Monthly State Let Construction Report For Paris District As Of Jan 11, 2013 Page 4 Of 4
Last Update: Monday, January 14, 2013
|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | GRAYSON |
| Highway |
FM 131 |
| From |
FM 120 |
| To |
FM 691 |
| CSJ |
2454-01-009 |
| Proj ID |
STP 2012(576) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
3.351 |
1658502.26 |
291889.13 |
1249853.42 |
75.6 |
| Work Order |
07-12-12 |
| Work Began |
08-03-12 |
| Work Completed |
|
| Time Computed |
10-10-12 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
96 |
| Percent Time Used |
106 |
| Contractor(s) |
| BILLY CUMMINGS CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2454-01-009 BAHENA CONSTRUCTION CO.,INC. (2.41%) CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.16%) UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(2.91%) MOHL AND SCOTT, INC. ( 18.48%) SAMMY G. SMALLWOOD (2.54%)
|
| Contract # |
05123022 |
|
Totals |
1658502.26 |
291889.13 |
1249853.42 |
75.6 |
|
| County | GRAYSON |
| Highway |
FM 902 |
| From |
COOKE COUNTY LINE |
| To |
US 377 |
| CSJ |
2459-02-010 |
| Proj ID |
STP 1102(289)HRR |
| Work Type |
HAZARD ELIMINATION & SAFETY |
| |
|
1.825 |
883742.00 |
0.00 |
259227.16 |
29.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-31-12 |
| Work Began |
05-07-12 |
| Work Completed |
|
| Time Computed |
04-30-12 |
| Contract Working Days |
74 |
| Addl Days Granted |
0 |
| Working Days Charged |
75 |
| Percent Time Used |
101 |
| Contractor(s) |
| KEN-DO CONTRACTING, LP |
SUBCONTRACTOR(S) FOR CCSJ: 2459-02-010 DALLAS LITE AND BARRICADE INC. (0.44%) DUSTIN ALLEN, INC. (4.08%) MCMAHON CONTRACTING, L.P.( 12.91%) IOWA BRIDGE & CULVERT, LC(1.85%) STRIPING TECHNOLOGY, L.P.(4.11%) TEX OP CONSTRUCTION, LP(3.33%) W. W. FOUNDATION DRILLING, LTD.(2.59%)
|
| Contract # |
12113011 |
|
Totals |
883742.00 |
0.00 |
259227.16 |
29.4 |
|
| County | GRAYSON |
| Highway |
FM 406 |
| From |
SH 289 (FM 120) |
| To |
FM 84 |
| CSJ |
2640-02-007 |
| Proj ID |
STP 2012(071) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
3.833 |
2569783.12 |
0.00 |
2445807.42 |
95.1 |
| Work Order |
11-30-11 |
| Work Began |
03-26-12 |
| Work Completed |
|
| Time Computed |
01-30-12 |
| Contract Working Days |
173 |
| Addl Days Granted |
0 |
| Working Days Charged |
158 |
| Percent Time Used |
91 |
| Contractor(s) |
| BILLY CUMMINGS CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2640-02-007 UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.64%) J. M. CONSTRUCTION (6.51%) LYON BARRICADE AND CONSTRUCTION CO.(0.58%) MOHL AND SCOTT, INC. ( 20.61%) CF SOUTHWEST ENVIRONMENT SERVICES LLC(3.03%) SAMMY G. SMALLWOOD (1.44%)
|
| Contract # |
10113210 |
|
Totals |
2569783.12 |
0.00 |
2445807.42 |
95.1 |
|