Monthly State Let Construction Report For Pharr District As Of Apr 11, 2016 Page 4 Of 4

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHIDALGO
Highway SH 364
From SH 495 N
To FM 1924
CSJ 2966-01-009
Proj ID C 2966-1-9
Work Type GRADING, STRUCTURES & SURFACING
 
2.000 6848709.56 0.00 171591.76 2.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 02-16-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 2
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2966-01-009
GULF COAST CONTRACTORS, INC. (0.92%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.25%)
MUSTANG COLT SERVICES, INC.(4.14%)
Contract # 11153214
Totals 6848709.56 0.00 171591.76 2.5

CountyJIM HOGG
Highway FM 3073
From FM 649
To SH 16
CSJ 3099-01-008
Proj ID STP 2013(798)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
16.247 5647170.00 89550.00 5425933.64 97.0
Work Order 09-05-13
Work Began 01-29-14
Work Completed  
Time Computed 09-21-13
Contract Working Days 177
Addl Days Granted 46
Working Days Charged 274
Percent Time Used 122
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3099-01-008
ABC EROSION CONTROL, INC.(3.28%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.59%)
FLASHER EQUIPMENT COMPANY(0.34%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.70%)
FOREMOST PAVING, INC.( 36.38%)
Contract # 06133016
Totals 5647170.00 89550.00 5425933.64 97.0

page 1 | page 2 | page 3 | page 4