Monthly State Let Construction Report For Paris District As Of Mar 13, 2017 Page 2 Of 3

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRAINS
HighwayUS 69
FromSH 19
To586 NORTH OF FM 3299 INTERSECTION
CSJ0203-03-044
Proj IDSTP 1402(093)
Work TypeMISCELLANEOUS CONSTRUCTION
 
3.2404635055.964415408.1395.7
Work Order11-12-14
Work Began02-26-15
Work Completed
Time Computed02-10-15
Contract Working Days159
Addl Days Granted0
Working Days Charged183
Percent Time Used115
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-044
ALTUS TRAFFIC MANAGEMENT LLC (0.27)
BAHENA CONSTRUCTION CO.,INC. (13.11)
MOORE CONSTRUCTION, INC. (0.76)
RK HALL, LLC (38.07)
SAMMY G. SMALLWOOD (0.30)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (0.69)
TEX OP CONSTRUCTION, LP (0.35)
WITHERS CONSTRUCTION, LLC (0.37)
STRIPING TECHNOLOGY, L.P. (0.77)
Contract #09143209
Totals4635055.9621140.004415408.1395.7

CountyFANNIN
HighwaySH 78
FromSH 11
To0.68 MI S OF SH 56
CSJ0279-03-035
Proj IDSTP 2017(188)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
23.8702675061.25237243.988.8
Work Order12-06-16
Work Began01-09-17
Work Completed
Time Computed02-01-17
Contract Working Days159
Addl Days Granted0
Working Days Charged21
Percent Time Used13
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0279-03-035
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.76)
WITHERS CONSTRUCTION, LLC (1.32)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (13.21)
Contract #10163212
Totals2675061.25221835.98237243.988.8

CountyHOPKINS
HighwaySH 19
FromDELTA COUNTY LINE
ToLOOP 301
CSJ0400-02-048
Proj IDSTP 1502(137)
Work TypeOVERLAY
 
12.2041267814.141359457.9499.9
Work Order06-15-15
Work Began08-24-15
Work Completed
Time Computed07-16-15
Contract Working Days48
Addl Days Granted18
Working Days Charged62
Percent Time Used93
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0400-02-048
FLEX SUPPLY, LLC (0.60)
JOHN MILLSAP (5.23)
STRIPING TECHNOLOGY, L.P. (6.43)
WEST TEXAS RUMBLE STRIP (0.81)
Contract #05153032
Totals1267814.140.001359457.9499.9

CountyHOPKINS
HighwaySH 154
From0.315 MILES NORTH OF FM 1567 EAST
To0.195 MILES SOUTH OF CR 1104
CSJ0401-01-022
Proj IDSTP 2013(464)
Work TypeUPGRADE TO NON-FREEWAY STANDARDS
 
4.9736591501.998106460.5899.9
Work Order05-13-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days457
Addl Days Granted0
Working Days Charged451
Percent Time Used98
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-01-022
PANOLA SIGN & BARRICADE, INC. (0.54)
BAHENA CONSTRUCTION CO.,INC. (9.56)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.24)
FORTSON CONTRACTING, INC. (4.14)
STRIPING TECHNOLOGY, L.P. (1.24)
MOORE CONSTRUCTION, INC. (0.57)
TEXANA LAND & ASPHALT, INC. (0.57)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (27.89)
Contract #03133219
Totals6591501.990.008106460.5899.9

CountyRED RIVER
HighwayFM 44
FromFM 412
ToFM 911
CSJ0427-01-037
Proj IDSTP 2016(363)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.3634617291.242930413.3363.4
Work Order03-15-16
Work Began04-25-16
Work Completed
Time Computed05-16-16
Contract Working Days222
Addl Days Granted4
Working Days Charged173
Percent Time Used76
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0427-01-037
HIGHWAY 19 CONSTRUCTION, LLC (1.62)
LYON BARRICADE AND CONSTRUCTION CO. (0.52)
WITHERS CONSTRUCTION, LLC (2.23)
MOORE CONSTRUCTION CO. (2.98)
SAMMY SMALLWOOD COMPANY (2.37)
BAHENA CONSTRUCTION CO.,INC. (11.37)
TEX OP CONSTRUCTION, LP (0.15)
STRIPING TECHNOLOGY, L.P. (1.84)
STRIPING SYSTEMS, INC. (0.02)
MOORE CONSTRUCTION, INC. (2.98)
Contract #02163241
Totals4617291.2462296.182930413.3363.4

CountyLAMAR
HighwayFM 137
FromFM 38
ToUS 82
CSJ0435-01-068
Proj IDSTP 2016(099)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.9983768340.103449492.2091.9
Work Order11-13-15
Work Began12-09-15
Work Completed
Time Computed01-12-16
Contract Working Days171
Addl Days Granted0
Working Days Charged187
Percent Time Used109
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-068
N-LINE TRAFFIC MAINTENANCE, L.P. (0.72)
STRIPING TECHNOLOGY, L.P. (3.34)
CATOCON, INC. (1.79)
MOORE CONSTRUCTION, INC. (1.99)
SAMMY SMALLWOOD COMPANY (4.58)
BAHENA CONSTRUCTION CO.,INC. (1.46)
MURRAY CONSTRUCTION (1.48)
ACU CONSTRUCTION LLC (0.65)
ANCHOR CONTRACTING, LLC (0.43)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.49)
Contract #09153025
Totals3768340.100.003449492.2091.9

CountyGRAYSON
HighwayFM 902
FromUS 377
ToSH 289
CSJ0510-01-026
Proj IDSTP 2015(309)
Work TypeREHABILITATION OF EXISTING ROAD
 
14.4277337375.525648387.9977.3
Work Order01-02-15
Work Began09-28-15
Work Completed
Time Computed04-02-15
Contract Working Days304
Addl Days Granted0
Working Days Charged327
Percent Time Used107
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05)
CATOCON, INC. (1.83)
FARR FOUNDATION, INC. (4.74)
LYON BARRICADE AND CONSTRUCTION CO. (0.46)
MURRAY CONSTRUCTION (1.26)
SAMMY G. SMALLWOOD (1.75)
STRIPING TECHNOLOGY, L.P. (1.54)
TEXANA LAND & ASPHALT, INC. (2.35)
BAHENA CONSTRUCTION CO.,INC. (14.62)
MOORE CONSTRUCTION, INC. (1.15)
Contract #11143220
Totals7337375.525072.005648387.9977.3

CountyDELTA ETC
HighwaySH 19 ETC
From@ BRUSHY CREEK
To.
CSJ0525-01-020
Proj IDBR 1502(141)
Work TypeBRIDGE REPLACEMENT
 
0.6784018602.903589999.8189.3
Work Order06-30-15
Work Began09-22-15
Work Completed
Time Computed08-30-15
Contract Working Days348
Addl Days Granted0
Working Days Charged253
Percent Time Used72
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
PANOLA SIGN & BARRICADE, INC. (0.71)
MOORE CONSTRUCTION, INC. (1.43)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (4.08)
DUSTIN ALLEN, INC. (3.15)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.02)
STRIPING TECHNOLOGY, L.P. (1.08)
PENHALL COMPANY (0.23)
TEX OP CONSTRUCTION, LP (0.62)
WITHERS CONSTRUCTION, LLC (0.79)
MCL CONTRACTING, LLC (0.30)
Contract #05153217
Totals4018602.9013618.503589999.8189.3

CountyFANNIN
HighwaySH 121
FromUS 82
ToSH 56
CSJ0549-01-029
Proj IDSTP 2012(575)
Work TypeUPGRADE TO NON-FREEWAY STANDARDS
 
1.8636855007.156355139.9999.3
Work Order10-18-12
Work Began03-11-13
Work Completed
Time Computed04-22-13
Contract Working Days284
Addl Days Granted36
Working Days Charged725
Percent Time Used226
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. (12.74)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70)
NE-TEX CONSTRUCTION, LTD. (37.43)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.64)
STRIPING TECHNOLOGY, L.P. (1.16)
TEX OP CONSTRUCTION, LP (0.16)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13)
SCOTT DERR PAINTING CO, LLC (0.04)
STRIPING SYSTEMS, INC. (0.00)
Contract #08123015
Totals6855007.15434.386355139.9999.3

CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE (EB)
ToTITUS COUNTY LINE
CSJ0610-02-052
Proj IDNH 2016(100)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.7229114259.968561809.6193.9
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE (WB)
ToTITUS COUNTY LINE
CSJ0610-02-053
Proj IDNH 2016(100)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.7227316744.767077529.1796.7
Work Order10-22-15
Work Began03-02-16
Work Completed
Time Computed12-21-15
Contract Working Days223
Addl Days Granted0
Working Days Charged173
Percent Time Used77
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0610-02-052
A BROTHERS MILLING, LLC (2.54)
CDM HOLDINGS, LLC (7.36)
STRAIGHT LINE SAWING & SEALING (0.20)
TRP CONSTRUCTION GROUP, LLC (1.04)
ALTUS TRAFFIC MANAGEMENT LLC (0.15)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10)
MARTIN MARIETTA MATERIALS (POWDERLY) (0.00)
TEX OP CONSTRUCTION, LP (0.03)
JM YANEZ CONSTRUCTION (0.16)
Contract #09153003
Totals16431004.7212041.4915639338.7895.1

CountyHUNT
HighwaySH 276
From5.92 MILES EAST OF FM 751
To0.17 MILES EAST OF FM 513
CSJ0641-01-033
Proj IDC 641-1-33
Work TypeBRIDGE REPLACEMENT
 
2.80347845878.7148114885.2599.9
Work Order08-28-12
Work Began09-25-12
Work Completed
Time Computed02-25-13
Contract Working Days671
Addl Days Granted225
Working Days Charged893
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-01-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03)
SCOTT DERR PAINTING CO (0.58)
SAMMY G. SMALLWOOD (0.21)
NORTH TEXAS REBAR, LLC (7.04)
BAHENA CONSTRUCTION CO.,INC. (0.15)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
PEACHTREE CONSTRUCTION, LTD. (1.37)
INTERSTATE BARRICADES & MARKINGS, INC. (0.13)
BOWMAN ENGINEERING & CONSULTING, INC. (5.78)
ROADWAY CONSTRUCTION, LLC (0.82)
W.O.E. CONSTRUCTION (0.30)
Contract #07123202
Totals47845878.71149194.7348114885.2599.9

CountyHUNT
HighwayFM 36
FromIH 30
ToSH 276
CSJ0642-03-022
Proj IDSTP 1502(557)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
8.6302623426.372962708.1999.9
Work Order11-02-15
Work Began11-09-15
Work Completed
Time Computed01-01-16
Contract Working Days112
Addl Days Granted3
Working Days Charged120
Percent Time Used104
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0642-03-022
LYON BARRICADE AND CONSTRUCTION CO. (0.26)
TRP CONSTRUCTION GROUP, LLC (1.78)
WITHERS CONSTRUCTION, LLC (3.09)
MOORE CONSTRUCTION, INC. (2.19)
SAMMY SMALLWOOD COMPANY (0.91)
BAHENA CONSTRUCTION CO.,INC. (27.82)
GIST ENTERPRISES, INC. (5.98)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.53)
Contract #08153031
Totals2623426.3717096.552962708.1999.9

CountyLAMAR
HighwayFM 196
FromUS 271
ToFM 1501
CSJ0680-01-015
Proj IDSTP 2017(086)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.8062490743.37628975.7525.2
Work Order11-15-16
Work Began01-03-17
Work Completed
Time Computed12-15-16
Contract Working Days144
Addl Days Granted0
Working Days Charged35
Percent Time Used24
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-01-015
CATACON, INC. (1.92)
MOORE CONSTRUCTION, INC. (2.36)
SCOTT PAVING, INC. (17.51)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
Contract #09163221
Totals2490743.37599663.65628975.7525.2

CountyHOPKINS
HighwayFM 900
FromAT W GREENWOOD CREEK
To.
CSJ0680-05-008
Proj IDBR 0090(264)
Work TypeBRIDGE REPLACEMENT
 
0.2201570944.581556353.4999.0
Work Order04-20-15
Work Began06-24-15
Work Completed
Time Computed06-20-15
Contract Working Days270
Addl Days Granted0
Working Days Charged269
Percent Time Used99
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-008
N LINE TRAFFIC CONTROL (1.15)
SAMMY G. SMALLWOOD (6.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.21)
MESA ROD BUSTERS, INC. (0.32)
MOORE CONSTRUCTION, INC. (1.19)
STRIPING TECHNOLOGY, L.P. (0.80)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.05)
PENHALL COMPANY (0.20)
Contract #03153019
Totals1570944.58122972.451556353.4999.0

CountyHUNT
HighwayFM 1570
FromFM 2101
ToSH 34
CSJ0692-01-017
Proj IDSTP 2016(743)
Work TypeOVERLAY
 
5.9992207943.102340307.3699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-16
Work Began04-28-16
Work Completed
Time Computed00-00-00
Contract Working Days58
Addl Days Granted9
Working Days Charged58
Percent Time Used86
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0692-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.47)
J & M CONTRACTING, COMPANY (5.37)
DUSTROL, INC. (2.80)
SAMMY G. SMALLWOOD (3.73)
WOLFE CONSTRUCTION GROUP, INC. (0.41)
STRIPING TECHNOLOGY, L.P. (3.26)
STRIPING SYSTEMS, INC. (0.01)
Contract #02163218
Totals2207943.100.002340307.3699.9

CountyGRAYSON
HighwayFM 120
FromCENTER AVE
ToOKLAHOMA STATE LINE
CSJ0728-02-029
Proj IDSTP 1502(558)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.4862460214.081776083.3872.6
Work Order10-22-15
Work Began02-08-16
Work Completed
Time Computed12-21-15
Contract Working Days116
Addl Days Granted14
Working Days Charged143
Percent Time Used110
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0728-02-029
ALTUS TRAFFIC MANAGEMENT LLC (0.51)
SAMMY GIST ENTERPRISES, INC. (1.96)
BAHENA CONSTRUCTION CO.,INC. (19.32)
WIMMS ENVIRONMENTAL, INC. (0.73)
DUSTIN ALLEN, INC. (8.13)
TRP CONSTRUCTION GROUP, LLC (2.20)
MOORE CONSTRUCTION, INC. (1.78)
WITHERS CONSTRUCTION, LLC (4.14)
TEXANA LAND & ASPHALT, INC. (4.39)
Contract #08153225
Totals2460214.0824402.721776083.3872.6

CountyGRAYSON
HighwayFM 121
FromSH 289
To1200 FT WEST OF FM 3356
CSJ0729-01-037
Proj IDSTP 1502(559)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.9584609064.062927090.4163.5
Work Order01-29-16
Work Began03-16-16
Work Completed
Time Computed04-28-16
Contract Working Days272
Addl Days Granted0
Working Days Charged185
Percent Time Used68
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0729-01-037
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
STRIPING TECHNOLOGY, L.P. (2.18)
CATACON, INC. (1.41)
MOORE CONSTRUCTION, INC. (1.88)
LONE STAR BARRIER SERVICES, LLC (4.24)
BAHENA CONSTRUCTION CO.,INC. (15.72)
DUSTIN ALLEN, INC. (3.33)
MARCOM"S MOWING SERVICE, LLC (0.88)
STRIPING SYSTEMS, INC. (0.00)
Contract #10153228
Totals4609064.06267501.562927090.4163.5

CountyGRAYSON
HighwayFM 121
FromAT WEST FORK OF PILOT GROVE CREEK
To.
CSJ0729-02-026
Proj IDBR 1502(261)
Work TypeREPLACE BRIDGE
 
0.1931590415.601451684.4991.2
Work Order07-30-15
Work Began10-20-15
Work Completed
Time Computed08-31-15
Contract Working Days234
Addl Days Granted0
Working Days Charged234
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0729-02-026
ALTUS TRAFFIC MANAGEMENT LLC (1.30)
STRIPE-A-ZONE, INC. (1.56)
ODUM SERVICES, L.P. (2.63)
PENHALL COMPANY (0.22)
FOUNDATION DRILLERS, INC. (3.38)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.36)
W. W. FOUNDATION DRILLING, LTD. (4.13)
MOORE CONSTRUCTION, INC. (1.83)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.35)
Contract #06153031
Totals1590415.6064080.001451684.4991.2

CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-017
Proj IDSTP 2016(101)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.8151161897.121128191.0797.0
CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-020
Proj IDSTP 2016(102)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
3.819542959.77519647.3395.7
Work Order01-29-16
Work Began03-28-16
Work Completed
Time Computed03-29-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0735-05-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
MOORE CONSTRUCTION, INC. (3.73)
STRIPING TECHNOLOGY, L.P. (2.49)
CATACON, INC. (1.45)
SCOTT PAVING, INC. (24.79)
SAMMY G. SMALLWOOD (1.27)
STRIPING SYSTEMS, INC. (0.05)
Contract #09153218
Totals1704856.894838.001647838.4096.6

CountyHUNT
HighwayFM 272
FromUS 69
ToFM 816
CSJ0764-02-011
Proj IDC 764-2-11
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0883455817.181563254.8645.2
Work Order09-20-16
Work Began10-07-16
Work Completed
Time Computed10-20-16
Contract Working Days202
Addl Days Granted0
Working Days Charged69
Percent Time Used34
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0764-02-011
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
STRIPING TECHNOLOGY, L.P. (1.47)
CATOCON, INC. (2.46)
MOORE CONSTRUCTION, INC. (3.34)
SAMMY SMALLWOOD COMPANY (4.09)
BAHENA CONSTRUCTION CO.,INC. (8.01)
MURRAY CONSTRUCTION (1.38)
DUSTROL, INC. (0.33)
Contract #07163021
Totals3455817.18365858.211563254.8645.2

page 1 | page 2 | page 3