Monthly State Let Construction Report For Paris District As Of Nov 9, 2016 Page 2 Of 3

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFRANKLIN
Highway SH 37
From FM 21
To WOOD C/L
CSJ 0190-01-021
Proj ID NH 1502(556)
Work Type RECONST & ADD 10' SHLDRS
 
13.258 20387243.98 477685.30 5978373.30 29.3
Work Order 03-08-16
Work Began 03-23-16
Work Completed  
Time Computed 06-06-16
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 26
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-01-021
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18%)
BAHENA CONSTRUCTION CO.,INC. (1.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.99%)
MORRIS COUNTY CONTRACTORS, L.L.C.(0.33%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.74%)
STRIPING TECHNOLOGY, L.P.(1.18%)
TX TINMAN ENTERPRISES, LLC.(1.85%)
WOLFE CONSTRUCTION GROUP, INC. (0.57%)
KLP COMMERCIAL, LLC(0.00%)
MESA ROD BUSTERS, INC. (0.04%)
DFW REBAR, INC.(0.02%)
Contract # 01163001
Totals 20387243.98 477685.30 5978373.30 29.3

CountyRAINS
Highway US 69
From SH 19
To 586 NORTH OF FM 3299 INTERSECTION
CSJ 0203-03-044
Proj ID STP 1402(093)
Work Type MISCELLANEOUS CONSTRUCTION
 
3.240 4635055.96 6045.15 4394268.13 95.3
Work Order 11-12-14
Work Began 02-26-15
Work Completed  
Time Computed 02-10-15
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 115
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0203-03-044
ALTUS TRAFFIC MANAGEMENT LLC (0.27%)
BAHENA CONSTRUCTION CO.,INC. ( 13.11%)
MOORE CONSTRUCTION, INC. (0.76%)
RK HALL, LLC ( 38.07%)
SAMMY G. SMALLWOOD (0.30%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.69%)
TEX OP CONSTRUCTION, LP(0.35%)
WITHERS CONSTRUCTION, LLC(0.37%)
STRIPING TECHNOLOGY, L.P.(0.77%)
Contract # 09143209
Totals 4635055.96 6045.15 4394268.13 95.3

CountyFANNIN
Highway SH 78
From SH 11
To 0.68 MI S OF SH 56
CSJ 0279-03-035
Proj ID STP 2017(188)HES
Work Type HAZARD ELIMINATION & SAFETY
 
23.870 2675061.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0279-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163212
Totals 2675061.25 0.00 0.00 0.0

CountyHOPKINS
Highway SH 19
From DELTA COUNTY LINE
To LOOP 301
CSJ 0400-02-048
Proj ID STP 1502(137)
Work Type OVERLAY
 
12.204 1267814.14 0.00 1359457.94 99.9
Work Order 06-15-15
Work Began 08-24-15
Work Completed  
Time Computed 07-16-15
Contract Working Days 48
Addl Days Granted 18
Working Days Charged 62
Percent Time Used 93
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0400-02-048
FLEX SUPPLY, LLC (0.60%)
JOHN MILLSAP (5.23%)
STRIPING TECHNOLOGY, L.P.(6.43%)
WEST TEXAS RUMBLE STRIP(0.81%)
Contract # 05153032
Totals 1267814.14 0.00 1359457.94 99.9

CountyHOPKINS
Highway SH 154
From 0.315 MILES NORTH OF FM 1567 EAST
To 0.195 MILES SOUTH OF CR 1104
CSJ 0401-01-022
Proj ID STP 2013(464)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
4.973 6591501.99 149646.03 8105965.58 99.9
Work Order 05-13-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 451
Percent Time Used 98
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-01-022
PANOLA SIGN & BARRICADE, INC.(0.54%)
BAHENA CONSTRUCTION CO.,INC. (9.56%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
FORTSON CONTRACTING, INC.(4.14%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MOORE CONSTRUCTION, INC. (0.57%)
TEXANA LAND & ASPHALT, INC.(0.57%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. ( 27.89%)
Contract # 03133219
Totals 6591501.99 149646.03 8105965.58 99.9

CountyRED RIVER
Highway FM 44
From FM 412
To FM 911
CSJ 0427-01-037
Proj ID STP 2016(363)
Work Type REHABILITATION OF EXISTING ROAD
 
10.363 4617291.24 336856.67 2481074.85 53.7
Work Order 03-15-16
Work Began 04-25-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 222
Addl Days Granted 4
Working Days Charged 116
Percent Time Used 51
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0427-01-037
HIGHWAY 19 CONSTRUCTION, LLC (1.62%)
LYON BARRICADE AND CONSTRUCTION CO.(0.52%)
WITHERS CONSTRUCTION, LLC(2.23%)
MOORE CONSTRUCTION CO. (2.98%)
SAMMY SMALLWOOD COMPANY(2.37%)
BAHENA CONSTRUCTION CO.,INC. ( 11.37%)
TEX OP CONSTRUCTION, LP(0.15%)
STRIPING TECHNOLOGY, L.P.(1.84%)
STRIPING SYSTEMS, INC. (0.02%)
MOORE CONSTRUCTION, INC. (2.98%)
Contract # 02163241
Totals 4617291.24 336856.67 2481074.85 53.7

CountyLAMAR
Highway FM 137
From FM 38
To US 82
CSJ 0435-01-068
Proj ID STP 2016(099)
Work Type REHABILITATION OF EXISTING ROAD
 
8.998 3768340.10 111889.55 3444312.07 91.5
Work Order 11-13-15
Work Began 12-09-15
Work Completed  
Time Computed 01-12-16
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 102
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-068
N-LINE TRAFFIC MAINTENANCE, L.P. (0.72%)
STRIPING TECHNOLOGY, L.P.(3.34%)
CATOCON, INC.(1.79%)
MOORE CONSTRUCTION, INC. (1.99%)
SAMMY SMALLWOOD COMPANY(4.58%)
BAHENA CONSTRUCTION CO.,INC. (1.46%)
MURRAY CONSTRUCTION(1.48%)
ACU CONSTRUCTION LLC (0.65%)
ANCHOR CONTRACTING, LLC(0.43%)
MORRIS COUNTY CONTRACTORS, L.L.C.(1.49%)
Contract # 09153025
Totals 3768340.10 111889.55 3444312.07 91.5

CountyGRAYSON
Highway FM 902
From US 377
To SH 289
CSJ 0510-01-026
Proj ID STP 2015(309)
Work Type REHABILITATION OF EXISTING ROAD
 
14.427 7337375.52 320357.71 5290514.49 72.2
Work Order 01-02-15
Work Began 09-28-15
Work Completed  
Time Computed 04-02-15
Contract Working Days 304
Addl Days Granted 0
Working Days Charged 313
Percent Time Used 102
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05%)
CATOCON, INC.(1.83%)
FARR FOUNDATION, INC.(4.74%)
LYON BARRICADE AND CONSTRUCTION CO.(0.46%)
MURRAY CONSTRUCTION(1.26%)
SAMMY G. SMALLWOOD (1.75%)
STRIPING TECHNOLOGY, L.P.(1.54%)
TEXANA LAND & ASPHALT, INC.(2.35%)
BAHENA CONSTRUCTION CO.,INC. ( 14.62%)
MOORE CONSTRUCTION, INC. (1.15%)
Contract # 11143220
Totals 7337375.52 320357.71 5290514.49 72.2

CountyDELTA
Highway SH 19 ETC
From @ BRUSHY CREEK
To .
CSJ 0525-01-020
Proj ID BR 1502(141)
Work Type BRIDGE REPLACEMENT
 
0.678 4018602.90 251346.61 3490672.63 86.8
Work Order 06-30-15
Work Began 09-22-15
Work Completed  
Time Computed 08-30-15
Contract Working Days 348
Addl Days Granted 0
Working Days Charged 208
Percent Time Used 59
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
PANOLA SIGN & BARRICADE, INC.(0.71%)
MOORE CONSTRUCTION, INC. (1.43%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (4.08%)
DUSTIN ALLEN, INC. (3.15%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.02%)
STRIPING TECHNOLOGY, L.P.(1.08%)
PENHALL COMPANY(0.23%)
TEX OP CONSTRUCTION, LP(0.62%)
WITHERS CONSTRUCTION, LLC(0.79%)
MCL CONTRACTING, LLC (0.30%)
Contract # 05153217
Totals 4018602.90 251346.61 3490672.63 86.8

CountyFANNIN
Highway SH 121
From US 82
To SH 56
CSJ 0549-01-029
Proj ID STP 2012(575)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
1.863 6855007.15 16881.67 5851385.66 91.2
Work Order 10-18-12
Work Began 03-11-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 284
Addl Days Granted 36
Working Days Charged 680
Percent Time Used 212
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. ( 12.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70%)
NE-TEX CONSTRUCTION, LTD.( 37.43%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.64%)
STRIPING TECHNOLOGY, L.P.(1.13%)
TEX OP CONSTRUCTION, LP(0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13%)
SCOTT DERR PAINTING CO, LLC(0.04%)
Contract # 08123015
Totals 6855007.15 16881.67 5851385.66 91.2

CountyFRANKLIN
Highway IH 30
From HOPKINS COUNTY LINE (EB)
To TITUS COUNTY LINE
CSJ 0610-02-052
Proj ID NH 2016(100)
Work Type REHABILITATION OF EXISTING ROAD
 
10.722 9114259.96 82001.34 8360512.74 91.7
CountyFRANKLIN
Highway IH 30
From HOPKINS COUNTY LINE (WB)
To TITUS COUNTY LINE
CSJ 0610-02-053
Proj ID NH 2016(100)
Work Type REHABILITATION OF EXISTING ROAD
 
10.722 7316744.76 1444395.40 6842124.30 93.5
Work Order 10-22-15
Work Began 03-02-16
Work Completed  
Time Computed 12-21-15
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 65
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0610-02-052
A BROTHERS MILLING, LLC(2.54%)
CDM HOLDINGS, LLC(7.36%)
STRAIGHT LINE SAWING & SEALING (0.20%)
TRP CONSTRUCTION GROUP, LLC(1.04%)
ALTUS TRAFFIC MANAGEMENT LLC (0.15%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10%)
MARTIN MARIETTA MATERIALS (POWDERLY) (0.00%)
J.M. YANEZ CONSTRUCTION(0.00%)
TEX OP CONSTRUCTION, LP(0.03%)
Contract # 09153003
Totals 16431004.72 1526396.74 15202637.04 92.5

CountyHUNT
Highway SH 276
From 5.92 MILES EAST OF FM 751
To 0.17 MILES EAST OF FM 513
CSJ 0641-01-033
Proj ID C 641-1-33
Work Type BRIDGE REPLACEMENT
 
2.803 47845878.71 446121.90 46356302.68 96.8
Work Order 08-28-12
Work Began 09-25-12
Work Completed  
Time Computed 02-25-13
Contract Working Days 671
Addl Days Granted 225
Working Days Charged 818
Percent Time Used 91
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-01-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03%)
SCOTT DERR PAINTING CO (0.58%)
SAMMY G. SMALLWOOD (0.21%)
NORTH TEXAS REBAR, LLC (7.04%)
BAHENA CONSTRUCTION CO.,INC. (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
PEACHTREE CONSTRUCTION, LTD. (1.37%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.13%)
BOWMAN ENGINEERING & CONSULTING, INC.(5.78%)
ROADWAY CONSTRUCTION, LLC(0.82%)
W.O.E. CONSTRUCTION(0.30%)
Contract # 07123202
Totals 47845878.71 446121.90 46356302.68 96.8

CountyHUNT
Highway FM 36
From IH 30
To SH 276
CSJ 0642-03-022
Proj ID STP 1502(557)HES
Work Type HAZARD ELIMINATION & SAFETY
 
8.630 2623426.37 0.00 2851724.70 99.9
Work Order 11-02-15
Work Began 11-09-15
Work Completed  
Time Computed 01-01-16
Contract Working Days 112
Addl Days Granted 3
Working Days Charged 120
Percent Time Used 104
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0642-03-022
LYON BARRICADE AND CONSTRUCTION CO.(0.26%)
TRP CONSTRUCTION GROUP, LLC(1.78%)
WITHERS CONSTRUCTION, LLC(3.09%)
MOORE CONSTRUCTION, INC. (2.19%)
SAMMY SMALLWOOD COMPANY(0.91%)
BAHENA CONSTRUCTION CO.,INC. ( 27.82%)
GIST ENTERPRISES, INC. (5.98%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.53%)
Contract # 08153031
Totals 2623426.37 0.00 2851724.70 99.9

CountyLAMAR
Highway FM 196
From US 271
To FM 1501
CSJ 0680-01-015
Proj ID STP 2017(086)
Work Type REHABILITATION OF EXISTING ROAD
 
4.806 2490743.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 144
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163221
Totals 2490743.37 0.00 0.00 0.0

CountyHOPKINS
Highway FM 900
From AT W GREENWOOD CREEK
To .
CSJ 0680-05-008
Proj ID BR 0090(264)
Work Type BRIDGE REPLACEMENT
 
0.220 1570944.58 182640.00 900112.34 57.2
Work Order 04-20-15
Work Began 06-24-15
Work Completed  
Time Computed 06-20-15
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 229
Percent Time Used 84
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-008
N LINE TRAFFIC CONTROL (1.15%)
SAMMY G. SMALLWOOD (6.27%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.21%)
MESA ROD BUSTERS, INC. (0.32%)
MOORE CONSTRUCTION, INC. (1.19%)
STRIPING TECHNOLOGY, L.P.(0.80%)
Contract # 03153019
Totals 1570944.58 182640.00 900112.34 57.2

CountyLAMAR
Highway FM 1497 ETC
From AT CANEY CREEK
To .
CSJ 0688-03-023
Proj ID BR 2014(202)
Work Type BRIDGE REPLACEMENT
 
0.585 2196575.03 0.00 1891039.88 86.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 03-18-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 381
Addl Days Granted 0
Working Days Charged 394
Percent Time Used 103
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0688-03-023
SOUTHWEST ENVIRONMENT SERVICES LLC (1.42%)
SAMMY G. SMALLWOOD (3.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.06%)
TEX OP CONSTRUCTION, LP(0.73%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.54%)
ACTION SERVICES(0.33%)
SOTO"S STEEL (0.31%)
PENHALL COMPANY(0.18%)
FRITCHER CONSTRUCTION SERVICES (1.60%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (0.85%)
SCOTT PAVING, INC. (1.04%)
MCL CONTRACTING, LLC (0.36%)
Contract # 11133009
Totals 2196575.03 0.00 1891039.88 86.5

CountyHUNT
Highway FM 1570
From FM 2101
To SH 34
CSJ 0692-01-017
Proj ID STP 2016(743)
Work Type OVERLAY
 
5.999 2207943.10 0.00 2319763.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-16
Work Began 04-28-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 58
Addl Days Granted 9
Working Days Charged 58
Percent Time Used 86
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0692-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.47%)
J & M CONTRACTING, COMPANY (5.37%)
DUSTROL, INC.(2.80%)
SAMMY G. SMALLWOOD (3.73%)
WOLFE CONSTRUCTION GROUP, INC. (0.41%)
STRIPING TECHNOLOGY, L.P.(3.26%)
STRIPING SYSTEMS, INC. (0.01%)
Contract # 02163218
Totals 2207943.10 0.00 2319763.24 99.9

CountyGRAYSON
Highway SH 91
From AT SHAWNEE CREEK
To .
CSJ 0705-01-027
Proj ID ER 2016(253)
Work Type EMERGENCY RELIEF PROJECT
 
0.282 1734743.20 15384.60 1708247.11 98.5
Work Order 02-16-16
Work Began 03-17-16
Work Completed  
Time Computed 03-17-16
Contract Working Days 71
Addl Days Granted 4
Working Days Charged 76
Percent Time Used 101
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0705-01-027
MORRIS COUNTY CONTRACTORS, L.L.C.(3.53%)
HOUSTON SAWING & DRILLING(0.22%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.14%)
STRIPING TECHNOLOGY, L.P.(0.44%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.19%)
PEACHTREE CONSTRUCTION, LTD. (5.68%)
TEXOP CONSTRUCTION (0.34%)
Contract # 12153045
Totals 1734743.20 15384.60 1708247.11 98.5

CountyGRAYSON
Highway FM 120
From CENTER AVE
To OKLAHOMA STATE LINE
CSJ 0728-02-029
Proj ID STP 1502(558)HES
Work Type HAZARD ELIMINATION & SAFETY
 
6.486 2460214.08 253069.89 1546443.29 62.8
Work Order 10-22-15
Work Began 02-08-16
Work Completed  
Time Computed 12-21-15
Contract Working Days 116
Addl Days Granted 14
Working Days Charged 128
Percent Time Used 98
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0728-02-029
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
SAMMY GIST ENTERPRISES, INC. (1.96%)
BAHENA CONSTRUCTION CO.,INC. ( 19.32%)
WIMMS ENVIRONMENTAL, INC.(0.73%)
DUSTIN ALLEN, INC. (8.13%)
TRP CONSTRUCTION GROUP, LLC(2.20%)
MOORE CONSTRUCTION, INC. (1.78%)
WITHERS CONSTRUCTION, LLC(4.14%)
TEXANA LAND & ASPHALT, INC.(4.39%)
Contract # 08153225
Totals 2460214.08 253069.89 1546443.29 62.8

CountyGRAYSON
Highway FM 121
From SH 289
To 1200 FT WEST OF FM 3356
CSJ 0729-01-037
Proj ID STP 1502(559)HES
Work Type HAZARD ELIMINATION & SAFETY
 
6.958 4609064.06 19840.00 2129429.32 46.2
Work Order 01-29-16
Work Began 03-16-16
Work Completed  
Time Computed 04-28-16
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 47
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0729-01-037
TOTAL HIGHWAY MAINTENANCE, LLC (0.49%)
STRIPING TECHNOLOGY, L.P.(2.18%)
CATACON, INC.(1.41%)
MOORE CONSTRUCTION, INC. (1.88%)
LONE STAR BARRIER SERVICES, LLC(4.24%)
BAHENA CONSTRUCTION CO.,INC. ( 15.72%)
STRIPING SYSTEMS, INC. (0.00%)
Contract # 10153228
Totals 4609064.06 19840.00 2129429.32 46.2

page 1 | page 2 | page 3