Monthly State Let Construction Report For Paris District As Of Sep 15, 2016 Page 1 Of 4

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOPKINS
Highway IH 30
From ON IH 30, 1 MILE EAST OF CUMBY
To .
CSJ 0009-09-081
Proj ID STP 2000(825)TE
Work Type MISCELLANEOUS CONSTRUCTION
 
1.363 23690539.51 1273047.50 1273047.50 5.3
Work Order 07-01-16
Work Began 08-08-16
Work Completed  
Time Computed 08-01-16
Contract Working Days 368
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 4
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-081
EROSION CONTROL MANAGEMENT SERVICES(0.47%)
THELIN RECYCLING COMPANY, L.P. (0.54%)
DALLAS LITE AND BARRICADE INC. (0.53%)
GAY AND SONS MASONRY (3.79%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.39%)
Contract # 04163201
Totals 23690539.51 1273047.50 1273047.50 5.3

CountyHOPKINS
Highway IH 30
From 0.436 MI W OF SH 19 OVERPASS (NFR)
To TEXAS AVE IN SULPHUR SPRINGS
CSJ 0009-09-101
Proj ID NH 2016(821)
Work Type OVERLAY
 
11.427 2403661.81 495662.94 495662.94 20.6
Work Order 07-11-16
Work Began 08-11-16
Work Completed  
Time Computed 08-10-16
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 14
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-101
STRIPE-A-ZONE, INC.(3.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.22%)
SCR CIVIL CONSTRUCTION, LLC(3.87%)
DUSTROL, INC.(5.52%)
Contract # 03163014
Totals 2403661.81 495662.94 495662.94 20.6

CountyHUNT
Highway IH 30
From ROCKWALL COUNTY LINE
To FM 1565 NORTH
CSJ 0009-13-159
Proj ID BR 1602(330)
Work Type BRIDGE REPLACEMENT
 
5.778 22304844.44 0.00 0.00 0.0
CountyHUNT
Highway CR
From IH 30 EASTBOUND FRONTAGE ROAD
To FM 2642
CSJ 0901-22-115
Proj ID CC 901-22-115
Work Type REHABILITATION OF EXISTING ROAD
 
1.249 859715.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 493
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-159
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163005
Totals 23164560.31 0.00 0.00 0.0

CountyGRAYSON
Highway SH 56 ETC
From 564 FT E OF S BINKLEY PK DR
To TOLBERT AVE
CSJ 0045-03-048
Proj ID STP 2016(996)
Work Type OVERLAY
 
5.944 2250480.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-03-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163014
Totals 2250480.47 0.00 0.00 0.0

CountyLAMAR
Highway US 82
From FANNIN COUNTY LINE
To FM 38 EAST
CSJ 0045-08-036
Proj ID NH 2014(736)
Work Type WIDEN NON - FREEWAY
 
15.205 8860584.85 0.00 9135669.75 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 08-08-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 224
Percent Time Used 99
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-08-036
MOORE CONSTRUCTION, INC. (1.84%)
SAMMY G. SMALLWOOD (1.03%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
HIGHWAY 19 CONSTRUCTION, LLC (0.71%)
BAHENA CONSTRUCTION CO.,INC. (5.99%)
DUSTROL, INC.(0.97%)
RK HALL, LLC ( 68.34%)
STRIPING TECHNOLOGY, L.P.(2.05%)
CATACON, INC.(2.39%)
RED SIXTEEN CONSTRUCTION, INC(0.30%)
Contract # 06143204
Totals 8860584.85 0.00 9135669.75 99.9

CountyGRAYSON
Highway US 82
From FM 1897
To FANNIN COUNTY LINE
CSJ 0045-19-047
Proj ID C 45-19-47
Work Type WIDEN NON - FREEWAY
 
12.152 26059261.46 0.00 27626567.58 99.9
Work Order 10-12-12
Work Began 11-15-12
Work Completed  
Time Computed 04-10-13
Contract Working Days 473
Addl Days Granted 55
Working Days Charged 498
Percent Time Used 94
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-047
BAHENA CONSTRUCTION CO.,INC. (3.42%)
FORTSON CONTRACTING, INC.(0.06%)
L & N BRIDGE, LLC(2.48%)
GARY A. CRAIN, INC.(0.01%)
LYON BARRICADE AND CONSTRUCTION CO.(0.18%)
MOORE CONSTRUCTION, INC. (0.65%)
MURRAY CONSTRUCTION(0.63%)
RK HALL, LLC ( 42.19%)
STRIPING TECHNOLOGY, L.P.(0.72%)
WEST TEXAS RUMBLE STRIP(0.06%)
WYLIE DRILLING & DRAINAGE, INC.(0.38%)
TEX OP CONSTRUCTION, LP(0.69%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
TEXAS SHAFTS, INC. (0.20%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.25%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.01%)
Contract # 08123201
Totals 26059261.46 0.00 27626567.58 99.9

CountyGRAYSON
Highway US 82
From FRISCO ROAD (SHERMAN)
To FM 1417 EAST
CSJ 0045-19-050
Proj ID C 45-19-50
Work Type WIDEN NON - FREEWAY
 
1.617 12500127.04 106093.00 5742561.72 45.9
Work Order 11-10-15
Work Began 01-20-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 350
Addl Days Granted 0
Working Days Charged 134
Percent Time Used 38
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-050
ALTUS TRAFFIC MANAGEMENT LLC (0.25%)
LONE STAR BARRIER SERVICES, LLC(0.77%)
WOLFE CONSTRUCTION GROUP, INC. (0.79%)
DIAMOND SURFACE, INC.(0.08%)
OVERLAND CORPORATION ( 23.31%)
EROSION CONTROL MANAGEMENT SERVICES(0.26%)
RPM XCONSTRUCTION, LLC ( 29.70%)
FARR FOUNDATION, INC.(0.22%)
STRIPING TECHNOLOGY, L.P.(0.52%)
VENUS CONSTRUCTION (5.39%)
KMB TRUCKING LLC (0.00%)
TEXOP CONSTRUCTION (0.29%)
Contract # 07153207
Totals 12500127.04 106093.00 5742561.72 45.9

CountyFANNIN
Highway US 82
From AT FM 898
To .
CSJ 0045-20-019
Proj ID STP 1602(438)
Work Type INTERCHANGE IMPROVEMENT
 
0.759 2147616.85 0.00 0.00 0.0
CountyFANNIN
Highway FM 898
From @ US 82
To .
CSJ 0510-05-015
Proj ID STP 1602(438)
Work Type INTERCHANGE MODIFICATION
 
0.500 4699617.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163223
Totals 6847234.61 0.00 0.00 0.0

CountyRED RIVER
Highway US 82
From @ KICKAPOO CREEK
To .
CSJ 0046-01-061
Proj ID BR 1502(210)
Work Type BRIDGE REPLACEMENT
 
0.515 2651371.11 21957.53 645536.30 24.3
Work Order 07-31-15
Work Began 10-02-15
Work Completed  
Time Computed 08-30-15
Contract Working Days 200
Addl Days Granted 11
Working Days Charged 55
Percent Time Used 26
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-061
TOTAL HIGHWAY MAINTENANCE, LLC (0.34%)
RK HALL, LLC (8.77%)
DUSTIN ALLEN, INC. (1.93%)
MOORE CONSTRUCTION, INC. (2.23%)
TEX OP CONSTRUCTION, LP(0.66%)
PENHALL COMPANY(0.24%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.03%)
WITHERS CONSTRUCTION, LLC(0.16%)
STRIPING TECHNOLOGY, L.P.(0.36%)
WEST TEXAS RUMBLE STRIP(0.22%)
MCL CONTRACTING, LLC (0.17%)
STRIPING SYSTEMS, INC. (0.03%)
Contract # 06153246
Totals 2651371.11 21957.53 645536.30 24.3

CountyRED RIVER
Highway US 82
From 0.285 MI WEST OF FM 114
To 0.185 MI EAST OF FM 412
CSJ 0046-01-062
Proj ID STP 1502(550)HES
Work Type HAZARD ELIMINATION & SAFETY
 
1.251 795946.99 159148.52 601238.63 76.5
Work Order 10-30-15
Work Began 12-08-15
Work Completed  
Time Computed 12-29-15
Contract Working Days 66
Addl Days Granted 6
Working Days Charged 85
Percent Time Used 118
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-062
BAHENA CONSTRUCTION CO.,INC. ( 10.99%)
MOORE CONSTRUCTION, INC. (2.40%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.36%)
SAMMY SMALLWOOD COMPANY(3.28%)
STRIPING TECHNOLOGY, L.P.(2.80%)
STRIPING SYSTEMS, INC. (0.11%)
TEXANA LAND & ASPHALT, INC.(0.75%)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.01%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (3.93%)
Contract # 08153240
Totals 795946.99 159148.52 601238.63 76.5

CountyGRAYSON
Highway SH 5
From COLLIN COUNTY LINE
To US 75
CSJ 0047-03-075
Proj ID STP 1402(084)
Work Type MISCELLANEOUS CONSTRUCTION
 
9.575 3711917.79 402471.42 3494730.09 96.3
Work Order 11-12-14
Work Began 12-02-14
Work Completed  
Time Computed 02-10-15
Contract Working Days 107
Addl Days Granted 2
Working Days Charged 193
Percent Time Used 177
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-075
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
MOORE CONSTRUCTION, INC. (0.26%)
WITHERS CONSTRUCTION, LLC(2.37%)
BAHENA CONSTRUCTION CO.,INC. (9.12%)
LONE STAR BARRIER SERVICES, LLC(0.77%)
TEXANA LAND & ASPHALT, INC.( 10.26%)
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.33%)
STRIPING TECHNOLOGY, L.P.(1.88%)
SAMMY GIST ENTERPRISES, INC. (0.00%)
FARR FOUNDATION, INC.(1.93%)
Contract # 09143041
Totals 3711917.79 402471.42 3494730.09 96.3

CountyGRAYSON
Highway US 75
From FM 902
To SHEPHERD DRIVE
CSJ 0047-03-076
Proj ID C 47-3-76
Work Type REHABILITATION OF EXISTING ROADWAY
 
1.495 8342650.77 0.00 8913825.25 99.9
Work Order 11-04-13
Work Began 01-27-14
Work Completed  
Time Computed 01-03-14
Contract Working Days 142
Addl Days Granted 47
Working Days Charged 255
Percent Time Used 134
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-076
BROCK ENVIRONMENTAL, LLC (0.10%)
DUSTROL, INC.(0.10%)
FORTSON CONTRACTING, INC.(0.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.38%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
SAMMY G. SMALLWOOD (0.42%)
W.O.E. CONSTRUCTION(0.44%)
STRIPING TECHNOLOGY, L.P.(1.27%)
ANTIGO CONSTRUCTION, INC.(0.38%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.29%)
VENUS CONSTRUCTION (4.15%)
MCL CONTRACTING, LLC (1.18%)
MABAK DIRECTIONAL DRILLING (0.08%)
ASPLUNDH TREE EXPERT CO(0.39%)
Contract # 08133224
Totals 8342650.77 0.00 8913825.25 99.9

CountyGRAYSON
Highway US 75
From @ FM 84
To .
CSJ 0047-18-070
Proj ID STP 1502(552)HES
Work Type HAZARD ELIMINATION & SAFETY
 
0.100 142990.00 0.00 143232.60 99.9
Work Order 09-22-15
Work Began 05-16-16
Work Completed  
Time Computed 03-21-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 86
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153025
Totals 142990.00 0.00 143232.60 99.9

CountyGRAYSON
Highway US 75
From LOY LAKE ROAD
To US 82
CSJ 0047-18-071
Proj ID NH 1502(553)
Work Type MISCELLANEOUS CONSTRUCTION
 
0.266 579502.00 3500.00 551227.37 95.1
Work Order 09-22-15
Work Began 12-10-15
Work Completed  
Time Computed 10-22-15
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 79
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-071
STRIPING TECHNOLOGY, L.P.(3.61%)
PEACHTREE CONSTRUCTION, LTD. (8.24%)
RMI WORLDWIDE, LLC (0.77%)
Contract # 08153223
Totals 579502.00 3500.00 551227.37 95.1

CountyGRAYSON
Highway US 75
From AT FM 120, US 75 NORTH BOUND FR
To AT FM 120, US 75 SOUTH BOUND FR
CSJ 0047-18-074
Proj ID NH 1602(183)
Work Type MISCELLANEOUS CONSTRUCTION
 
1.340 4673413.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163211
Totals 4673413.96 0.00 0.00 0.0

CountyGRAYSON
Highway US 377 ETC
From US 82
To DENTON COUNTY LINE
CSJ 0081-07-023
Proj ID STP 1602(331)HESG
Work Type HAZARD ELIMINATION & SAFETY
 
212.898 1372921.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-07-023
COWBELL TRAFFIC SERVICES, INC. ( 14.93%)
Contract # 07163218
Totals 1372921.84 0.00 0.00 0.0

CountyGRAYSON
Highway US 377 ETC
From US 82
To FM 901
CSJ 0081-10-042
Proj ID STP 2016(186)
Work Type SEAL COAT
 
242.218 8437785.28 1491310.31 5433924.18 64.3
Work Order 01-26-16
Work Began 06-04-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 55
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-10-042
STRIPE-A-ZONE, INC.( 16.29%)
Contract # 10153216
Totals 8437785.28 1491310.31 5433924.18 64.3

CountyGRAYSON
Highway BU 377C
From HUGHES STREET
To FM 902
CSJ 0081-16-003
Proj ID STP 2016(595)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 178510.00 2745.00 177803.65 99.6
Work Order 03-01-16
Work Began 04-19-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 28
Addl Days Granted 3
Working Days Charged 31
Percent Time Used 100
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-16-003
ALTUS TRAFFIC MANAGEMENT LLC (1.41%)
Contract # 01163222
Totals 178510.00 2745.00 177803.65 99.6

CountyHOPKINS
Highway SH 11
From 0.08 MI SE OF COUNTY LINE
To 3.03 MI W OF FM 2653 S
CSJ 0083-02-048
Proj ID STP 1502(554)HES
Work Type HAZARD ELIMINATION & SAFETY
 
3.157 5504239.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-28-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 231
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0083-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163041
Totals 5504239.11 0.00 0.00 0.0

CountyRAINS
Highway SH 19
From HOPKINS COUNTY LINE
To US 69
CSJ 0108-10-024
Proj ID STP 1602(125)
Work Type REHABILITATION OF EXISTING ROAD
 
7.724 8460153.96 0.00 49803.00 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 2
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0108-10-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163202
Totals 8460153.96 0.00 49803.00 0.5

page 1 | page 2 | page 3 | page 4