Monthly State Let Construction Report For Pharr District As Of Dec 10, 2014 Page 4 Of 4

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCAMERON
Highway FM 2480
From FM 3069
To FM 510
CSJ 2366-01-009
Proj ID STP 2012(644)
Work Type REHABILITATE AND RESTORE PAVEMENT
 
4.280 2868112.75 221944.15 613940.91 21.4
Work Order 05-13-14
Work Began 00-00-00
Work Completed  
Time Computed 05-29-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 17
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2366-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143243
Totals 2868112.75 221944.15 613940.91 21.4

CountyJIM HOGG
Highway FM 3073
From FM 649
To SH 16
CSJ 3099-01-008
Proj ID STP 2013(798)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
16.247 5647170.00 221435.89 5211531.28 92.7
Work Order 09-05-13
Work Began 01-29-14
Work Completed  
Time Computed 09-21-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 114
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3099-01-008
ABC EROSION CONTROL, INC.(3.28%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.59%)
FLASHER EQUIPMENT COMPANY(0.34%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.70%)
FOREMOST PAVING, INC.( 36.38%)
Contract # 06133016
Totals 5647170.00 221435.89 5211531.28 92.7