Monthly State Let Construction Report For Paris District As Of Jul 13, 2015 Page 3 Of 3

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLAMAR
Highway FM 195
From 5.215 MI N OF US 82
To 2.0 MI S OF FM 906
CSJ 0730-02-013
Proj ID STP 2013(783)
Work Type REHABILITATION OF EXISTING ROAD
 
4.962 1632328.37 0.00 1500955.74 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 08-15-13
Work Completed 07-24-14
Time Computed 08-16-13
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 77
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0730-02-013
STRIPING TECHNOLOGY, L.P.(2.60%)
R. K. HALL CONSTRUCTION, LTD.( 46.27%)
LYON BARRICADE AND CONSTRUCTION CO.(0.57%)
DUSTROL, INC.(2.61%)
MOORE CONSTRUCTION, INC. (0.76%)
RK HALL, LLC ( 46.27%)
Contract # 06133018
Totals 1632328.37 0.00 1500955.74 100.0

CountyDELTA
Highway FM 1533
From FM 1530
To FM 128
CSJ 0749-04-011
Proj ID STP 2015(537)
Work Type REHABILITATION OF EXISTING ROAD
 
3.686 1574292.03 194956.21 775617.57 49.2
Work Order 02-20-15
Work Began 03-10-15
Work Completed  
Time Computed 03-08-15
Contract Working Days 99
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 55
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0749-04-011
BAHENA CONSTRUCTION CO.,INC. ( 11.46%)
SAMMY G. SMALLWOOD (0.86%)
CATACON, INC.(1.14%)
STRIPING TECHNOLOGY, L.P.(1.94%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MOORE CONSTRUCTION, INC. (2.98%)
Contract # 01153010
Totals 1574292.03 194956.21 775617.57 49.2

CountyHOPKINS
Highway FM 69
From 1.553 MI S OF FM 1537
To 3.830 MI N OF FM 1537
CSJ 0766-01-027
Proj ID STP 2014(203)
Work Type REHABILITATION OF EXISTING ROAD
 
5.383 1863527.19 0.00 1429051.96 76.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 04-09-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 186
Addl Days Granted 14
Working Days Charged 194
Percent Time Used 97
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0766-01-027
SAMMY G. SMALLWOOD (1.49%)
DUSTIN ALLEN, INC. (0.72%)
CATACON, INC.(5.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MOORE CONSTRUCTION, INC. (3.75%)
SCOTT PAVING, INC. ( 15.94%)
BAHENA CONSTRUCTION CO.,INC. ( 11.29%)
LYON BARRICADE AND CONSTRUCTION CO.(0.95%)
TEXANA LAND & ASPHALT, INC.(0.64%)
Contract # 11133210
Totals 1863527.19 0.00 1429051.96 76.6

CountyHUNT
Highway FM 513
From FM 499
To IH 30 SOUTH FRONTAGE ROAD
CSJ 0768-02-020
Proj ID STP 2015(529)
Work Type REHABILITATION OF EXISTING ROAD
 
1.836 1604270.96 283173.29 283173.29 17.6
Work Order 02-13-15
Work Began 06-02-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 118
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 14
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0768-02-020
TOTAL HIGHWAY MAINTENANCE, LLC (0.37%)
BAHENA CONSTRUCTION CO.,INC. ( 13.74%)
CATOCON, INC.(1.27%)
TEX OP CONSTRUCTION, LP(0.65%)
HIGHWAY 19 CONSTRUCTION, LLC ( 10.50%)
STRIPING TECHNOLOGY, L.P.(1.40%)
MOORE CONSTRUCTION, INC. (3.01%)
SAMMY SMALLWOOD COMPANY(4.73%)
Contract # 01153214
Totals 1604270.96 283173.29 283173.29 17.6

CountyRED RIVER
Highway FM 410
From 3.2 MILES N OF US 82
To FM 195
CSJ 0772-01-027
Proj ID STP 2014(033)
Work Type REHABILITATION OF EXISTING ROAD
 
7.420 2516692.96 0.00 2615455.73 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-13
Work Began 01-02-14
Work Completed 02-05-15
Time Computed 00-00-00
Contract Working Days 330
Addl Days Granted 0
Working Days Charged 171
Percent Time Used 51
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0772-01-027
LYON BARRICADE AND CONSTRUCTION CO.(1.04%)
CATACON, INC.(1.47%)
HIGHWAY 19 CONSTRUCTION, LLC ( 15.39%)
SAMMY G. SMALLWOOD (4.14%)
STRIPING TECHNOLOGY, L.P.(3.04%)
MOORE CONSTRUCTION, INC. (2.77%)
Contract # 09133031
Totals 2516692.96 0.00 2615455.73 100.0

CountyLAMAR
Highway VA
From VARIOUS LOCATIONS IN HUNT AND
To HOPKINS COUNTIES
CSJ 0901-00-052
Proj ID STP 2014(632)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1777289.00 153010.00 1418363.02 79.8
Work Order 06-20-14
Work Began 07-07-14
Work Completed  
Time Computed 07-06-14
Contract Working Days 194
Addl Days Granted 5
Working Days Charged 179
Percent Time Used 89
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-00-052
TOTAL HIGHWAY MAINTENANCE, LLC (0.60%)
ACTION SERVICES(0.44%)
Contract # 05143222
Totals 1777289.00 153010.00 1418363.02 79.8

CountyLAMAR
Highway VA
From VARIOUS LOCATIONS IN PARIS DISTRICT
To .
CSJ 0901-00-053
Proj ID STP 2014(702)
Work Type MISCELLANEOUS CONSTRUCTION
 
0.001 217690.25 0.00 185236.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 08-28-14
Work Completed 02-03-15
Time Computed 08-19-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 94
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-00-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143037
Totals 217690.25 0.00 185236.75 100.0

CountyHUNT
Highway CR
From INDIAN TRAIL RD IN HAWK COVE
To @ HAWK COVE TRIBUTARY
CSJ 0901-22-097
Proj ID BR 2012(621)
Work Type BRIDGE REPLACEMENT
 
0.090 549983.20 12285.40 382783.19 69.5
Work Order 10-28-14
Work Began 12-03-14
Work Completed  
Time Computed 12-29-14
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 17
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-097
FORTSON CONTRACTING, INC.(4.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.79%)
Contract # 08143033
Totals 549983.20 12285.40 382783.19 69.5

CountyRED RIVER
Highway CR
From ON CR 3230 & CR 3240 FROM FM 1158
To FM 1159
CSJ 0901-27-044
Proj ID HP 2012(770)
Work Type PAVING, BASE WORK, OVERLAY, ETC.
 
7.247 0.00 41550.37 776106.01 0.0
Work Order 08-06-13
Work Began 08-20-13
Work Completed  
Time Computed 08-22-13
Contract Working Days 58
Addl Days Granted 20
Working Days Charged 78
Percent Time Used 100
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-27-044
MOORE CONSTRUCTION, INC. (1.47%)
LYON BARRICADE AND CONSTRUCTION CO.(0.59%)
WES SCOTT, INC.( 29.01%)
HIGHWAY 19 CONSTRUCTION, LLC (2.46%)
Contract # 04133006
Totals 0.00 41550.37 776106.01 0.0

CountyHOPKINS
Highway CR
From CR 431-1
To AT BIG CREEK
CSJ 0901-28-053
Proj ID BR 2013(721)
Work Type BRIDGE REPLACEMENT
 
0.188 683133.48 5720.00 675052.74 98.8
Work Order 04-02-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 62
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-28-053
LONE STAR BARRIER SERVICES, LLC(3.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.23%)
MCL CONTRACTING, LLC (0.73%)
Contract # 02143017
Totals 683133.48 5720.00 675052.74 98.8

CountyLAMAR
Highway CR
From AT CANE CREEK
To CR 510-1
CSJ 0901-29-065
Proj ID BR 2014(599)
Work Type BRIDGE REPLACEMENT
 
0.136 656785.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-29-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153047
Totals 656785.40 0.00 0.00 0.0

CountyFANNIN
Highway CR
From CR 237-2
To AT POT CREEK
CSJ 0901-32-043
Proj ID BR 2013(433)
Work Type BRIDGE REPLACEMENT
 
0.020 417187.50 0.00 232935.86 55.8
Work Order 08-27-14
Work Began 10-24-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 45
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-32-043
TOTAL HIGHWAY MAINTENANCE, LLC (1.45%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.82%)
LONE STAR BARRIER SERVICES, LLC(4.06%)
Contract # 07143019
Totals 417187.50 0.00 232935.86 55.8

CountyFANNIN
Highway CR
From CR 239-5
To AT N SULPHUR RIVER TRIBUTARY
CSJ 0901-32-044
Proj ID BR 2013(424)
Work Type BRIDGE REPLACEMENT
 
0.418 1410705.60 82723.00 1170344.17 82.9
Work Order 01-17-14
Work Began 03-18-14
Work Completed  
Time Computed 03-28-14
Contract Working Days 332
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 65
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-32-044
LYON BARRICADE AND CONSTRUCTION CO.(1.03%)
DUSTIN ALLEN, INC. (3.45%)
PRIMATE CONSTRUCTION, INC. (1.45%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.00%)
Contract # 12133210
Totals 1410705.60 82723.00 1170344.17 82.9

CountyHUNT
Highway FM 1568
From FM 3218
To SH 499
CSJ 1497-01-012
Proj ID STP 2013(910)
Work Type REHABILITATION OF EXISTING ROAD
 
4.393 1749177.04 0.00 1726893.17 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-13
Work Began 12-12-13
Work Completed 08-22-14
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 57
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1497-01-012
LYON BARRICADE AND CONSTRUCTION CO.(0.63%)
CATOCON, INC.(1.39%)
MOORE CONSTRUCTION, INC. (2.92%)
STRIPING TECHNOLOGY, L.P.(2.64%)
SAMMY G. SMALLWOOD (2.60%)
Contract # 09133022
Totals 1749177.04 0.00 1726893.17 100.0

CountyLAMAR
Highway SL 286
From 864 FT WEST OF KIAMICHI RAILROAD
To 775 FT SOUTH OF US 271 SOUTH
CSJ 1690-01-112
Proj ID STP 1502(187)
Work Type OVERLAY
 
6.247 1981524.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-11-15
Work Began 00-00-00
Work Completed  
Time Computed 07-12-15
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1690-01-112
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
MOORE CONSTRUCTION, INC. (1.12%)
DIAMOND SURFACE, INC.(0.42%)
STRIPING TECHNOLOGY, L.P.(3.50%)
A. K. GILLIS & SONS, INC.(9.80%)
TEX OP CONSTRUCTION, LP(0.37%)
Contract # 05153035
Totals 1981524.05 0.00 0.00 0.0

CountyHUNT
Highway FM 118
From SS 118
To FM 512
CSJ 1725-01-011
Proj ID STP 2015(620)
Work Type REHABILITATION OF EXISTING ROAD
 
5.410 2470540.21 16859.00 16859.00 0.6
Work Order 03-26-15
Work Began 06-26-15
Work Completed  
Time Computed 06-24-15
Contract Working Days 144
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 3
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1725-01-011
TOTAL HIGHWAY MAINTENANCE, LLC (0.44%)
WITHERS CONSTRUCTION, LLC(1.23%)
MOORE CONSTRUCTION, INC. (3.52%)
SCOTT PAVING, INC. ( 23.52%)
STRIPING TECHNOLOGY, L.P.(2.10%)
SAMMY SMALLWOOD COMPANY(4.31%)
Contract # 02153032
Totals 2470540.21 16859.00 16859.00 0.6

CountyHUNT
Highway FM 2101
From SH 34
To FM 2947
CSJ 2035-01-019
Proj ID STP 2014(934)HES
Work Type HAZARD ELIMINATION & SAFETY
 
6.680 2546840.04 162646.83 1879350.61 74.0
Work Order 09-11-14
Work Began 10-08-14
Work Completed  
Time Computed 09-27-14
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 107
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 2035-01-019
TOTAL HIGHWAY MAINTENANCE, LLC (0.73%)
CATOCON, INC.(3.53%)
MOORE CONSTRUCTION, INC. (1.12%)
BAHENA CONSTRUCTION CO.,INC. ( 13.01%)
HIGHWAY 19 CONSTRUCTION, LLC (8.16%)
LONE STAR BARRIER SERVICES, LLC(1.48%)
DUSTROL, INC.(0.21%)
SAMMY GIST ENTERPRISES, INC. (1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.30%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.19%)
STRIPING TECHNOLOGY, L.P.(1.93%)
ANCHOR CONTRACTING, LLC(0.30%)
J.M. YANEZ CONSTRUCTION(7.92%)
SHINN & GREGORY, INC.(2.30%)
Contract # 07143026
Totals 2546840.04 162646.83 1879350.61 74.0

CountyFANNIN
Highway SH 11
From SH 121
To SH 78
CSJ 2139-03-019
Proj ID STP 2013(395)HES
Work Type HAZARD ELIMINATION & SAFETY
 
6.890 4938297.25 6929.50 4915297.25 99.5
Work Order 05-06-13
Work Began 05-23-13
Work Completed  
Time Computed 07-05-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 299
Percent Time Used 96
Contractor(s)
WESTFIELD INSURANCE GROUP
SUBCONTRACTOR(S) FOR CCSJ: 2139-03-019
HIGHWAY 19 CONSTRUCTION, LLC (3.19%)
LYON BARRICADE AND CONSTRUCTION CO.(0.67%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.14%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
MOORE CONSTRUCTION, INC. (2.08%)
SAMMY G. SMALLWOOD (3.86%)
A. K. GILLIS & SONS, INC.( 63.23%)
STRIPING TECHNOLOGY, L.P.(1.00%)
CATOCON, INC.(0.48%)
TEXANA LAND & ASPHALT, INC.(0.71%)
Contract # 02133211
Totals 4938297.25 6929.50 4915297.25 99.5

CountyGRAYSON
Highway FM 902
From COOKE COUNTY LINE
To US 377
CSJ 2459-02-011
Proj ID STP 2014(935)HES
Work Type HAZARD ELIMINATION & SAFETY
 
1.825 1547314.71 0.00 962924.36 63.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 10-02-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 126
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2459-02-011
TOTAL HIGHWAY MAINTENANCE, LLC (0.69%)
TEX OP CONSTRUCTION, LP(0.84%)
IOWA BRIDGE & CULVERT, LC( 14.14%)
DUSTIN ALLEN, INC. (2.60%)
STRIPE-A-ZONE, INC.(1.18%)
WITHERS CONSTRUCTION, LLC(1.19%)
JM YANEZ CONSTRUCTION(6.12%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.54%)
SYNERGY SIGNS & SERVICES, LLC(1.20%)
Contract # 07143224
Totals 1547314.71 0.00 962924.36 63.0

CountyHOPKINS
Highway FM 2560
From SH 11
To FM 1567
CSJ 2875-01-008
Proj ID STP 1402(105)
Work Type REHABILITATION OF EXISTING ROADWAY
 
5.340 2396113.01 28043.96 198866.96 8.2
Work Order 10-14-14
Work Began 03-03-15
Work Completed  
Time Computed 12-15-14
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 30
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 2875-01-008
ALTUS TRAFFIC MANAGEMENT LLC (0.55%)
CATOCON, INC.(2.35%)
MOORE CONSTRUCTION, INC. (2.40%)
BAHENA CONSTRUCTION CO.,INC. ( 20.99%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.41%)
SAMMY GIST ENTERPRISES, INC. (1.64%)
Contract # 08143223
Totals 2396113.01 28043.96 198866.96 8.2