Monthly State Let Construction Report For Paris District As Of Jun 12, 2017 Page 2 Of 3

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFANNIN
HighwaySH 78
FromSH 11
To0.68 MI S OF SH 56
CSJ0279-03-035
Proj IDSTP 2017(188)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
23.8702675061.25577938.2621.6
Work Order12-06-16
Work Began01-09-17
Work Completed
Time Computed02-01-17
Contract Working Days159
Addl Days Granted0
Working Days Charged47
Percent Time Used29
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0279-03-035
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.76)
WITHERS CONSTRUCTION, LLC (1.32)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (13.21)
Contract #10163212
Totals2675061.2563086.88577938.2621.6

CountyRED RIVER
HighwayFM 44
FromFM 412
ToFM 911
CSJ0427-01-037
Proj IDSTP 2016(363)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.3634617291.243135691.4467.9
Work Order03-15-16
Work Began04-25-16
Work Completed
Time Computed05-16-16
Contract Working Days222
Addl Days Granted4
Working Days Charged211
Percent Time Used93
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0427-01-037
HIGHWAY 19 CONSTRUCTION, LLC (1.62)
LYON BARRICADE AND CONSTRUCTION CO. (0.52)
WITHERS CONSTRUCTION, LLC (2.23)
MOORE CONSTRUCTION CO. (2.98)
SAMMY SMALLWOOD COMPANY (2.37)
BAHENA CONSTRUCTION CO.,INC. (11.37)
TEX OP CONSTRUCTION, LP (0.15)
STRIPING TECHNOLOGY, L.P. (1.84)
STRIPING SYSTEMS, INC. (0.02)
MOORE CONSTRUCTION, INC. (2.98)
Contract #02163241
Totals4617291.24122036.873135691.4467.9

CountyLAMAR
HighwayFM 137
FromFM 38
ToUS 82
CSJ0435-01-068
Proj IDSTP 2016(099)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.9983768340.103454266.6892.0
Work Order11-13-15
Work Began12-09-15
Work Completed
Time Computed01-12-16
Contract Working Days171
Addl Days Granted0
Working Days Charged187
Percent Time Used109
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-068
N-LINE TRAFFIC MAINTENANCE, L.P. (0.72)
STRIPING TECHNOLOGY, L.P. (3.34)
CATOCON, INC. (1.79)
MOORE CONSTRUCTION, INC. (1.99)
SAMMY SMALLWOOD COMPANY (4.58)
BAHENA CONSTRUCTION CO.,INC. (1.46)
MURRAY CONSTRUCTION (1.48)
ACU CONSTRUCTION LLC (0.65)
ANCHOR CONTRACTING, LLC (0.43)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.49)
Contract #09153025
Totals3768340.103631.483454266.6892.0

CountyGRAYSON
HighwayFM 902
FromUS 377
ToSH 289
CSJ0510-01-026
Proj IDSTP 2015(309)
Work TypeREHABILITATION OF EXISTING ROAD
 
14.4277337375.525874575.5780.4
Work Order01-02-15
Work Began09-28-15
Work Completed
Time Computed04-02-15
Contract Working Days304
Addl Days Granted0
Working Days Charged329
Percent Time Used108
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05)
CATOCON, INC. (1.83)
FARR FOUNDATION, INC. (4.74)
LYON BARRICADE AND CONSTRUCTION CO. (0.46)
MURRAY CONSTRUCTION (1.26)
SAMMY G. SMALLWOOD (1.75)
STRIPING TECHNOLOGY, L.P. (1.54)
TEXANA LAND & ASPHALT, INC. (2.35)
BAHENA CONSTRUCTION CO.,INC. (14.62)
MOORE CONSTRUCTION, INC. (1.15)
Contract #11143220
Totals7337375.52209205.305874575.5780.4

CountyDELTA ETC
HighwaySH 19 ETC
From@ BRUSHY CREEK
To.
CSJ0525-01-020
Proj IDBR 1502(141)
Work TypeBRIDGE REPLACEMENT
 
0.6784018602.903823311.9695.1
Work Order06-30-15
Work Began09-22-15
Work Completed
Time Computed08-30-15
Contract Working Days348
Addl Days Granted0
Working Days Charged302
Percent Time Used86
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
PANOLA SIGN & BARRICADE, INC. (0.71)
MOORE CONSTRUCTION, INC. (1.43)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (4.08)
DUSTIN ALLEN, INC. (3.15)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.02)
STRIPING TECHNOLOGY, L.P. (1.08)
PENHALL COMPANY (0.23)
TEX OP CONSTRUCTION, LP (0.62)
WITHERS CONSTRUCTION, LLC (0.79)
MCL CONTRACTING, LLC (0.30)
STRIPING SYSTEMS, INC. (0.00)
Contract #05153217
Totals4018602.900.003823311.9695.1

CountyFANNIN
HighwaySH 121
FromUS 82
ToSH 56
CSJ0549-01-029
Proj IDSTP 2012(575)
Work TypeUPGRADE TO NON-FREEWAY STANDARDS
 
1.8636855007.156407914.3399.9
Work Order10-18-12
Work Began03-11-13
Work Completed
Time Computed04-22-13
Contract Working Days284
Addl Days Granted36
Working Days Charged725
Percent Time Used226
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. (12.83)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70)
NE-TEX CONSTRUCTION, LTD. (37.43)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.64)
STRIPING TECHNOLOGY, L.P. (1.16)
TEX OP CONSTRUCTION, LP (0.16)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13)
SCOTT DERR PAINTING CO, LLC (0.04)
STRIPING SYSTEMS, INC. (0.00)
Contract #08123015
Totals6855007.152441.726407914.3399.9

CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE (EB)
ToTITUS COUNTY LINE
CSJ0610-02-052
Proj IDNH 2016(100)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.7229114259.968736426.4695.8
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE (WB)
ToTITUS COUNTY LINE
CSJ0610-02-053
Proj IDNH 2016(100)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.7227316744.767077529.1796.7
Work Order10-22-15
Work Began03-02-16
Work Completed
Time Computed12-21-15
Contract Working Days223
Addl Days Granted0
Working Days Charged173
Percent Time Used77
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0610-02-052
A BROTHERS MILLING, LLC (2.54)
CDM HOLDINGS, LLC (7.36)
STRAIGHT LINE SAWING & SEALING (0.20)
TRP CONSTRUCTION GROUP, LLC (1.04)
ALTUS TRAFFIC MANAGEMENT LLC (0.15)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10)
MARTIN MARIETTA MATERIALS (POWDERLY) (0.00)
TEX OP CONSTRUCTION, LP (0.03)
JM YANEZ CONSTRUCTION (0.16)
Contract #09153003
Totals16431004.72115010.0015813955.6396.2

CountyHUNT
HighwayFM 36
FromIH 30
ToSH 276
CSJ0642-03-022
Proj IDSTP 1502(557)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
8.6302623426.372962708.1999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-02-15
Work Began11-09-15
Work Completed
Time Computed01-01-16
Contract Working Days112
Addl Days Granted3
Working Days Charged120
Percent Time Used104
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0642-03-022
LYON BARRICADE AND CONSTRUCTION CO. (0.26)
TRP CONSTRUCTION GROUP, LLC (1.78)
WITHERS CONSTRUCTION, LLC (3.09)
MOORE CONSTRUCTION, INC. (2.19)
SAMMY SMALLWOOD COMPANY (0.91)
BAHENA CONSTRUCTION CO.,INC. (27.82)
GIST ENTERPRISES, INC. (5.98)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.53)
Contract #08153031
Totals2623426.370.002962708.1999.9

CountyLAMAR
HighwayFM 196
FromUS 271
ToFM 1501
CSJ0680-01-015
Proj IDSTP 2017(086)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.8062490743.371395387.8456.0
Work Order11-15-16
Work Began01-03-17
Work Completed
Time Computed12-15-16
Contract Working Days144
Addl Days Granted0
Working Days Charged85
Percent Time Used59
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-01-015
CATACON, INC. (1.92)
MOORE CONSTRUCTION, INC. (2.36)
SCOTT PAVING, INC. (17.51)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
SOUTHERN CROSS CONTRACTORS, LLC (2.24)
Contract #09163221
Totals2490743.37425597.221395387.8456.0

CountyHOPKINS
HighwayFM 900
FromAT W GREENWOOD CREEK
To.
CSJ0680-05-008
Proj IDBR 0090(264)
Work TypeBRIDGE REPLACEMENT
 
0.2201570944.581566122.5899.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-20-15
Work Began06-24-15
Work Completed
Time Computed06-20-15
Contract Working Days270
Addl Days Granted0
Working Days Charged272
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-008
N LINE TRAFFIC CONTROL (1.15)
SAMMY G. SMALLWOOD (6.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.21)
MESA ROD BUSTERS, INC. (0.32)
MOORE CONSTRUCTION, INC. (1.19)
STRIPING TECHNOLOGY, L.P. (0.80)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.05)
PENHALL COMPANY (0.20)
Contract #03153019
Totals1570944.580.001566122.5899.7

CountyGRAYSON
HighwayFM 120
FromCENTER AVE
ToOKLAHOMA STATE LINE
CSJ0728-02-029
Proj IDSTP 1502(558)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.4862460214.081796603.3873.4
Work Order10-22-15
Work Began02-08-16
Work Completed
Time Computed12-21-15
Contract Working Days116
Addl Days Granted14
Working Days Charged143
Percent Time Used110
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0728-02-029
ALTUS TRAFFIC MANAGEMENT LLC (0.51)
SAMMY GIST ENTERPRISES, INC. (1.96)
BAHENA CONSTRUCTION CO.,INC. (19.32)
WIMMS ENVIRONMENTAL, INC. (0.73)
DUSTIN ALLEN, INC. (8.13)
TRP CONSTRUCTION GROUP, LLC (2.20)
MOORE CONSTRUCTION, INC. (1.78)
WITHERS CONSTRUCTION, LLC (4.14)
TEXANA LAND & ASPHALT, INC. (4.39)
Contract #08153225
Totals2460214.080.001796603.3873.4

CountyGRAYSON
HighwayFM 121
FromSH 289
To1200 FT WEST OF FM 3356
CSJ0729-01-037
Proj IDSTP 1502(559)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.9584609064.063468380.5575.2
Work Order01-29-16
Work Began03-16-16
Work Completed
Time Computed04-28-16
Contract Working Days272
Addl Days Granted0
Working Days Charged234
Percent Time Used86
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0729-01-037
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
STRIPING TECHNOLOGY, L.P. (2.18)
CATACON, INC. (1.41)
MOORE CONSTRUCTION, INC. (1.88)
LONE STAR BARRIER SERVICES, LLC (4.24)
BAHENA CONSTRUCTION CO.,INC. (15.72)
DUSTIN ALLEN, INC. (3.33)
MARCOM"S MOWING SERVICE, LLC (0.88)
STRIPING SYSTEMS, INC. (0.00)
Contract #10153228
Totals4609064.06212868.363468380.5575.2

CountyGRAYSON
HighwayFM 121
FromAT WEST FORK OF PILOT GROVE CREEK
To.
CSJ0729-02-026
Proj IDBR 1502(261)
Work TypeREPLACE BRIDGE
 
0.1931590415.601547322.4997.7
Work Order07-30-15
Work Began10-20-15
Work Completed
Time Computed08-31-15
Contract Working Days234
Addl Days Granted0
Working Days Charged243
Percent Time Used103
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0729-02-026
ALTUS TRAFFIC MANAGEMENT LLC (1.30)
STRIPE-A-ZONE, INC. (1.56)
ODUM SERVICES, L.P. (2.63)
PENHALL COMPANY (0.22)
FOUNDATION DRILLERS, INC. (3.38)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.36)
W. W. FOUNDATION DRILLING, LTD. (4.13)
MOORE CONSTRUCTION, INC. (1.83)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.35)
Contract #06153031
Totals1590415.607690.001547322.4997.7

CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-017
Proj IDSTP 2016(101)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.8151161897.121135191.0797.7
CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-020
Proj IDSTP 2016(102)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
3.819542959.77519647.3395.7
Work Order01-29-16
Work Began03-28-16
Work Completed
Time Computed03-29-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0735-05-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
MOORE CONSTRUCTION, INC. (3.73)
STRIPING TECHNOLOGY, L.P. (2.49)
CATACON, INC. (1.45)
SCOTT PAVING, INC. (24.79)
SAMMY G. SMALLWOOD (1.27)
STRIPING SYSTEMS, INC. (0.05)
Contract #09153218
Totals1704856.897000.001654838.4097.0

CountyHUNT
HighwayFM 272
FromUS 69
ToFM 816
CSJ0764-02-011
Proj IDC 764-2-11
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0883455817.182301046.9766.5
Work Order09-20-16
Work Began10-07-16
Work Completed
Time Computed10-20-16
Contract Working Days202
Addl Days Granted0
Working Days Charged115
Percent Time Used56
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0764-02-011
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
STRIPING TECHNOLOGY, L.P. (1.47)
CATOCON, INC. (2.46)
MOORE CONSTRUCTION, INC. (3.34)
SAMMY SMALLWOOD COMPANY (4.09)
BAHENA CONSTRUCTION CO.,INC. (8.01)
MURRAY CONSTRUCTION (1.38)
DUSTROL, INC. (0.33)
Contract #07163021
Totals3455817.1885477.992301046.9766.5

CountyLAMAR
HighwayFM 906
FromCR 45030
ToCR 47400
CSJ0769-02-028
Proj IDSTP 2016(189)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.6554368067.411701034.2738.9
CountyLAMAR
HighwayFM 906
FromFM 197
ToUS 271
CSJ0769-02-030
Proj IDSTP 2016(190)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
4.4541549596.88695394.3744.8
Work Order06-23-16
Work Began09-21-16
Work Completed
Time Computed07-25-16
Contract Working Days345
Addl Days Granted4
Working Days Charged145
Percent Time Used41
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0769-02-028
BAHENA CONSTRUCTION CO.,INC. (8.62)
DUSTIN ALLEN, INC. (6.76)
MOORE CONSTRUCTION, INC. (1.89)
RK HALL, LLC (13.56)
STRIPING TECHNOLOGY, L.P. (2.46)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
WITHERS CONSTRUCTION, LLC (2.12)
LYON BARRICADE AND CONSTRUCTION CO. (0.56)
TEXOP CONSTRUCTION (1.20)
SAMMY GIST ENTERPRISES, INC. (0.31)
Contract #01163215
Totals5917664.29308362.712396428.6440.4

CountyRED RIVER
HighwayFM 412
FromFM 1487
ToFM 44
CSJ0773-01-018
Proj IDSTP 1602(357)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.3782784332.411646883.6859.1
CountyRED RIVER
HighwayFM 412
From0.97 MI SW OF INTERSECTION FM 44
To.
CSJ0773-01-019
Proj IDER 2016(876)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.092100550.0090350.0089.8
Work Order09-15-16
Work Began10-11-16
Work Completed
Time Computed10-20-16
Contract Working Days162
Addl Days Granted6
Working Days Charged98
Percent Time Used58
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0773-01-018
CHEROKEE SERVICES (0.29)
DUSTIN ALLEN, INC. (4.73)
HIGHWAY 19 CONSTRUCTION, LLC (12.35)
MOORE CONSTRUCTION, INC. (4.07)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
TOTAL HIGHWAY MAINTENANCE, LLC (1.88)
WITHERS CONSTRUCTION, LLC (2.74)
SAMMY SMALLWOOD COMPANY (0.79)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.86)
Contract #07163027
Totals2884882.41250031.191737233.6860.2

CountyGRAYSON
HighwayCR
FromCR 202-2
ToAT ELBA CREEK
CSJ0901-19-182
Proj IDBR 2016(436)
Work TypeBRIDGE REPLACEMENT
 
0.197931194.17815747.8187.6
Work Order08-08-16
Work Began09-09-16
Work Completed
Time Computed09-07-16
Contract Working Days125
Addl Days Granted0
Working Days Charged112
Percent Time Used89
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-182
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
PENHALL COMPANY (0.64)
WOLFE CONSTRUCTION GROUP, INC. (0.46)
W. W. FOUNDATION DRILLING, LTD. (6.78)
ODUM SERVICES, L.P. (5.31)
Contract #06163029
Totals931194.17138634.94815747.8187.6

CountyHUNT
HighwayCR
FromCR 137-1
ToCOWLEECH FORK SABINE RIVER
CSJ0901-22-107
Proj IDBR 2015(643)
Work TypeBRIDGE REPLACEMENT
 
0.113520226.20499091.6595.9
Work Order11-29-16
Work Began01-03-17
Work Completed
Time Computed12-29-16
Contract Working Days122
Addl Days Granted0
Working Days Charged71
Percent Time Used58
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-107
WOLFE CONSTRUCTION GROUP, INC. (0.76)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.68)
DFW REBAR, INC. (0.31)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.75)
PANOLA SIGN & BARRICADE, INC. (1.71)
ISAACS CONSTRUCTION SERVICES, LLC. (2.25)
Contract #09163018
Totals520226.204839.20499091.6595.9

CountyRED RIVER
HighwayCS
FromON PECAN STREET IN CLARKSVILLE
To@ DELAWARE CREEK
CSJ0901-27-029
Proj IDBR 2008(634)
Work TypeBRIDGE REPLACEMENT
 
0.1711506400.301547882.8099.9
Work Order03-16-16
Work Began04-14-16
Work Completed
Time Computed04-15-16
Contract Working Days190
Addl Days Granted0
Working Days Charged204
Percent Time Used107
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-27-029
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.15)
BLASTCO TEXAS INC. (6.29)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.44)
Contract #01163036
Totals1506400.3017801.501547882.8099.9

page 1 | page 2 | page 3