Monthly State Let Construction Report For Pharr District As Of Apr 10, 2015 Page 2 Of 3

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCAMERON
Highway US 281
From 0.24 MI E OF FM 506
To .099 MI E OF HIDALGO/CAMERON CL
CSJ 0220-03-027
Proj ID STP 2015(380)
Work Type REHABILITATE & WIDEN ROADWAY
 
2.789 5229348.79 247046.00 249546.00 4.7
Work Order 01-28-15
Work Began 00-00-00
Work Completed  
Time Computed 02-13-15
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 5
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-027
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.02%)
LAREDO STRIPING INC. (3.35%)
PAVEMENT MARKINGS INC. (2.49%)
SOIL-TECH, INC.(1.38%)
VALLEY INFRASTRUCTURE, INC.(8.38%)
Contract # 12143006
Totals 5229348.79 247046.00 249546.00 4.7

CountyCAMERON
Highway US 281
From 0.05 MI W OF FM 1479
To 0.24 MI EAST OF FM 506
CSJ 0220-03-028
Proj ID STP 2015(037)
Work Type REHAB & WIDEN EXIST ROADWAY SUPER 2
 
3.863 7709997.35 435840.00 499840.00 6.4
Work Order 11-25-14
Work Began 00-00-00
Work Completed  
Time Computed 12-11-14
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 1
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-028
HIGHWAY BARRICADES AND SERVICES, LLC (1.78%)
GO UNDERGROUND, LIMITED LIABILITY COMPANY(6.01%)
Contract # 09143009
Totals 7709997.35 435840.00 499840.00 6.4

CountyBROOKS
Highway US 281
From BUS 281 NORTH SIDE
To BROOKS COUNTY LINE
CSJ 0255-03-026
Proj ID HP 2009(663)ES
Work Type GR., STRS., AND SURF
 
4.133 40039527.43 9115.61 44047766.74 99.9
CountyBROOKS
Highway US 281
From SH 285
To BROOKS COUNTY LINE
CSJ 0255-03-031
Proj ID RW 255-3-31
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1792061.65 0.00 2122790.25 99.9
CountyBROOKS
Highway US 281
From BUS 281 NORTH SIDE
To BUS 281 SOUTH SIDE
CSJ 0255-14-001
Proj ID STP 2009(664)ES
Work Type GR., STRS., AND SURF
 
2.062 25860723.89 7822.90 25710410.12 99.4
Work Order 07-14-09
Work Began 08-18-09
Work Completed  
Time Computed 07-30-09
Contract Working Days 720
Addl Days Granted 167
Working Days Charged 1,211
Percent Time Used 136
Contractor(s)
ZURICH AMERICAN INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0255-03-026
HIGHWAY TECHNOLOGIES, INC. (0.46%)
LEAL CONSTRUCTION, INC.(3.11%)
MENDEZ EXCAVATION(0.27%)
RHYNER CONSTRUCTION SERVICES, INC. (0.15%)
SUNBELT EXPRESS SERVICES, INC. (0.77%)
EXTERIOR DESIGNS (0.76%)
W. W. FOUNDATION DRILLING, LTD.(2.75%)
LAREDO STRIPING INC. (0.64%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
CHICO TRUCKING CO., INC. (1.38%)
J & P TRUCKING AND HAULING (6.05%)
CABCOS CONTRACTORS LLC (1.64%)
STAR OPERATIONS, INC.(3.55%)
CRAWFORD YANT(0.16%)
CERTIFIED PLACERS LLC(0.47%)
RGV ALLIANCE CONSTRUCTION, L.L.C.(1.28%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.05%)
MORRIS CONSTRUCTION, INC.(0.31%)
CORTEZ TRUCKING TRANSPORT(1.82%)
DOUG'S DRIP IRRIGATION (0.16%)
G & E ESCOBEDO CONSTRUCTION, INC.(0.02%)
ADVANCED PUMPING CONCEPTS, INC.(0.08%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.15%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.14%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.25%)
D S TEXAS ICON CONSTRUCTION, LLC (0.01%)
DUSTROL, INC.(0.07%)
TEXAS CORDIA CONSTRUCTION, LLC (2.55%)
PIERCE CONSTRUCTION AND CONTRACT HAULING (1.53%)
GUERRA CONSTRUCTION COMPANY(0.30%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.30%)
D & C CONCRETE CUTTING, INC. (0.00%)
TEXAS CURB CUT, INC.(HUB)(0.01%)
HURRICANE FENCE COMPANY(0.28%)
Contract # 05093023
Totals 67692312.97 16938.51 71880967.11 99.9

CountyBROOKS
Highway US 281
From 448 FT E OF BUS 281
To US 281
CSJ 0255-04-085
Proj ID STP 2015(579)
Work Type DRAINAGE IMPROVEMENTS
 
0.305 1269572.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 00-00-00
Work Completed  
Time Computed 04-26-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0255-04-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153231
Totals 1269572.61 0.00 0.00 0.0

CountyBROOKS
Highway US 281
From US 281 @ FM 755
To .
CSJ 0255-05-034
Proj ID C 255-5-34
Work Type CONSTRUCT OVERPASS
 
1.373 13828828.39 11637.50 14262586.14 99.9
Work Order 10-24-12
Work Began 01-24-13
Work Completed  
Time Computed 11-09-12
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 454
Percent Time Used 190
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-05-034
CABCOS CONTRACTORS LLC (5.36%)
CERTIFIED PLACERS LLC(0.24%)
COWBELL TRAFFIC SERVICES, INC. (0.04%)
D S TEXAS ICON CONSTRUCTION, LLC (0.23%)
FOREMOST PAVING, INC.( 25.22%)
GUERRA CONSTRUCTION COMPANY(0.85%)
HIGHWAY TECHNOLOGIES, INC. (0.82%)
PRIMATE CONSTRUCTION, INC. (0.11%)
S & S BRIDGE PAINTING, INC.(0.05%)
STAR OPERATIONS, INC.(1.98%)
WEBBER BARRIER SERVICES, INC.(0.51%)
W. W. FOUNDATION DRILLING, LTD.(1.40%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.58%)
TEXAS HIGHWAY SYSTEMS, INC.(0.06%)
Contract # 08123006
Totals 13828828.39 11637.50 14262586.14 99.9

CountyHIDALGO
Highway US 281
From FM 162
To FM 490
CSJ 0255-07-128
Proj ID STP 2012(793)MM
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.372 12040791.34 57430.10 11018340.85 92.8
CountyHIDALGO
Highway US 281
From FM 2812
To FM 162
CSJ 0255-07-129
Proj ID C 255-7-129
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.173 7776379.96 30560.12 6902666.69 88.7
Work Order 10-18-12
Work Began 01-15-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 526
Percent Time Used 131
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-128
STAR OPERATIONS, INC.(0.59%)
LAREDO STRIPING INC. (3.21%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.30%)
WEST TEXAS RUMBLE STRIP(0.03%)
D S TEXAS ICON CONSTRUCTION, LLC (0.95%)
ANDERSON COLUMBIA CO., INC.( 27.10%)
CERTIFIED PLACERS LLC(0.19%)
PRIMATE CONSTRUCTION, INC. (0.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00%)
M & M INDUSTRIAL PAINTING(0.05%)
NORTH TEXAS REBAR, LLC (0.06%)
GULF COAST CONTRACTORS, INC. (0.07%)
Contract # 08123207
Totals 19817171.30 87990.22 17921007.54 91.2

CountyWILLACY
Highway US 77
From FM 1018
To 0.3 MILES N OF FM 498
CSJ 0327-10-053
Proj ID NH 1102(173)
Work Type CONSTRUCT MAINLANES
 
3.335 11158184.54 1629.25 10820613.82 99.2
CountyWILLACY
Highway US 77
From 0.3 MILES N OF FM 498
To FM 3168
CSJ 0327-10-054
Proj ID NH 1102(173)
Work Type CONSTRUCT OVERPASS AND MAINLANES
 
4.399 14602597.36 0.00 14002153.63 95.8
Work Order 08-30-11
Work Began 09-09-11
Work Completed  
Time Computed 09-15-11
Contract Working Days 473
Addl Days Granted 19
Working Days Charged 582
Percent Time Used 118
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-053
STAR OPERATIONS, INC.(2.01%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.04%)
CABCOS CONTRACTORS LLC (2.33%)
HIGHWAY TECHNOLOGIES, INC. (0.60%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(1.24%)
SHINN & GREGORY, INC.(0.84%)
CERTIFIED PLACERS LLC(0.24%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
EXTERIOR DESIGNS (0.98%)
GUERRA CONSTRUCTION COMPANY(0.67%)
MCALLEN CONSTRUCTION, INC. ( 16.81%)
SOIL-TECH, INC.(0.84%)
LAREDO STRIPING INC. (1.22%)
RIO GRANDE REBAR PLACING, LTD. (0.08%)
D S TEXAS ICON CONSTRUCTION, LLC (0.33%)
TEXAS CORDIA CONSTRUCTION, LLC (0.50%)
FOUR-B PAVING, INC.(0.21%)
SCOTT DERR PAINTING CO, LLC(0.05%)
Contract # 07113201
Totals 25760781.90 1629.25 24822767.45 97.3

CountyCAMERON
Highway SH 100
From IH 69E
To FM 803
CSJ 0331-01-042
Proj ID STP 2015(038)HESG
Work Type TEXTURIZE SHOULDERS
 
3.392 65580.80 0.00 60045.48 91.5
CountyCAMERON
Highway SH 100
From 0.52 MI E OF FM 1847
To 3.63 MI E OF FM 1847
CSJ 0331-01-043
Proj ID STP 2015(039)HESG
Work Type TEXTURIZE SHOULDERS
 
3.076 64141.20 0.00 63835.60 99.5
CountyWILLACY
Highway SH 186
From CR 465
To RM 564 + 0.9
CSJ 0433-05-024
Proj ID STP 2015(040)HESG
Work Type TEXTURIZE SHOULDERS
 
12.629 147103.86 1500.00 98780.16 67.1
CountyZAPATA
Highway SH 16
From JIM HOGG CL
To 20TH ST.
CSJ 0517-07-042
Proj ID STP 2015(041)HESG
Work Type TEXTURIZE SHOULDERS
 
22.280 259922.58 0.00 166971.12 64.2
Work Order 10-10-14
Work Began 12-05-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 61
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-042
BRYDL CONTRACTING, INC.( 13.55%)
Contract # 09143019
Totals 536748.44 1500.00 389632.36 72.5

CountyCAMERON
Highway SH 100 ETC
From 1.5 MI WEST OF FM 510
To HARDING BLVD. (1.7 MI E OF FM 510)
CSJ 0331-02-050
Proj ID STP 2014(363)HESG
Work Type CENTERLINE TEXTURING
 
81.251 740429.05 188802.60 625123.41 84.4
Work Order 02-13-14
Work Began 09-26-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 39
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-02-050
STAR OPERATIONS, INC.(7.29%)
BRYDL CONTRACTING, INC.( 31.07%)
Contract # 01143005
Totals 740429.05 188802.60 625123.41 84.4

CountyHIDALGO
Highway SH 107
From BUS 281
To US 281
CSJ 0342-01-087
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.862 531025.62 0.00 0.00 0.0
CountyHIDALGO
Highway SH 107
From RAIL ROAD TRACKS
To US 281 SQUARE
CSJ 0528-01-107
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.303 135280.47 0.00 0.00 0.0
CountyHIDALGO
Highway FM 2220
From US 83
To BUS 83
CSJ 2094-01-053
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.923 403673.46 0.00 0.00 0.0
CountyHIDALGO
Highway FM 2220
From BUS 83
To FM 1924
CSJ 2094-01-054
Proj ID STP 2014(254)
Work Type OVERLAY
 
2.882 1397798.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-24-15
Work Began 00-00-00
Work Completed  
Time Computed 03-27-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0342-01-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153213
Totals 2467777.77 0.00 0.00 0.0

CountyHIDALGO
Highway FM 681
From FM 681 (N) @ FM 2221
To SH 107
CSJ 0669-01-043
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
1.784 12345193.52 10237.50 5623592.91 45.5
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF SH 364 (LA HOMA)
To .25 MI W OF MOOREFIELD RD
CSJ 0862-01-037
Proj ID STP 2013(040)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.574 2333144.96 0.00 210725.00 9.0
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF MOOREFIELD RD
To FM 681
CSJ 0862-01-047
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
0.338 2162777.75 0.00 423884.34 19.5
Work Order 08-19-13
Work Began 09-04-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 20.85%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29%)
SOIL-TECH, INC.(1.94%)
PAVEMENT MARKINGS INC. (1.01%)
VALLEY INFRASTRUCTURE, INC.( 10.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76%)
Contract # 06133203
Totals 16841116.23 10237.50 6258202.25 37.1

CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI N OF MILE 16 N
CSJ 0698-03-084
Proj ID STP 2012(699)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.249 2681776.78 114479.54 1570734.81 61.0
CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI. N. OF MIE 16 N
CSJ 0698-03-086
Proj ID RW 0698-3-86
Work Type ROW ACQUISITION
 
0.249 467213.71 7800.00 574995.41 99.9
Work Order 01-03-13
Work Began 04-09-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 142
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-084
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.44%)
VALLEY STRIPING CORP.(1.43%)
Contract # 09123235
Totals 3148990.49 122279.54 2145730.22 70.2

CountyHIDALGO
Highway FM 493
From CHAMPION ST.
To US 281
CSJ 0863-01-047
Proj ID HP 2014(907)
Work Type RECONSTRUCT & ADD SHOULDERS
 
5.681 11333645.32 0.00 118686.89 1.0
CountyHIDALGO
Highway FM 493
From BUSINESS 83
To CHAMPION AVE
CSJ 0863-01-053
Proj ID HP 2014(907)
Work Type OVERLAY
 
0.768 579679.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 09-25-14
Contract Working Days 480
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143208
Totals 11913324.88 0.00 118686.89 0.9

CountyHIDALGO
Highway CS
From MILE 2 WEST, FROM MILE 12 NORTH
To .44 MI NORTH OF US 83
CSJ 0921-02-170
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
4.750 4729717.44 59743.50 1882904.28 39.8
CountyHIDALGO
Highway CS
From ON MILE 2 NORTH,.44 MI N OF US 83
To US 83
CSJ 0921-02-307
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
0.440 744320.06 0.00 155950.00 20.9
Work Order 06-26-13
Work Began 12-16-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 480
Addl Days Granted 6
Working Days Charged 168
Percent Time Used 34
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-170
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 12.90%)
SOIL-TECH, INC.(6.29%)
PAVEMENT MARKINGS INC. (0.92%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.48%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.68%)
Contract # 04133203
Totals 5474037.50 59743.50 2038854.28 37.2

CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-171
Proj ID HP 2008(134)
Work Type CONSTR 2 LN RDWY W / 4 LA TRANS
 
3.000 4309680.38 15834.14 3839830.90 94.1
CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-288
Proj ID HP 1102(318)
Work Type ROW ACQ.; UTL. ADJ.
 
3.000 849420.66 13840.16 779870.87 91.8
Work Order 08-25-11
Work Began 10-11-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 518
Percent Time Used 161
Contractor(s)
CONTINENTAL CASUALTY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-171
HIGHWAY TECHNOLOGIES, INC. (0.69%)
SOIL-TECH, INC.(1.28%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.74%)
PAVEMENT MARKINGS INC. (0.98%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.99%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.56%)
VALLEY INFRASTRUCTURE, INC.( 33.21%)
Contract # 07113251
Totals 5159101.04 29674.30 4619701.77 93.7

CountyHIDALGO
Highway VA
From US CUSTOMS PORT OF ENTRY EXIT
To US 281
CSJ 0921-02-173
Proj ID BOR 2002(632)
Work Type CONSTRUCT BSIF
 
1.350 20116428.45 21446.81 17500982.50 87.1
Work Order 08-25-11
Work Began 10-18-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 380
Addl Days Granted 115
Working Days Charged 517
Percent Time Used 104
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173
BULLARD CONSTRUCTION, INC. ( 19.38%)
HIGHWAY TECHNOLOGIES, INC. (1.61%)
HURRICANE FENCE COMPANY(0.96%)
METTLER TOTLEDO(5.03%)
NORTH TEXAS REBAR, LLC (0.54%)
ROVAN, LLC (3.33%)
SOIL-TECH, INC.(1.21%)
STAR OPERATIONS, INC.( 19.28%)
TSI LABORATORIES SOUTH,INC.(0.04%)
RGV ALLIANCE CONSTRUCTION, LLC (0.54%)
FOREMOST PAVING, INC.(9.34%)
CONTINENTAL REFRIGERATION(1.12%)
M & A PAINTING SERVICE, INC. (0.39%)
L & G CONCRETE CONSTRUCTION, INC.(3.86%)
SOUTHERN STEEL FABRICATORS (4.27%)
CANTU"S PLUMBING (0.88%)
METRO ELECTRIC, INC. (1.81%)
ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC.(0.07%)
INTERTECH FLOORING (0.33%)
WEIGHT AND TEST SOLUTIONS, INC.(0.70%)
RGV ALLIANCE CONSTRUCTION, LLC (0.12%)
MCALLEN PEST CONTROL (0.03%)
THE CABINET SHOP (0.24%)
PRIME CONSTRUCTION (0.10%)
TAYLOR LIGHTNING PROTECTION(0.14%)
TAMU, DBA CONSTRUCTION SPECIALTIES (0.37%)
T & D SOLUTIONS, LTD (0.87%)
Contract # 07113207
Totals 20116428.45 21446.81 17500982.50 87.1

CountyHIDALGO
Highway CS
From CITY OF EDINBURG, EISENHOWER ELEM
To & MEMORIAL MIDDLE SCHOOL
CSJ 0921-02-258
Proj ID STP 1102(186)SRS
Work Type SIDEWALK, CROSSWALK, BIKE RACKS
 
13.043 2667755.20 0.00 2703203.08 99.9
Work Order 11-09-12
Work Began 12-11-12
Work Completed  
Time Computed 11-25-12
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 230
Percent Time Used 95
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-258
STAR OPERATIONS, INC.( 17.31%)
VALLEY STRIPING CORP.(3.07%)
ACE DRILLING, INC. (0.43%)
Contract # 09123221
Totals 2667755.20 0.00 2703203.08 99.9

CountyHIDALGO
Highway CS
From CITY OF EDINBURG,
To CANO-GONZALEZ ELEMENTARY
CSJ 0921-02-266
Proj ID STP 1102(187)SRS
Work Type SIDEWALKS, CROSSWALKS, BIKE RACKS
 
1.600 4251199.44 97189.67 3728579.36 87.7
Work Order 08-02-13
Work Began 12-02-13
Work Completed  
Time Computed 08-18-13
Contract Working Days 465
Addl Days Granted 0
Working Days Charged 327
Percent Time Used 70
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-266
VALLEY STRIPING CORP.(2.39%)
STAR OPERATIONS, INC.( 11.14%)
Contract # 05133221
Totals 4251199.44 97189.67 3728579.36 87.7

CountyHIDALGO
Highway VA
From CITY OF HIDALGO, EAST
To TO SANTA ANNA NWR TO MCALLEN
CSJ 0921-02-282
Proj ID STP 2011(242)TE
Work Type PEDESTRIAN & BICYCLE ACCESS
 
9.788 1277719.46 0.00 1355839.62 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-13
Work Began 08-28-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 180
Percent Time Used 100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-282
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 17.50%)
EXTERIOR DESIGNS (2.24%)
PAVEMENT MARKINGS INC. (2.83%)
D S TEXAS ICON CONSTRUCTION, LLC (9.05%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.87%)
DELTA SPECIALTIES SIGNS & SUPPLIES (2.75%)
J & P TRUCKING AND HAULING (1.82%)
2GS, LLC (1.35%)
CABCOS CONTRACTORS LLC (0.58%)
Contract # 05133019
Totals 1277719.46 0.00 1355839.62 99.9

CountyHIDALGO
Highway VA
From VARIOUS LOCATIONS IN HIDALGO COUNTY
To .
CSJ 0921-02-313
Proj ID STP 2014(446)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1657902.70 111770.44 1185165.79 71.4
Work Order 04-25-14
Work Began 05-27-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 242
Addl Days Granted 0
Working Days Charged 209
Percent Time Used 86
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-313
TEXAS CONCRETE AND DEMOLITION, INC.( 26.30%)
CERTIFIED PLACERS LLC(0.72%)
SOIL-TECH, INC.(1.22%)
VALLEY STRIPING CORP.(5.09%)
Contract # 02143016
Totals 1657902.70 111770.44 1185165.79 71.4

page 1 | page 2 | page 3