Monthly State Let Construction Report For Paris District As Of Jun 11, 2013 Page 1 Of 3

Last Update: Tuesday, June 11, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOPKINS
Highway IH 30
From HUNT COUNTY LINE
To 0.11 MI EAST OF FM 499 CONNECTOR
CSJ 0009-09-097
Proj ID IM 0302(098)
Work Type OVERLAY
 
3.359 2799967.06 110586.70 2674360.43 96.1
Work Order 05-15-12
Work Began 10-09-12
Work Completed  
Time Computed 05-31-12
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 146
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-097
HIGHWAY TECHNOLOGIES, INC. (0.06%)
DUSTROL, INC.(5.37%)
MOORE CONSTRUCTION, INC. (0.24%)
STRIPING TECHNOLOGY, L.P.(1.58%)
Contract # 04123217
Totals 2799967.06 110586.70 2674360.43 96.1

CountyHOPKINS
Highway IH 30 ETC
From HUNT COUNTY LINE (NFR)
To SH 19
CSJ 0009-09-098
Proj ID IM 0302(099)
Work Type SEAL COAT
 
252.774 9380182.59 3443320.13 8387343.15 89.4
Work Order 11-14-12
Work Began 00-00-00
Work Completed  
Time Computed 04-01-13
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 47
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-098
STRIPING TECHNOLOGY, L.P.(5.07%)
BRYDL CONTRACTING, INC.(0.65%)
Contract # 10123210
Totals 9380182.59 3443320.13 8387343.15 89.4

CountyHOPKINS
Highway IH 30
From BILL BRADFORD ROAD
To LOOP 301
CSJ 0010-02-087
Proj ID IM 0302(100)
Work Type RESTORATION OF EXISTING ROAD
 
2.254 2519811.30 966359.90 1196924.59 47.5
Work Order 04-03-13
Work Began 04-17-13
Work Completed  
Time Computed 04-19-13
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 37
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-02-087
SOUTHWEST ENVIRONMENT SERVICES LLC (0.04%)
DUSTIN ALLEN, INC. (0.07%)
HIGHWAY TECHNOLOGIES, INC. (0.29%)
SCR CONSTRUCTION CO., INC. (9.18%)
STRIPING TECHNOLOGY, L.P.(1.58%)
WINDING ROAD CONSTRUCTION, INC.(5.92%)
DUSTROL, INC.(2.50%)
DALE BROWN, INC. (0.00%)
Contract # 01133224
Totals 2519811.30 966359.90 1196924.59 47.5

CountyHOPKINS
Highway IH 30
From IH 30 WB
To AT ROCK CREEK RELIEF #2 AND #3
CSJ 0010-02-090
Proj ID BR 2012(449)
Work Type BRIDGE REPLACEMENT
 
0.194 1478966.64 47690.68 1476552.18 99.8
Work Order 04-16-12
Work Began 08-06-12
Work Completed  
Time Computed 05-02-12
Contract Working Days 191
Addl Days Granted 66
Working Days Charged 126
Percent Time Used 49
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-02-090
HIGHWAY TECHNOLOGIES, INC. (0.66%)
DUSTROL, INC.(0.70%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.36%)
RK HALL, LLC ( 14.37%)
JUST GROOVING, LTD.(0.26%)
SCOTT DERR PAINTING CO (0.35%)
DUSTIN ALLEN, INC. (2.36%)
STRIPING TECHNOLOGY, L.P.(1.18%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.38%)
MESA ROD BUSTERS, INC. (0.00%)
GREGG WILLIAMS CONSTRUCTION(0.15%)
Contract # 03123001
Totals 1478966.64 47690.68 1476552.18 99.8

CountyGRAYSON
Highway SH 56 ETC
From US 82
To COLLINS ROAD
CSJ 0045-02-031
Proj ID STP 2012(069)
Work Type SEAL COAT
 
227.306 7539782.11 0.00 8058408.83 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-16-11
Work Began 05-09-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 54
Addl Days Granted 4
Working Days Charged 60
Percent Time Used 103
Contractor(s)
NE-TEX CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0045-02-031
STRIPING TECHNOLOGY, L.P.(9.22%)
Contract # 10113208
Totals 7539782.11 0.00 8058408.83 99.9

CountyGRAYSON
Highway US 82
From AT FM 1417
To .
CSJ 0045-19-044
Proj ID STP 2010(989)SB
Work Type SAFETY
 
0.750 3606776.26 0.00 4181687.38 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-10
Work Began 11-09-10
Work Completed  
Time Computed 11-05-10
Contract Working Days 273
Addl Days Granted 17
Working Days Charged 300
Percent Time Used 103
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-044
DALLAS LITE AND BARRICADE INC. (0.54%)
MOORE CONSTRUCTION, INC. (0.47%)
BIG BIRD TREE SERVICE, INC.(0.88%)
BAHENA CONSTRUCTION CO.,INC. (0.05%)
JONA CONTRACTING, INC. (1.00%)
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
AUSTIN BRIDGE & ROAD, LP ( 34.99%)
HODGES AND SON CONSTRUCTION COMPANY, INC.( 18.80%)
TEX OP CONSTRUCTION, LP(0.12%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.12%)
WEST TEXAS RUMBLE STRIP(0.11%)
STATEWIDE TRUCKING CORP. (0.33%)
CARRASCO TRUCKING(0.33%)
OCHOA I. TRUCKING(0.33%)
HOUSTON SAWING & DRILLING(0.15%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.00%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.00%)
Contract # 08103009
Totals 3606776.26 0.00 4181687.38 99.9

CountyGRAYSON
Highway US 82
From FM 1897
To FANNIN COUNTY LINE
CSJ 0045-19-047
Proj ID C 45-19-47
Work Type WIDEN NON - FREEWAY
 
12.152 26059261.46 1225999.54 5761213.97 22.1
Work Order 10-12-12
Work Began 11-15-12
Work Completed  
Time Computed 04-10-13
Contract Working Days 473
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 20
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-047
BAHENA CONSTRUCTION CO.,INC. (3.42%)
FORTSON CONTRACTING, INC.(0.06%)
L & N BRIDGE, LLC(2.48%)
GARY A. CRAIN, INC.(0.01%)
LYON BARRICADE AND CONSTRUCTION CO.(0.18%)
MOORE CONSTRUCTION, INC. (0.65%)
MURRAY CONSTRUCTION(0.35%)
RK HALL, LLC ( 42.19%)
STRIPING TECHNOLOGY, L.P.(0.72%)
WEST TEXAS RUMBLE STRIP(0.06%)
WYLIE DRILLING & DRAINAGE, INC.(0.38%)
TEX OP CONSTRUCTION, LP(0.69%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
TEXAS SHAFTS, INC. (0.20%)
Contract # 08123201
Totals 26059261.46 1225999.54 5761213.97 22.1

CountyGRAYSON
Highway US 69
From AT BNSF & UP RAILROAD OVERPASS
To .
CSJ 0047-02-092
Proj ID BR 1102(287)
Work Type BRIDGE REPLACEMENT
 
0.413 7983527.71 236183.15 7436926.14 93.5
Work Order 09-13-11
Work Began 11-08-11
Work Completed  
Time Computed 12-12-11
Contract Working Days 361
Addl Days Granted 0
Working Days Charged 393
Percent Time Used 108
Contractor(s)
L & N BRIDGE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-02-092
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.10%)
DALLAS LITE AND BARRICADE INC. (0.23%)
DUSTROL, INC.(0.15%)
GARY A. CRAIN, INC.(0.43%)
INTERSTATE FOUNDATION, LLC (3.08%)
LONE STAR BARRIER SERVICES, LLC(0.56%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (1.00%)
RK HALL, LLC (1.27%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.51%)
RG PAINTING(0.86%)
Contract # 08113215
Totals 7983527.71 236183.15 7436926.14 93.5

CountyGRAYSON
Highway SH 91
From US 75
To SPUR 503
CSJ 0047-02-132
Proj ID STP 2012(450)
Work Type OVERLAY
 
5.330 2685392.03 44894.50 2873786.02 99.9
Work Order 05-15-12
Work Began 09-05-12
Work Completed  
Time Computed 05-31-12
Contract Working Days 48
Addl Days Granted 5
Working Days Charged 92
Percent Time Used 173
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-02-132
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.40%)
DUSTROL, INC.( 11.30%)
FORTSON CONTRACTING, INC.(1.01%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.23%)
PRIMATE CONSTRUCTION, INC. (2.47%)
STRIPING TECHNOLOGY, L.P.(3.71%)
Contract # 04123214
Totals 2685392.03 44894.50 2873786.02 99.9

CountyHOPKINS
Highway SH 11
From 3.61 MILES EAST OF FM 2653
To 6.21 MILES EAST OF FM 2653
CSJ 0083-02-049
Proj ID STP 2012(480)
Work Type REHABILITATION OF EXISTING ROAD
 
2.605 2433157.68 1145.00 1318546.97 54.1
Work Order 05-22-12
Work Began 08-13-12
Work Completed  
Time Computed 07-23-12
Contract Working Days 251
Addl Days Granted 0
Working Days Charged 117
Percent Time Used 46
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0083-02-049
BAHENA CONSTRUCTION CO.,INC. ( 10.74%)
CATOCON, INC.(0.48%)
FORTSON CONTRACTING, INC.(0.36%)
HIGHWAY TECHNOLOGIES, INC. (0.65%)
MOORE CONSTRUCTION, INC. (1.40%)
STRIPING TECHNOLOGY, L.P.(1.87%)
Contract # 04123209
Totals 2433157.68 1145.00 1318546.97 54.1

CountyHOPKINS
Highway SH 11
From 1.568 MI E OF FM 269N
To FRANKLIN COUNTY LINE
CSJ 0083-04-023
Proj ID STP 2011(348)
Work Type REHABILITATION OF EXISTING ROAD
 
5.388 4638237.36 16935.13 4251516.77 91.7
Work Order 09-23-10
Work Began 03-30-11
Work Completed  
Time Computed 03-22-11
Contract Working Days 292
Addl Days Granted 30
Working Days Charged 328
Percent Time Used 101
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0083-04-023
PANOLA LIGHT & SIGN(0.55%)
MOORE CONSTRUCTION, INC. (2.81%)
CATOCON, INC.(0.79%)
BAHENA CONSTRUCTION CO.,INC. ( 10.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.15%)
DUSTIN ALLEN, INC. (0.37%)
MURRAY CONSTRUCTION(1.23%)
BILLY CUMMINGS CONSTRUCTION INC( 20.36%)
MOHL AND SCOTT, INC. (5.07%)
J & L PAVING (0.21%)
Contract # 08103306
Totals 4638237.36 16935.13 4251516.77 91.7

CountyGRAYSON
Highway SH 289
From 0.300 MILES SOUTH OF SP 316
To 0.183 MILES NORTH OF SP 316
CSJ 0091-01-046
Proj ID STP 2012(573)
Work Type WIDEN NON - FREEWAY
 
7.464 4252949.45 329772.21 3338932.26 78.5
Work Order 07-12-12
Work Began 07-31-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 201
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 87
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0091-01-046
CATOCON, INC.(0.96%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.12%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.61%)
J. M. CONSTRUCTION (6.12%)
LONE STAR BARRIER SERVICES, LLC(0.19%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.11%)
RK HALL, LLC (2.79%)
TEX OP CONSTRUCTION, LP(0.25%)
Contract # 05123220
Totals 4252949.45 329772.21 3338932.26 78.5

CountyHUNT
Highway US 380
From 0.395 MILES EAST OF FM 903
To US 69
CSJ 0135-07-039
Proj ID NH 2009(450)
Work Type WIDEN NON - FREEWAY
 
4.209 17631266.70 422849.14 15315227.31 89.3
Work Order 06-04-09
Work Began 06-22-09
Work Completed  
Time Computed 06-20-09
Contract Working Days 374
Addl Days Granted 319
Working Days Charged 977
Percent Time Used 140
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0135-07-039
COWBELL TRAFFIC SERVICES, INC. (0.13%)
BAHENA CONSTRUCTION CO.,INC. (5.70%)
MOORE CONSTRUCTION, INC. (0.60%)
TEXAS SHAFTS, INC. (1.05%)
BRAZOS VALLEY CONTRACTING CO.(7.63%)
DUSTIN ALLEN, INC. (0.43%)
HIGHWAY TECHNOLOGIES, INC. (0.47%)
PRIMATE CONSTRUCTION, INC. (0.07%)
S & S BRIDGE PAINTING, INC.(0.10%)
CLEMENTE CONSTRUCTION INC. (1.87%)
RUNNING HORSE CONSTRUCTION, INC. (0.88%)
WEIR BROS.,INC.( 22.64%)
DUSTROL, INC. (ROANOKE)(0.84%)
STRIPING TECHNOLOGY, L.P.(0.48%)
FARR FOUNDATION, INC.(0.20%)
J. M. CONSTRUCTION (2.20%)
Contract # 05093201
Totals 17631266.70 422849.14 15315227.31 89.3

CountyLAMAR
Highway US 271
From FM 1499 (SB)
To US 82 (SB)
CSJ 0136-07-048
Proj ID NH 2012(781)
Work Type REHABILITATION OF EXISTING ROAD
 
8.935 3275793.23 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-24-12
Work Began 00-00-00
Work Completed  
Time Computed 03-25-13
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0136-07-048
MOORE CONSTRUCTION, INC. (1.74%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.54%)
TEX OP CONSTRUCTION, LP(0.17%)
LONE STAR BARRIER SERVICES, LLC(0.90%)
COWBELL TRAFFIC SERVICES, INC. (0.50%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.48%)
LYON BARRICADE AND CONSTRUCTION CO.(0.40%)
Contract # 08123229
Totals 3275793.23 0.00 0.00 0.0

CountyFANNIN
Highway SH 34
From 0.014 MI NORTH OF SH 56
To 0.120 MI NORTH OF US 82
CSJ 0174-04-028
Proj ID STP 2013(678)
Work Type OVERLAY
 
1.185 301262.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0174-04-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133013
Totals 301262.01 0.00 0.00 0.0

CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-007
Proj ID BR 2012(716)
Work Type BRIDGE REPLACEMENT
 
0.570 11302230.33 645457.10 2073673.58 18.3
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-009
Proj ID BR 2012(792)
Work Type BRIDGE REPLACEMENT
 
0.360 1517866.78 0.00 272346.24 17.9
CountyRED RIVER
Highway SH 37
From AT RED RIVER
To .
CSJ 0189-01-010
Proj ID CC 189-1-10
Work Type BRIDGE REPLACEMENT
 
0.360 1759959.64 0.00 463474.96 26.3
Work Order 10-24-12
Work Began 02-05-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 495
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 8
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0189-01-007
ATS DRILLING, INC. ( 14.68%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.91%)
SCOTT DERR PAINTING CO, LLC(0.20%)
TEX OP CONSTRUCTION, LP(0.22%)
RK HALL, LLC ( 12.53%)
SOUTHEAST GRINDING & GROOVING, LLC (0.09%)
MCL CONTRACTING, LLC (0.96%)
LYON BARRICADE AND CONSTRUCTION CO.(0.11%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.08%)
DUSTIN ALLEN, INC. (0.13%)
MCL CONTRACTING, LLC (2.18%)
HIGHWAY TECHNOLOGIES, INC. (0.37%)
Contract # 08123208
Totals 14580056.75 645457.10 2809494.78 19.2

CountyGRAYSON
Highway FM 131
From @ US 82 FRONTAGE ROADS
To .
CSJ 0202-08-051
Proj ID STP 2012(451)
Work Type MISCELLANEOUS CONSTRUCTION
 
0.316 590830.44 0.00 635152.92 99.9
CountyGRAYSON
Highway CS
From CANYON GROVE ROAD
To US 82 WB FR
CSJ 0901-19-174
Proj ID STP 2012(486)
Work Type NEW LOCATION NON - FREEWAY
 
0.108 299729.04 0.00 286685.35 95.6
Work Order 06-25-12
Work Began 09-13-12
Work Completed  
Time Computed 08-24-12
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 94
Contractor(s)
NE-TEX CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0202-08-051
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.64%)
HJC FARMS, INC.(3.14%)
J. M. CONSTRUCTION ( 32.88%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION ( 12.59%)
STRIPING TECHNOLOGY, L.P.(2.51%)
SYNERGY SIGNS & SERVICES (1.34%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.64%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. ( 26.61%)
Contract # 04123016
Totals 890559.48 0.00 921838.27 99.9

CountyGRAYSON
Highway FM 131
From CANYON GROVE ROAD
To FM 691
CSJ 0202-08-055
Proj ID STP 2013(679)
Work Type OVERLAY
 
2.008 906055.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0202-08-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133017
Totals 906055.26 0.00 0.00 0.0

CountyGRAYSON
Highway FM 1417
From REFUGE ROAD
To 1.0 MILE SOUTH OF REFUGE RD
CSJ 0202-08-057
Proj ID STP 2013(332)
Work Type MISCELLANEOUS CONSTRUCTION
 
1.000 359999.95 48422.09 137334.32 38.1
Work Order 03-22-13
Work Began 00-00-00
Work Completed  
Time Computed 05-21-13
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 56
Contractor(s)
BILLY CUMMINGS CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0202-08-057
MOORE CONSTRUCTION, INC. (3.28%)
TEX OP CONSTRUCTION, LP(1.34%)
MOHL AND SCOTT, INC. (9.29%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (2.61%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.56%)
PEACHTREE CONSTRUCTION, LTD. ( 45.38%)
HIGHWAY TECHNOLOGIES, INC. (3.84%)
HIGHWAY 19 CONSTRUCTION, LLC (5.17%)
Contract # 01133219
Totals 359999.95 48422.09 137334.32 38.1

CountyHUNT
Highway US 69
From 1.64 MILES SOUTH OF BU 69
To FM 513
CSJ 0203-02-041
Proj ID STP 1102(440)
Work Type WIDEN NON - FREEWAY
 
9.742 14582825.27 1288676.49 12184147.22 83.5
Work Order 09-27-11
Work Began 02-08-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 320
Addl Days Granted 28
Working Days Charged 293
Percent Time Used 84
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
R. K. HALL CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-02-041
CATOCON, INC.(0.34%)
DUSTIN ALLEN, INC. (0.40%)
HIGHWAY TECHNOLOGIES, INC. (0.25%)
J. M. CONSTRUCTION (4.76%)
MOORE CONSTRUCTION, INC. (0.48%)
STRIPING TECHNOLOGY, L.P.(1.67%)
TEXAS ALTERNATIVE GRASSER, INC.(0.35%)
TEX OP CONSTRUCTION, LP(0.14%)
RK HALL, LLC ( 38.97%)
Contract # 08113206
Totals 14582825.27 1288676.49 12184147.22 83.5