| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | GRAYSON |
| Highway |
CR |
| From |
AT RANGE CREEK |
| To |
CR 251-1 |
| CSJ |
0901-19-154 |
| Proj ID |
BR 2011(757) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.132 |
405434.60 |
2812.00 |
396591.60 |
97.8 |
| Work Order |
03-12-12 |
| Work Began |
04-24-12 |
| Work Completed |
|
| Time Computed |
03-28-12 |
| Contract Working Days |
105 |
| Addl Days Granted |
0 |
| Working Days Charged |
77 |
| Percent Time Used |
73 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-154 CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.13%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.54%) SAMMY G. SMALLWOOD (8.86%)
|
| Contract # |
02123011 |
|
Totals |
405434.60 |
2812.00 |
396591.60 |
97.8 |
|
| County | GRAYSON |
| Highway |
PW |
| From |
WITHIN EISENHOWER STATE PARK |
| To |
. |
| CSJ |
0901-19-172 |
| Proj ID |
C 901-19-172 |
| Work Type |
MISCELLANEOUS CONSTRUCTION |
| |
|
0.100 |
1172197.09 |
0.00 |
1278262.18 |
99.9 |
| Work Order |
06-21-12 |
| Work Began |
07-10-12 |
| Work Completed |
|
| Time Computed |
07-07-12 |
| Contract Working Days |
105 |
| Addl Days Granted |
0 |
| Working Days Charged |
91 |
| Percent Time Used |
86 |
| Contractor(s) |
| SAMMY GIST ENTERPRISES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-172 UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.29%) NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (1.22%) J. M. CONSTRUCTION (5.18%) J & L PAVING (4.29%) P.R. PARKER COMPANY, INC.( 24.30%)
|
| Contract # |
05123024 |
|
Totals |
1172197.09 |
0.00 |
1278262.18 |
99.9 |
|
| County | GRAYSON |
| Highway |
CR |
| From |
AT DESERT CREEK |
| To |
CR 332-1 |
| CSJ |
0901-19-173 |
| Proj ID |
BR 1102(563) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.200 |
658770.60 |
98893.30 |
550402.25 |
83.5 |
| Work Order |
01-04-13 |
| Work Began |
01-22-13 |
| Work Completed |
|
| Time Computed |
01-20-13 |
| Contract Working Days |
193 |
| Addl Days Granted |
0 |
| Working Days Charged |
60 |
| Percent Time Used |
31 |
| Contractor(s) |
| EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-173 CF SOUTHWEST ENVIRONMENT SERVICES LLC(3.01%) FORTSON CONTRACTING, INC.(3.06%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.02%) PEACHTREE CONSTRUCTION, LTD. (2.18%) TOTAL HIGHWAY MAINTENANCE, LLC (0.81%) NORTH TEXAS REBAR, LLC (0.26%)
|
| Contract # |
12123204 |
|
Totals |
658770.60 |
98893.30 |
550402.25 |
83.5 |
|
| County | HUNT |
| Highway |
CR |
| From |
CR 300-1 |
| To |
AT TURKEY CREEK |
| CSJ |
0901-22-083 |
| Proj ID |
BR 1102(276) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.257 |
611115.50 |
0.00 |
606836.00 |
99.2 |
| Work Order |
08-20-12 |
| Work Began |
10-08-12 |
| Work Completed |
|
| Time Computed |
09-05-12 |
| Contract Working Days |
77 |
| Addl Days Granted |
0 |
| Working Days Charged |
69 |
| Percent Time Used |
89 |
| Contractor(s) |
| EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-083 M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.58%) FORTSON CONTRACTING, INC.(6.59%) SOUTHWEST ENVIRONMENT SERVICES LLC (1.72%) NORTH TEXAS REBAR, LLC (0.35%)
|
| Contract # |
06123211 |
|
Totals |
611115.50 |
0.00 |
606836.00 |
99.2 |
|
| County | HUNT |
| Highway |
CR |
| From |
CR 504-1 |
| To |
AT MIDDLE FORK OF TURKEY CREEK |
| CSJ |
0901-22-085 |
| Proj ID |
BR 1102(274) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.179 |
458755.20 |
104253.83 |
323203.00 |
70.4 |
| Work Order |
01-18-13 |
| Work Began |
03-05-13 |
| Work Completed |
|
| Time Computed |
03-04-13 |
| Contract Working Days |
143 |
| Addl Days Granted |
0 |
| Working Days Charged |
34 |
| Percent Time Used |
23 |
| Contractor(s) |
| EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-085 PEACHTREE CONSTRUCTION, LTD. (1.85%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.81%) SOUTHWEST ENVIRONMENT SERVICES LLC (2.98%) FORTSON CONTRACTING, INC.(5.36%) NORTH TEXAS REBAR, LLC (0.01%)
|
| Contract # |
12123214 |
|
Totals |
458755.20 |
104253.83 |
323203.00 |
70.4 |
|
| County | HUNT |
| Highway |
CR |
| From |
CR 507-2 |
| To |
AT WEST FORK TURKEY CREEK |
| CSJ |
0901-22-087 |
| Proj ID |
BR 2012(619) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.149 |
348298.25 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-19-13 |
| Work Began |
05-01-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
65 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-087 M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.14%) SAMMY G. SMALLWOOD (4.65%) SOUTHWEST ENVIRONMENT SERVICES LLC (2.78%) NORTH TEXAS REBAR, LLC (3.29%)
|
| Contract # |
01133014 |
|
Totals |
348298.25 |
0.00 |
0.00 |
0.0 |
|
| County | HUNT |
| Highway |
VA |
| From |
AT IH 30/SH 34 INTERCHANGE |
| To |
. |
| CSJ |
0901-22-102 |
| Proj ID |
STP 1102(456) |
| Work Type |
LANDSCAPE AND SCENIC ENHANCEMENT |
| |
|
0.100 |
104820.00 |
6495.12 |
181864.21 |
99.9 |
| Work Order |
09-13-11 |
| Work Began |
12-14-11 |
| Work Completed |
|
| Time Computed |
09-29-11 |
| Contract Working Days |
64 |
| Addl Days Granted |
45 |
| Working Days Charged |
69 |
| Percent Time Used |
63 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-102 LONE STAR TRAFFIC SERVICE, INC.(1.71%) DOWN UNDER CONSTRUCTION(1.71%)
|
| Contract # |
08113072 |
|
Totals |
104820.00 |
6495.12 |
181864.21 |
99.9 |
|
| County | RED RIVER |
| Highway |
CR |
| From |
ON CR 3230 & CR 3240 FROM FM 1158 |
| To |
FM 1159 |
| CSJ |
0901-27-044 |
| Proj ID |
HP 2012(770) |
| Work Type |
PAVING, BASE WORK, OVERLAY, ETC. |
| |
|
7.247 |
0.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
58 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SAMMY GIST ENTERPRISES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-27-044 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133006 |
|
Totals |
0.00 |
0.00 |
0.00 |
0.0 |
|
| County | HOPKINS |
| Highway |
CR |
| From |
CR 185-1 |
| To |
AT STOUTS CREEK |
| CSJ |
0901-28-051 |
| Proj ID |
BR 1102(533) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.328 |
746315.00 |
35666.25 |
461071.15 |
61.7 |
| Work Order |
10-12-12 |
| Work Began |
11-16-12 |
| Work Completed |
|
| Time Computed |
10-28-12 |
| Contract Working Days |
190 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
43 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-28-051 HIGHWAY TECHNOLOGIES, INC. (0.56%) DUSTIN ALLEN, INC. (5.88%) SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
|
| Contract # |
09123025 |
|
Totals |
746315.00 |
35666.25 |
461071.15 |
61.7 |
|
| County | DELTA |
| Highway |
CR |
| From |
@ BRANCH OF JOHNS CREEK |
| To |
. |
| CSJ |
0901-31-113 |
| Proj ID |
BR 99(600) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.131 |
296611.43 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-04-13 |
| Work Began |
05-02-13 |
| Work Completed |
|
| Time Computed |
06-03-13 |
| Contract Working Days |
65 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| J.M. YANEZ CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 0901-31-113 HIGHWAY TECHNOLOGIES, INC. (0.89%) SOUTHWEST ENVIRONMENT SERVICES LLC (2.97%) SAMMY G. SMALLWOOD (5.31%) W. W. FOUNDATION DRILLING, LTD.( 10.36%) NORTH TEXAS REBAR, LLC (0.44%) HIGHWAY 19 CONSTRUCTION, LLC (5.87%)
|
| Contract # |
01133009 |
|
Totals |
296611.43 |
0.00 |
0.00 |
0.0 |
|
| County | FANNIN |
| Highway |
CR |
| From |
CR 538-1 |
| To |
AT ROCK CREEK |
| CSJ |
0901-32-051 |
| Proj ID |
BR 2012(672) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.131 |
315225.20 |
88139.02 |
257722.81 |
81.7 |
| Work Order |
01-18-13 |
| Work Began |
02-25-13 |
| Work Completed |
|
| Time Computed |
02-25-13 |
| Contract Working Days |
65 |
| Addl Days Granted |
0 |
| Working Days Charged |
37 |
| Percent Time Used |
56 |
| Contractor(s) |
| EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0901-32-051 CF SOUTHWEST ENVIRONMENT SERVICES LLC(6.04%) DUSTIN ALLEN, INC. (5.00%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.44%)
|
| Contract # |
12123035 |
|
Totals |
315225.20 |
88139.02 |
257722.81 |
81.7 |
|
| County | FANNIN |
| Highway |
CR |
| From |
CR 648-1 |
| To |
AT SOUTH SULPHUR RIVER |
| CSJ |
0901-32-061 |
| Proj ID |
BR 1102(551) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.210 |
598067.62 |
48068.00 |
48068.00 |
8.0 |
| Work Order |
11-09-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
03-11-13 |
| Contract Working Days |
153 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| JW PAYNE CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0901-32-061 CF SOUTHWEST ENVIRONMENT SERVICES LLC(4.48%) DUSTIN ALLEN, INC. (6.12%) FOUNDATION DRILLERS, INC.(5.96%) UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.84%) SCOTT DERR PAINTING CO, LLC(0.46%)
|
| Contract # |
10123015 |
|
Totals |
598067.62 |
48068.00 |
48068.00 |
8.0 |
|
| County | HUNT |
| Highway |
SH 276 |
| From |
0.35 MILES EAST FM 36 |
| To |
SH 34 |
| CSJ |
1017-03-030 |
| Proj ID |
STP 2013(681) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
2.091 |
987632.03 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
59 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1017-03-030 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133222 |
|
Totals |
987632.03 |
0.00 |
0.00 |
0.0 |
|
| County | GRAYSON |
| Highway |
FM 922 |
| From |
US 377 |
| To |
COOKE COUNTY LINE |
| CSJ |
1855-02-007 |
| Proj ID |
STP 2012(070) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
1.754 |
746250.52 |
0.00 |
705307.15 |
94.8 |
| Work Order |
11-16-11 |
| Work Began |
01-30-12 |
| Work Completed |
|
| Time Computed |
01-15-12 |
| Contract Working Days |
141 |
| Addl Days Granted |
0 |
| Working Days Charged |
146 |
| Percent Time Used |
103 |
| Contractor(s) |
| NE-TEX CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1855-02-007 MOORE CONSTRUCTION, INC. (4.06%) BRYDL CONTRACTING, INC.(0.92%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (1.47%) TOTAL HIGHWAY MAINTENANCE, LLC (5.49%) J. M. CONSTRUCTION (4.04%)
|
| Contract # |
10113009 |
|
Totals |
746250.52 |
0.00 |
705307.15 |
94.8 |
|
| County | FANNIN |
| Highway |
SH 11 |
| From |
SH 121 |
| To |
SH 78 |
| CSJ |
2139-03-019 |
| Proj ID |
STP 2013(395)HES |
| Work Type |
HAZARD ELIMINATION & SAFETY |
| |
|
6.890 |
4938297.25 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-06-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
311 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BILLY CUMMINGS CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2139-03-019 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133211 |
|
Totals |
4938297.25 |
0.00 |
0.00 |
0.0 |
|
| County | HUNT |
| Highway |
SH 11 |
| From |
SH 34 |
| To |
SH 224 |
| CSJ |
2139-04-020 |
| Proj ID |
C 2139-4-20 |
| Work Type |
REHABILITATION OF EXISTING ROADWAY |
| |
|
12.996 |
6435254.20 |
977.78 |
6721256.77 |
99.9 |
| Work Order |
04-18-11 |
| Work Began |
07-18-11 |
| Work Completed |
|
| Time Computed |
10-17-11 |
| Contract Working Days |
336 |
| Addl Days Granted |
15 |
| Working Days Charged |
338 |
| Percent Time Used |
96 |
| Contractor(s) |
| D. L. LENNON INCORPORATED - CONTRACTOR |
SUBCONTRACTOR(S) FOR CCSJ: 2139-04-020 MOORE CONSTRUCTION, INC. (1.91%) TOTAL HIGHWAY MAINTENANCE, LLC (0.56%) LYON BARRICADE AND CONSTRUCTION CO.(0.49%) JONA CONTRACTING, INC. (1.75%) BALLOU PAVEMENT SOLUTIONS INC. (2.09%) J. M. CONSTRUCTION (7.49%) LONE STAR BARRIER SERVICES, LLC(1.75%)
|
| Contract # |
03113203 |
|
Totals |
6435254.20 |
977.78 |
6721256.77 |
99.9 |
|
| County | GRAYSON |
| Highway |
FM 131 |
| From |
FM 120 |
| To |
FM 691 |
| CSJ |
2454-01-009 |
| Proj ID |
STP 2012(576) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
3.351 |
1658502.26 |
52857.70 |
1460135.19 |
89.7 |
| Work Order |
07-12-12 |
| Work Began |
08-03-12 |
| Work Completed |
|
| Time Computed |
10-10-12 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
126 |
| Percent Time Used |
140 |
| Contractor(s) |
| BILLY CUMMINGS CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2454-01-009 BAHENA CONSTRUCTION CO.,INC. (2.41%) CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.16%) UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(2.91%) MOHL AND SCOTT, INC. ( 18.48%) SAMMY G. SMALLWOOD (2.54%)
|
| Contract # |
05123022 |
|
Totals |
1658502.26 |
52857.70 |
1460135.19 |
89.7 |
|
| County | GRAYSON |
| Highway |
FM 902 |
| From |
COOKE COUNTY LINE |
| To |
US 377 |
| CSJ |
2459-02-010 |
| Proj ID |
STP 1102(289)HRR |
| Work Type |
HAZARD ELIMINATION & SAFETY |
| |
|
1.825 |
883742.00 |
0.00 |
259227.16 |
29.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-31-12 |
| Work Began |
05-07-12 |
| Work Completed |
|
| Time Computed |
04-30-12 |
| Contract Working Days |
74 |
| Addl Days Granted |
0 |
| Working Days Charged |
75 |
| Percent Time Used |
101 |
| Contractor(s) |
| KEN-DO CONTRACTING, LP |
SUBCONTRACTOR(S) FOR CCSJ: 2459-02-010 DALLAS LITE AND BARRICADE INC. (0.44%) DUSTIN ALLEN, INC. (4.08%) MCMAHON CONTRACTING, L.P.( 12.91%) IOWA BRIDGE & CULVERT, LC(1.85%) STRIPING TECHNOLOGY, L.P.(4.11%) TEX OP CONSTRUCTION, LP(3.33%) W. W. FOUNDATION DRILLING, LTD.(2.59%)
|
| Contract # |
12113011 |
|
Totals |
883742.00 |
0.00 |
259227.16 |
29.4 |
|
| County | GRAYSON |
| Highway |
FM 406 |
| From |
SH 289 (FM 120) |
| To |
FM 84 |
| CSJ |
2640-02-007 |
| Proj ID |
STP 2012(071) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
3.833 |
2569783.12 |
21713.03 |
2469144.21 |
96.0 |
| Work Order |
11-30-11 |
| Work Began |
03-26-12 |
| Work Completed |
|
| Time Computed |
01-30-12 |
| Contract Working Days |
173 |
| Addl Days Granted |
0 |
| Working Days Charged |
158 |
| Percent Time Used |
91 |
| Contractor(s) |
| BILLY CUMMINGS CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2640-02-007 UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.64%) J. M. CONSTRUCTION (6.51%) LYON BARRICADE AND CONSTRUCTION CO.(0.58%) MOHL AND SCOTT, INC. ( 20.61%) CF SOUTHWEST ENVIRONMENT SERVICES LLC(3.03%) SAMMY G. SMALLWOOD (1.44%)
|
| Contract # |
10113210 |
|
Totals |
2569783.12 |
21713.03 |
2469144.21 |
96.0 |
|