICANE FENCE COMPANY(0.96%)
METTLER TOTLEDO(5.03%)
NORTH TEXAS REBAR, LLC (0.54%)
ROVAN, LLC (3.33%)
SOIL-TECH, INC.(1.21%)
STAR OPERATIONS, INC.( 19.28%)
TSI LABORATORIES SOUTH,INC.(0.04%)
RGV ALLIANCE CONSTRUCTION, LLC (0.54%)
FOREMOST PAVING, INC.(9.34%)
CONTINENTAL REFRIGERATION(1.12%)
M & A PAINTING SERVICE, INC. (0.39%)
L & G CONCRETE CONSTRUCTION, INC.(3.86%)
SOUTHERN STEEL FABRICATORS (4.27%)
CANTU"S PLUMBING (0.88%)
METRO ELECTRIC, INC. (1.81%)
ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC.(0.07%)
INTERTECH FLOORING (0.33%)
WEIGHT AND TEST SOLUTIONS, INC.(0.70%)
RGV ALLIANCE CONSTRUCTION, LLC (0.12%)
MCALLEN PEST CONTROL (0.03%)
THE CABINET SHOP (0.24%)
PRIME CONSTRUCTION (0.10%)
TAYLOR LIGHTNING PROTECTION(0.14%)
TAMU, DBA CONSTRUCTION SPECIALTIES (0.37%)
T & D SOLUTIONS, LTD (0.87%)
Contract # 07113207
Totals 20116428.45 7287.16 17388720.51 86.6

CountyHIDALGO
Highway CS
From ON SAM HOUSTON, US 281
To "I" RD
CSJ 0921-02-256
Proj ID STP 2012(540)MM
Work Type ADD LEFT TURN CENTER LANE
 
1.016 2174313.28 0.00 2204225.94 100.0
CountyHIDALGO
Highway CS
From ON SAM HOUSTON, US 281
To "I" RD
CSJ 0921-02-294
Proj ID RW 921-2-294
Work Type ROW UTL. ADJ.
 
1.016 224575.60 0.00 200086.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-21-12
Work Began 08-01-12
Work Completed 05-22-14
Time Computed 07-07-12
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 384
Percent Time Used 106
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-256
VALLEY STRIPING CORP.(1.31%)
SOIL-TECH, INC.(0.18%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.76%)
Contract # 05123227
Totals 2398888.88 0.00 2404312.54 100.0

CountyHIDALGO
Highway CS
From CITY OF EDINBURG, EISENHOWER ELEM
To & MEMORIAL MIDDLE SCHOOL
CSJ 0921-02-258
Proj ID STP 1102(186)SRS
Work Type SIDEWALK, CROSSWALK, BIKE RACKS
 
13.043 2667755.20 1683.10 2691284.23 99.9
Work Order 11-09-12
Work Began 12-03-12
Work Completed  
Time Computed 11-25-12
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 230
Percent Time Used 95
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-258
STAR OPERATIONS, INC.( 17.31%)
VALLEY STRIPING CORP.(3.07%)
ACE DRILLING, INC. (0.43%)
Contract # 09123221
Totals 2667755.20 1683.10 2691284.23 99.9

CountyHIDALGO
Highway CS
From CITY OF EDINBURG,
To CANO-GONZALEZ ELEMENTARY
CSJ 0921-02-266
Proj ID STP 1102(187)SRS
Work Type SIDEWALKS, CROSSWALKS, BIKE RACKS
 
1.600 4251199.44 231660.20 2323299.46 54.6
Work Order 08-02-13
Work Began 00-00-00
Work Completed  
Time Computed 08-18-13
Contract Working Days 465
Addl Days Granted 0
Working Days Charged 163
Percent Time Used 35
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-266
VALLEY STRIPING CORP.(2.39%)
STAR OPERATIONS, INC.( 11.14%)
Contract # 05133221
Totals 4251199.44 231660.20 2323299.46 54.6

CountyHIDALGO
Highway VA
From CITY OF HIDALGO, EAST
To TO SANTA ANNA NWR TO MCALLEN
CSJ 0921-02-282
Proj ID STP 2011(242)TE
Work Type PEDESTRIAN & BICYCLE ACCESS
 
9.788 1277719.46 2364.00 1346673.42 99.9
Work Order 08-08-13
Work Began 08-28-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 180
Percent Time Used 100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-282
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 17.50%)
EXTERIOR DESIGNS (2.24%)
PAVEMENT MARKINGS INC. (2.83%)
D S TEXAS ICON CONSTRUCTION, LLC (9.05%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.87%)
DELTA SPECIALTIES SIGNS & SUPPLIES (2.75%)
J & P TRUCKING AND HAULING (1.82%)
2GS, LLC (1.35%)
CABCOS CONTRACTORS LLC (0.58%)
Contract # 05133019
Totals 1277719.46 2364.00 1346673.42 99.9

CountyHIDALGO
Highway VA
From VARIOUS LOCATIONS IN HIDALGO COUNTY
To .
CSJ 0921-02-313
Proj ID STP 2014(446)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1657902.70 167124.87 334861.57 20.1
Work Order 04-25-14
Work Began 00-00-00
Work Completed  
Time Computed 05-11-14
Contract Working Days 242
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 20
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-313
TEXAS CONCRETE AND DEMOLITION, INC.( 26.30%)
CERTIFIED PLACERS LLC(0.72%)
SOIL-TECH, INC.(1.22%)
VALLEY STRIPING CORP.(5.09%)
Contract # 02143016
Totals 1657902.70 167124.87 334861.57 20.1

page 1 | page 2 | page 3