Monthly State Let Construction Report For Paris District As Of Sep 15, 2016 Page 4 Of 4

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOPKINS
Highway FM 2560
From SH 11
To FM 1567
CSJ 2875-01-008
Proj ID STP 1402(105)
Work Type REHABILITATION OF EXISTING ROADWAY
 
5.340 2396113.01 10500.00 2414301.47 99.9
Work Order 10-14-14
Work Began 03-03-15
Work Completed  
Time Computed 12-15-14
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 100
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 2875-01-008
ALTUS TRAFFIC MANAGEMENT LLC (0.55%)
CATOCON, INC.(2.35%)
MOORE CONSTRUCTION, INC. (2.92%)
BAHENA CONSTRUCTION CO.,INC. ( 20.99%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.41%)
SAMMY GIST ENTERPRISES, INC. (1.64%)
TEXANA LAND & ASPHALT, INC.(0.59%)
Contract # 08143223
Totals 2396113.01 10500.00 2414301.47 99.9

CountyRED RIVER
Highway FM 3390
From AT BURKHAND BRANCH
To .
CSJ 3371-01-009
Proj ID BR 1602(358)
Work Type BRIDGE REPLACEMENT
 
0.079 298222.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3371-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163235
Totals 298222.05 0.00 0.00 0.0