Monthly State Let Construction Report For Paris District As Of May 15, 2013 Page 2 Of 3

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGRAYSON
Highway FM 1417
From REFUGE ROAD
To 1.0 MILE SOUTH OF REFUGE RD
CSJ 0202-08-057
Proj ID STP 2013(332)
Work Type MISCELLANEOUS CONSTRUCTION
 
1.000 359999.95 88912.23 88912.23 24.6
Work Order 03-22-13
Work Began 00-00-00
Work Completed  
Time Computed 05-21-13
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 15
Contractor(s)
BILLY CUMMINGS CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0202-08-057
MOORE CONSTRUCTION, INC. (3.28%)
TEX OP CONSTRUCTION, LP(1.34%)
MOHL AND SCOTT, INC. (9.29%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (2.61%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.56%)
PEACHTREE CONSTRUCTION, LTD. ( 45.38%)
HIGHWAY TECHNOLOGIES, INC. (3.84%)
HIGHWAY 19 CONSTRUCTION, LLC (5.17%)
Contract # 01133219
Totals 359999.95 88912.23 88912.23 24.6

CountyHUNT
Highway US 69
From 1.64 MILES SOUTH OF BU 69
To FM 513
CSJ 0203-02-041
Proj ID STP 1102(440)
Work Type WIDEN NON - FREEWAY
 
9.742 14582825.27 719205.30 10880059.55 74.6
Work Order 09-27-11
Work Began 02-08-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 320
Addl Days Granted 6
Working Days Charged 272
Percent Time Used 83
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
R. K. HALL CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-02-041
CATOCON, INC.(0.34%)
DUSTIN ALLEN, INC. (0.40%)
HIGHWAY TECHNOLOGIES, INC. (0.25%)
J. M. CONSTRUCTION (4.76%)
MOORE CONSTRUCTION, INC. (0.48%)
STRIPING TECHNOLOGY, L.P.(1.67%)
TEXAS ALTERNATIVE GRASSER, INC.(0.35%)
TEX OP CONSTRUCTION, LP(0.14%)
RK HALL, LLC ( 37.86%)
Contract # 08113206
Totals 14582825.27 719205.30 10880059.55 74.6

CountyFANNIN
Highway SH 78
From LP 205
To RUSSELL ST
CSJ 0279-02-036
Proj ID STP 2011(632)ES
Work Type OVERLAY
 
1.967 485168.09 0.00 1340249.04 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-10
Work Began 05-16-11
Work Completed 01-09-13
Time Computed 05-09-11
Contract Working Days 22
Addl Days Granted 92
Working Days Charged 113
Percent Time Used 99
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0279-02-036
CATACON, INC.(1.07%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.95%)
STRIPING TECHNOLOGY, L.P.(6.95%)
Contract # 10103226
Totals 485168.09 0.00 1340249.04 100.0

CountyFANNIN
Highway SH 78
From SH 11
To SH 56
CSJ 0279-03-034
Proj ID STP 2012(425)
Work Type REHABILITATION OF EXISTING ROAD
 
10.495 3660234.59 1700.00 3121880.12 85.2
Work Order 04-23-12
Work Began 05-07-12
Work Completed  
Time Computed 07-23-12
Contract Working Days 216
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 65
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0279-03-034
LYON BARRICADE AND CONSTRUCTION CO.(0.65%)
STRIPING TECHNOLOGY, L.P.(1.07%)
CATOCON, INC.(1.21%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (8.38%)
MOORE CONSTRUCTION, INC. (2.88%)
BAHENA CONSTRUCTION CO.,INC. (5.36%)
SAMMY G. SMALLWOOD (4.27%)
Contract # 03123206
Totals 3660234.59 1700.00 3121880.12 85.2

CountyDELTA
Highway FM 64
From FM 1532
To FM 3388
CSJ 0399-03-034
Proj ID STP 2013(547)
Work Type REHABILITATION OF EXISTING ROAD
 
4.939 1399777.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0399-03-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133008
Totals 1399777.15 0.00 0.00 0.0

CountyHOPKINS
Highway SH 154
From 0.315 MILES NORTH OF FM 1567 EAST
To 0.195 MILES SOUTH OF CR 1104
CSJ 0401-01-022
Proj ID STP 2013(464)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
4.973 6591501.99 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133219
Totals 6591501.99 0.00 0.00 0.0

CountyGRAYSON
Highway US 69
From 0.490 MI. NORTH OF SH 11
To 0.638 MI. SOUTH OF SH 56
CSJ 0410-02-030
Proj ID STP 2013(069)
Work Type REHABILITATION OF EXISTING ROAD
 
6.282 5218898.13 253049.07 2362633.96 45.2
Work Order 11-01-12
Work Began 11-09-12
Work Completed  
Time Computed 04-30-13
Contract Working Days 131
Addl Days Granted 9
Working Days Charged 54
Percent Time Used 38
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0410-02-030
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.29%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.12%)
BAHENA CONSTRUCTION CO.,INC. (4.46%)
MOORE CONSTRUCTION, INC. (0.62%)
DUSTROL, INC.(0.09%)
SAMMY G. SMALLWOOD (1.19%)
COWBELL TRAFFIC SERVICES, INC. (0.17%)
MARTIN MARIETTA MATERIALS, INC.( 30.80%)
Contract # 09123214
Totals 5218898.13 253049.07 2362633.96 45.2

CountyLAMAR
Highway FM 137
From @ DENTON CREEK
To .
CSJ 0435-01-053
Proj ID BR 2013(680)
Work Type BRIDGE REPLACEMENT
 
0.216 960387.80 0.00 0.00 0.0
CountyLAMAR
Highway CS
From CR E050-1
To AT DENTON CREEK
CSJ 0901-29-055
Proj ID BR 1102(219)
Work Type BRIDGE REPLACEMENT
 
0.138 428290.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY 19 CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133226
Totals 1388678.68 0.00 0.00 0.0

CountyFANNIN
Highway SH 121
From US 82
To SH 56
CSJ 0549-01-029
Proj ID STP 2012(575)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
1.863 6855007.15 460025.93 643525.92 9.3
Work Order 10-18-12
Work Began 03-11-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 284
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 7
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. ( 11.85%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70%)
NE-TEX CONSTRUCTION, LTD.( 32.14%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.54%)
STRIPING TECHNOLOGY, L.P.(0.98%)
TEX OP CONSTRUCTION, LP(0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69%)
Contract # 08123015
Totals 6855007.15 460025.93 643525.92 9.3

CountyFANNIN
Highway SH 121
From 0.209 MILES NORTH OF BS 121D
To SH 56
CSJ 0549-01-034
Proj ID STP 2013(548)
Work Type HEAVY OVERLAY
 
5.696 3739245.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133213
Totals 3739245.50 0.00 0.00 0.0

CountyFANNIN
Highway SH 121
From COLLIN COUNTY LINE
To 0.209 MILES NORTH OF BS 121 D
CSJ 0549-02-025
Proj ID STP 2011(887)
Work Type PAVEMENT RESTORATION
 
11.140 7391449.43 0.00 7386606.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-18-11
Work Began 06-10-11
Work Completed 11-29-12
Time Computed 10-17-11
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 136
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0549-02-025
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.16%)
L.F. MILLER CONSTRUCTION CO. (1.15%)
HALL BROTHERS CONSTRUCTION CO., INC. (6.23%)
STRIPING TECHNOLOGY, L.P.(2.22%)
HIGHWAY TECHNOLOGIES, INC. (0.10%)
LONE STAR BARRIER SERVICES, LLC(0.88%)
Contract # 03113215
Totals 7391449.43 0.00 7386606.60 100.0

CountyHUNT
Highway SH 276
From 5.92 MILES EAST OF FM 751
To 0.17 MILES EAST OF FM 513
CSJ 0641-01-033
Proj ID C 641-1-33
Work Type BRIDGE REPLACEMENT
 
2.803 47845878.71 560512.47 13102896.79 27.3
Work Order 08-28-12
Work Began 09-25-12
Work Completed  
Time Computed 02-25-13
Contract Working Days 671
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 17
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-01-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03%)
SCOTT DERR PAINTING CO (0.58%)
SAMMY G. SMALLWOOD (0.21%)
NORTH TEXAS REBAR, LLC (7.01%)
BAHENA CONSTRUCTION CO.,INC. (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
PEACHTREE CONSTRUCTION, LTD. (0.48%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.07%)
Contract # 07123202
Totals 47845878.71 560512.47 13102896.79 27.3

CountyHUNT
Highway FM 36
From SH 66
To IH 30
CSJ 0642-03-019
Proj ID STP 2013(070)
Work Type REHABILITATION OF EXISTING ROAD
 
3.593 1731836.44 132907.26 661507.45 38.1
Work Order 09-24-12
Work Began 12-10-12
Work Completed  
Time Computed 11-23-12
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 48
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0642-03-019
COWBELL TRAFFIC SERVICES, INC. (0.67%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.85%)
CATOCON, INC.(1.01%)
BAHENA CONSTRUCTION CO.,INC. (4.97%)
MOORE CONSTRUCTION, INC. (1.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.90%)
Contract # 08123226
Totals 1731836.44 132907.26 661507.45 38.1

CountyGRAYSON
Highway SH 91
From AT U.P. RAILROAD IN NORTH DENISON
To RR DOT # 410 961N
CSJ 0705-01-023
Proj ID STP 2010(911)RGS
Work Type MISCELLANEOUS CONSTRUCTION
 
0.584 6566674.51 89546.38 6181320.36 96.7
Work Order 08-02-10
Work Began 01-24-11
Work Completed  
Time Computed 08-18-10
Contract Working Days 354
Addl Days Granted 58
Working Days Charged 571
Percent Time Used 138
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0705-01-023
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.28%)
J.V. CONCRETE CONSTRUCTION ( 10.15%)
DUSTROL, INC. (ROANOKE)(1.35%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.64%)
WEBBER BARRIER SERVICES, INC.(3.40%)
T-BAR FENCE, INC.(0.18%)
S & S BRIDGE PAINTING, INC.(0.36%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56%)
NORTH TEXAS REBAR, LLC (0.04%)
PRIMATE CONSTRUCTION, INC. (0.14%)
Contract # 06103204
Totals 6566674.51 89546.38 6181320.36 96.7

CountyGRAYSON
Highway FM 120
From LORRAINE STREET IN POTTSBORO
To ANSLEY LANE IN DENISON
CSJ 0728-01-044
Proj ID STP 2012(115)
Work Type OVERLAY
 
4.256 3371212.70 1557.49 3535553.87 99.9
Work Order 12-02-11
Work Began 04-12-12
Work Completed  
Time Computed 01-31-12
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 197
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0728-01-044
UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.15%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(0.18%)
DUSTIN ALLEN, INC. (1.81%)
DUSTROL, INC.(1.46%)
L.F. MILLER CONSTRUCTION CO. (3.22%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.33%)
Contract # 11113211
Totals 3371212.70 1557.49 3535553.87 99.9

CountyGRAYSON
Highway FM 120
From HOUSTON ST.
To 0.093 MI. E OF FM 1753
CSJ 0728-02-028
Proj ID STP 2013(465)
Work Type OVERLAY
 
1.651 908156.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BILLY CUMMINGS CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0728-02-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133015
Totals 908156.95 0.00 0.00 0.0

CountyFANNIN
Highway FM 273
From FM 1396
To FM 100
CSJ 0765-03-022
Proj ID STP 1102(136)HRR
Work Type HAZARD ELIMINATION & SAFETY
 
17.122 3909524.55 0.00 3621006.40 100.0
Work Order 08-25-11
Work Began 08-31-11
Work Completed 02-22-13
Time Computed 09-10-11
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 109
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0765-03-022
J. M. CONSTRUCTION (5.34%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.41%)
LONE STAR BARRIER SERVICES, LLC(0.34%)
STRIPING TECHNOLOGY, L.P.(1.59%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.69%)
CATACON, INC.(1.96%)
BROCK ENVIRONMENTAL, LLC (1.60%)
SAMMY GIST ENTERPRISES, INC. (3.00%)
Contract # 07113007
Totals 3909524.55 0.00 3621006.40 100.0

CountyLAMAR
Highway VA
From VARIOUS LOCATIONS IN GRAYSON
To AND FANNIN COUNTIES
CSJ 0901-00-050
Proj ID STP 2010(287)
Work Type CONSTRUCT CURB RAMPS
 
0.001 823833.50 0.00 872427.51 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-10
Work Began 03-24-10
Work Completed  
Time Computed 03-17-10
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 77
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-00-050
LYON BARRICADE AND CONSTRUCTION CO.(3.13%)
TEX OP CONSTRUCTION, LP(2.59%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (3.00%)
BTA SERVICES, LTD. (1.37%)
CENTRAL TEXAS ENVIRONMENTAL SERVICES, LLC(0.72%)
Contract # 01103215
Totals 823833.50 0.00 872427.51 99.9

CountyLAMAR
Highway VA
From AT VARIOUS LOCATIONS IN LAMAR CO
To .
CSJ 0901-00-051
Proj ID STP 2012(289)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1629779.06 14812.15 1504386.67 92.8
Work Order 03-19-12
Work Began 11-07-12
Work Completed  
Time Computed 04-04-12
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 221
Percent Time Used 105
Contractor(s)
INTERSTATE IMPROVEMENT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-00-051
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (3.86%)
BTA SERVICES, LTD. (3.83%)
TI-ZACK CONCRETE, INC. ( 61.12%)
SAMMY G. SMALLWOOD (0.03%)
Contract # 02123016
Totals 1629779.06 14812.15 1504386.67 92.8

CountyGRAYSON
Highway CR
From CR 274-02 (SPRING CREEK RD)
To AT SPRING CREEK TRIBUTARY
CSJ 0901-19-134
Proj ID BR 1102(011)
Work Type BRIDGE REPLACEMENT
 
0.139 546772.50 55955.00 473661.83 90.5
Work Order 07-16-12
Work Began 09-27-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 137
Percent Time Used 134
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-134
CF SOUTHWEST ENVIRONMENT SERVICES LLC(9.65%)
DALLAS LITE AND BARRICADE INC. (1.11%)
FORTSON CONTRACTING, INC.(3.78%)
FOUNDATION DRILLERS, INC.(8.76%)
BOLEN CONSTRUCTION (2.74%)
Contract # 06123011
Totals 546772.50 55955.00 473661.83 90.5

page 1 | page 2 | page 3