Monthly State Let Construction Report For Paris District As Of Jul 14, 2017 Page 1 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOPKINS
HighwayIH 30
FromON IH 30, 1 MILE EAST OF CUMBY
To.
CSJ0009-09-081
Proj IDSTP 2000(825)TE
Work TypeMISCELLANEOUS CONSTRUCTION
 
1.36323690539.5110851140.1645.8
Work Order07-01-16
Work Began08-08-16
Work Completed
Time Computed08-01-16
Contract Working Days368
Addl Days Granted0
Working Days Charged199
Percent Time Used54
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-081
EROSION CONTROL MANAGEMENT SERVICES (0.47)
THELIN RECYCLING COMPANY, L.P. (0.54)
DALLAS LITE AND BARRICADE INC. (0.53)
GAY AND SONS MASONRY (3.79)
TOTAL HIGHWAY MAINTENANCE, LLC (0.39)
PREMIER PAVING, LTD. (6.51)
RK HALL, LLC (2.28)
W.O.E. CONSTRUCTION (0.45)
J.R. POPE COMPANY, INC. (5.91)
TEXOP CONSTRUCTION (0.30)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
TEXAS YARD PRO INC. (0.77)
K & A STEEL, LLC (0.46)
CHIENER, LLC (0.76)
RELIANCE PLUMBING GROUP, INC. DBA RELIANCE MECHANICAL CONTR (3.72)
HUMPHREY & ASSOCIATES, INC. (4.69)
PEST FORCE (0.01)
SYNERGY SIGNS & SERVICES, LLC (0.35)
CNC CONSTRUCTION (0.59)
F&P CONSTRUCTION, LLC (2.86)
TBS SPECIALTIES DIRECT, INC. (0.10)
EASTEX GLASS & MIRROR DBA TYLER GLASS & MIRROR (1.55)
SAN ANTONIO TILE, INC. (1.67)
SCHNEIDER ELECTRIC (0.29)
AMERITEX FLAG & FLAGPOLE, LLC (0.05)
BLIND DEPOT (0.00)
T-BAR FENCE, INC. (0.00)
SIGN INTERNATIONAL, INC. (0.08)
HEARTLAND PARK AND RECREATION, LLC (0.36)
BECO METAL WORKS (4.03)
SHEET METAL PROFESSIONALS, LLC (2.64)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.79)
Contract #04163201
Totals23690539.51923125.7910851140.1645.8

CountyHUNT
HighwayIH 30
FromROCKWALL COUNTY LINE
ToFM 1565 NORTH
CSJ0009-13-159
Proj IDBR 1602(330)
Work TypeBRIDGE REPLACEMENT
 
5.77822304844.443227865.8814.4
CountyHUNT
HighwayCR
FromIH 30 EASTBOUND FRONTAGE ROAD
ToFM 2642
CSJ0901-22-115
Proj IDCC 901-22-115
Work TypeREHABILITATION OF EXISTING ROAD
 
1.249859715.87624957.4372.6
Work Order10-26-16
Work Began03-13-17
Work Completed
Time Computed11-25-16
Contract Working Days493
Addl Days Granted0
Working Days Charged46
Percent Time Used9
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-159
TOTAL HIGHWAY MAINTENANCE, LLC (0.28)
BOWMAN ENGINEERING & CONSULTING, INC (0.72)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15)
W.O.E. CONSTRUCTION (0.03)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.15)
TEX OP CONSTRUCTION, LP (0.79)
K & S UTILITY CONTRACTORS, INC. (6.45)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (0.00)
CARRASCO TRUCKING (0.00)
WITHERS CONSTRUCTION, LLC (0.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.40)
HOUSTON SAWING & DRILLING (0.02)
RAMBO CONTRACTING, INC. (2.42)
OSCAR ORDUNO, INC. (1.21)
SOUTHERN CROSS CONTRACTORS, LLC (0.43)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.89)
PANIOLO CONSTRUCTION SERVICES, LLC (2.85)
STRIPING TECHNOLOGY, L.P. (0.77)
NE-TEX CONSTRUCTION, LTD. (1.67)
PENHALL COMPANY (0.01)
JND & SONS BARRIER, LLC (0.65)
Contract #08163005
Totals23164560.31630622.383852823.3116.6

CountyHUNT ETC
HighwayIH 30 ETC
FromSS 302; SFR
ToSH 24
CSJ0009-13-163
Proj IDNH 2017(352)
Work TypeSEAL COAT
 
230.4478807758.173006242.7834.1
Work Order01-17-17
Work Began05-16-17
Work Completed
Time Computed02-16-17
Contract Working Days65
Addl Days Granted0
Working Days Charged18
Percent Time Used27
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-163
STRIPE-A-ZONE, INC. (11.98)
RED SIXTEEN CONSTRUCTION, INC (0.86)
INNOVATIVE ROADWAY SOLUTIONS LLC (1.17)
CDM HOLDINGS, LLC (4.05)
Contract #12163010
Totals8807758.172404126.083006242.7834.1

CountyFRANKLIN ETC
HighwayUS 67 ETC
FromSH 37 S
ToHOPKINS COUNTY LINE
CSJ0010-04-021
Proj IDSTP 1702(367)HESG
Work TypeSAFETY RELATED PROJECT - HSIP
 
71.630382000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-04-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173230
Totals382000.000.000.000.0

CountyGRAYSON
HighwaySH 56 ETC
From564 FT E OF S BINKLEY PK DR
ToTOLBERT AVE
CSJ0045-03-048
Proj IDSTP 2016(996)
Work TypeOVERLAY
 
5.9442250480.471789181.2179.5
Work Order01-03-17
Work Began04-07-17
Work Completed
Time Computed02-02-17
Contract Working Days45
Addl Days Granted0
Working Days Charged51
Percent Time Used113
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-03-048
TOTAL HIGHWAY MAINTENANCE, LLC (0.56)
STRIPING TECHNOLOGY, L.P. (3.21)
TEX OP CONSTRUCTION, LP (14.22)
SYNERGY SIGNS & SERVICES, LLC (5.24)
Contract #04163014
Totals2250480.4761652.081789181.2179.5

CountyGRAYSON
HighwayUS 82
FromFRISCO ROAD (SHERMAN)
ToFM 1417 EAST
CSJ0045-19-050
Proj IDC 45-19-50
Work TypeWIDEN NON-FREEWAY
 
1.61712500127.049965985.8279.7
Work Order11-10-15
Work Began01-20-16
Work Completed
Time Computed01-11-16
Contract Working Days350
Addl Days Granted0
Working Days Charged289
Percent Time Used82
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-050
ALTUS TRAFFIC MANAGEMENT LLC (0.25)
LONE STAR BARRIER SERVICES, LLC (0.77)
WOLFE CONSTRUCTION GROUP, INC. (0.79)
DIAMOND SURFACE, INC. (0.08)
OVERLAND CORPORATION (23.31)
EROSION CONTROL MANAGEMENT SERVICES (0.26)
RPM XCONSTRUCTION, LLC (29.70)
FARR FOUNDATION, INC. (0.22)
STRIPING TECHNOLOGY, L.P. (0.52)
VENUS CONSTRUCTION (5.39)
KMB TRUCKING LLC (0.00)
TEXOP CONSTRUCTION (0.29)
CDM HOLDINGS, LLC (2.25)
SELECT STRIPING LLC (0.41)
Contract #07153207
Totals12500127.04749417.209965985.8279.7

CountyFANNIN
HighwayUS 82
FromAT FM 898
To.
CSJ0045-20-019
Proj IDSTP 1602(438)
Work TypeINTERCHANGE IMPROVEMENT
 
0.7592147616.85860922.9140.0
CountyFANNIN
HighwayFM 898
From@ US 82
To.
CSJ0510-05-015
Proj IDSTP 1602(438)
Work TypeINTERCHANGE MODIFICATION
 
0.5004699617.761441359.6330.6
Work Order10-05-16
Work Began11-08-16
Work Completed
Time Computed11-04-16
Contract Working Days223
Addl Days Granted0
Working Days Charged102
Percent Time Used45
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-019
WYLIE DRILLING & DRAINAGE, INC. (2.10)
TEXOP CONSTRUCTION (1.10)
WEST TEXAS RUMBLE STRIP (0.05)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (11.39)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.69)
AARON CONCRETE CONTRACTORS, L.P. (0.95)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.13)
MOORE CONSTRUCTION, INC. (3.28)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09)
Contract #08163223
Totals6847234.61399688.702302282.5433.6

CountyRED RIVER
HighwayUS 82
From@ KICKAPOO CREEK
To.
CSJ0046-01-061
Proj IDBR 1502(210)
Work TypeBRIDGE REPLACEMENT
 
0.5152651371.112605873.7098.2
Work Order07-31-15
Work Began10-02-15
Work Completed
Time Computed08-30-15
Contract Working Days200
Addl Days Granted11
Working Days Charged208
Percent Time Used98
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-061
TOTAL HIGHWAY MAINTENANCE, LLC (0.34)
RK HALL, LLC (8.77)
DUSTIN ALLEN, INC. (1.93)
MOORE CONSTRUCTION, INC. (2.23)
TEX OP CONSTRUCTION, LP (0.66)
PENHALL COMPANY (0.24)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.03)
WITHERS CONSTRUCTION, LLC (0.16)
STRIPING TECHNOLOGY, L.P. (0.36)
WEST TEXAS RUMBLE STRIP (0.22)
MCL CONTRACTING, LLC (0.17)
STRIPING SYSTEMS, INC. (0.03)
Contract #06153246
Totals2651371.114340.002605873.7098.2

CountyGRAYSON
HighwaySH 5
FromCOLLIN COUNTY LINE
ToUS 75
CSJ0047-03-075
Proj IDSTP 1402(084)
Work TypeMISCELLANEOUS CONSTRUCTION
 
9.5753711917.793977578.0899.9
Work Order11-12-14
Work Began12-02-14
Work Completed
Time Computed02-10-15
Contract Working Days107
Addl Days Granted2
Working Days Charged304
Percent Time Used278
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-075
ALTUS TRAFFIC MANAGEMENT LLC (0.69)
MOORE CONSTRUCTION, INC. (0.26)
WITHERS CONSTRUCTION, LLC (2.37)
BAHENA CONSTRUCTION CO.,INC. (9.12)
LONE STAR BARRIER SERVICES, LLC (0.77)
TEXANA LAND & ASPHALT, INC. (10.26)
TEXAS ALTERNATIVE GRASSER, INC. (0.61)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (0.33)
STRIPING TECHNOLOGY, L.P. (1.88)
SAMMY GIST ENTERPRISES, INC. (0.00)
FARR FOUNDATION, INC. (1.93)
SOUTHERN CROSS CONTRACTORS, LLC (0.17)
Contract #09143041
Totals3711917.791434.953977578.0899.9

CountyGRAYSON
HighwayUS 75
FromAT FM 120, US 75 NORTH BOUND FR
ToAT FM 120, US 75 SOUTH BOUND FR
CSJ0047-18-074
Proj IDNH 1602(183)
Work TypeMISCELLANEOUS CONSTRUCTION
 
1.3404673413.963018398.5964.5
Work Order08-19-16
Work Began10-26-16
Work Completed
Time Computed09-19-16
Contract Working Days130
Addl Days Granted0
Working Days Charged126
Percent Time Used96
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-074
MORRIS COUNTY CONTRACTORS, L.L.C. (2.70)
RPM XCONSTRUCTION, LLC (5.86)
SOUTHERN CROSS CONTRACTORS, LLC (0.86)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (5.37)
WYLIE DRILLING & DRAINAGE, INC. (1.57)
DIAMOND SURFACE, INC. (0.17)
BOWMAN ENGINEERING & CONSULTING, INC (0.60)
DALLAS LITE AND BARRICADE INC. (0.60)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.18)
STRIPING TECHNOLOGY, L.P. (1.29)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.71)
HAYDON BUILDING CORP. (5.85)
W.O.E. CONSTRUCTION (0.06)
SELECT STRIPING LLC (1.29)
Contract #06163211
Totals4673413.96503941.043018398.5964.5

CountyGRAYSON ETC
HighwayUS 377 ETC
FromUS 82
ToDENTON COUNTY LINE
CSJ0081-07-023
Proj IDSTP 1602(331)HESG
Work TypeHAZARD ELIMINATION & SAFETY
 
212.8981372921.841096587.7681.0
Work Order08-11-16
Work Began09-27-16
Work Completed
Time Computed09-12-16
Contract Working Days70
Addl Days Granted0
Working Days Charged93
Percent Time Used132
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-07-023
COWBELL TRAFFIC SERVICES, INC. (14.93)
Contract #07163218
Totals1372921.840.071096587.7681.0

CountyGRAYSON ETC
HighwayUS 377 ETC
FromUS 82
ToFM 901
CSJ0081-10-042
Proj IDSTP 2016(186)
Work TypeSEAL COAT
 
242.2188437785.288561997.9199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-26-16
Work Began06-04-16
Work Completed
Time Computed05-16-16
Contract Working Days70
Addl Days Granted0
Working Days Charged80
Percent Time Used114
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-10-042
STRIPE-A-ZONE, INC. (16.29)
Contract #10153216
Totals8437785.280.008561997.9199.9

CountyHOPKINS
HighwaySH 11
From0.08 MI SE OF COUNTY LINE
To3.03 MI W OF FM 2653 S
CSJ0083-02-048
Proj IDSTP 1502(554)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
3.1575504239.112836553.9051.5
Work Order06-28-16
Work Began01-03-17
Work Completed
Time Computed09-01-16
Contract Working Days231
Addl Days Granted0
Working Days Charged85
Percent Time Used36
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0083-02-048
BAHENA CONSTRUCTION CO.,INC. (7.91)
PANOLA SIGN & BARRICADE, INC. (0.27)
STRIPING TECHNOLOGY, L.P. (0.99)
CATOCON, INC. (0.66)
MOORE CONSTRUCTION, INC. (1.29)
DUSTIN ALLEN, INC. (0.98)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (21.55)
TEXOP CONSTRUCTION (0.76)
SOUTHERN CROSS CONTRACTORS, LLC (0.58)
Contract #01163041
Totals5504239.11570097.462836553.9051.5

CountyRAINS
HighwaySH 19
FromHOPKINS COUNTY LINE
ToUS 69
CSJ0108-10-024
Proj IDSTP 1602(125)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.7248460153.963392135.0240.0
Work Order07-11-16
Work Began10-10-16
Work Completed
Time Computed08-10-16
Contract Working Days255
Addl Days Granted3
Working Days Charged168
Percent Time Used65
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0108-10-024
BAHENA CONSTRUCTION CO.,INC. (10.61)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.63)
TEXANA LAND & ASPHALT, INC. (2.66)
CATOCON, INC. (1.47)
STRIPING TECHNOLOGY, L.P. (1.62)
STRIPING SYSTEMS, INC. (0.00)
FLEX SUPPLY, LLC (0.17)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (31.04)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.73)
SAMMY G. SMALLWOOD (2.11)
DUSTROL, INC. (0.79)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.07)
DUSTIN ALLEN, INC. (2.11)
JM YANEZ CONSTRUCTION (3.93)
Contract #05163202
Totals8460153.96251956.863392135.0240.0

CountyDELTA
HighwaySH 24
FromFM 904
ToFM 64
CSJ0136-03-044
Proj IDTCSP 2010(387)
Work TypeGR, STRS BS, & SURF
 
10.95539277746.7128400036.0572.3
Work Order02-18-14
Work Began08-20-14
Work Completed
Time Computed08-01-14
Contract Working Days598
Addl Days Granted2
Working Days Charged526
Percent Time Used87
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0136-03-044
MOORE CONSTRUCTION, INC. (0.34)
LYON BARRICADE AND CONSTRUCTION CO. (0.20)
DUSTROL, INC. (0.04)
HIGHWAY 19 CONSTRUCTION, LLC (6.50)
FLAT LINE, INC. (0.80)
NORTH TEXAS HYDRA-HAMMER, INC. (0.05)
RK HALL, LLC (29.02)
SAMMY G. SMALLWOOD (0.83)
TEXAS ALTERNATIVE GRASSER, INC. (0.15)
TEX OP CONSTRUCTION, LP (0.19)
LONGVIEW BRIDGE AND ROAD, LTD. (16.25)
RED SIXTEEN CONSTRUCTION, INC (0.34)
MCL CONTRACTING, LLC (0.08)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.19)
BREDA COMPANY, INC. (0.02)
Contract #12133002
Totals39277746.71565072.8328400036.0572.3

CountyDELTA
HighwaySH 19
From@ NORTH SULPHUR RIVER
To.
CSJ0136-04-035
Proj IDBR 1702(379)
Work TypeBRIDGE REPLACEMENT
 
0.1181665295.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L & N BRIDGE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0136-04-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173037
Totals1665295.930.000.000.0

CountyHUNT
HighwaySH 34
FromINTERSECTION OF SH 276/SH 34
To.
CSJ0173-06-044
Proj IDSTP 1502(639)
Work TypeLANDSCAPE AND SCENIC ENHANCEMENT
 
0.10039179.0042606.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began03-14-16
Work Completed07-13-17
Time Computed02-29-16
Contract Working Days14
Addl Days Granted0
Working Days Charged13
Percent Time Used92
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-06-044
TX DOWN UNDER CONSTRUCTION, LLC (12.01)
ALTUS TRAFFIC MANAGEMENT LLC (3.34)
MABAK DIRECTIONAL DRILLING (7.65)
Contract #11153215
Totals39179.000.0042606.00100.0

CountyHUNT
HighwaySH 34 ETC
From0.19 MI. SOUTH OF IH30
ToBU 69-D
CSJ0173-07-055
Proj IDNH 2017(926)
Work TypeOVERLAY
 
6.4201683587.85540269.4532.0
Work Order05-18-17
Work Began06-15-17
Work Completed
Time Computed06-19-17
Contract Working Days102
Addl Days Granted0
Working Days Charged8
Percent Time Used7
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0173-07-055
ALTUS TRAFFIC MANAGEMENT LLC (0.82)
SOUTHWEST ENVIRONMENT SERVICES LLC (5.09)
TOTAL HIGHWAY MAINTENANCE, LLC (3.04)
Contract #04173014
Totals1683587.85540269.45540269.4532.0

CountyFRANKLIN
HighwaySH 37
FromFM 21
ToWOOD C/L
CSJ0190-01-021
Proj IDNH 1502(556)
Work TypeRECONST & ADD 10' SHLDRS
 
13.25820387243.989593984.5547.0
Work Order03-08-16
Work Began03-23-16
Work Completed
Time Computed06-06-16
Contract Working Days457
Addl Days Granted5
Working Days Charged261
Percent Time Used56
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-01-021
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18)
BAHENA CONSTRUCTION CO.,INC. (1.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.99)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.33)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.74)
STRIPING TECHNOLOGY, L.P. (1.18)
TX TINMAN ENTERPRISES, LLC. (1.85)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
KLP COMMERCIAL, LLC (0.00)
MESA ROD BUSTERS, INC. (0.04)
DFW REBAR, INC. (0.02)
ISAACS CONSTRUCTION SERVICES, LLC. (1.65)
Contract #01163001
Totals20387243.98298560.099593984.5547.0

CountyFANNIN ETC
HighwayUS 69
FromFM 151
ToHUNT COUNTY LINE
CSJ0202-03-041
Proj IDSTP 2017(739)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
39.0843186550.00511075.1616.0
Work Order03-15-17
Work Began04-10-17
Work Completed
Time Computed04-14-17
Contract Working Days180
Addl Days Granted0
Working Days Charged43
Percent Time Used23
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0202-03-041
AREA WIDE PROTECTIVE, INC. (0.84)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.02)
EAGLE BARRICADE,LLC. (1.12)
STRIPING TECHNOLOGY, L.P. (0.41)
SHALOM SERVICES CORPORATION (4.39)
ODUM SERVICES, L.P. (10.47)
Contract #02173020
Totals3186550.0024826.24511075.1616.0

page 1 | page 2 | page 3