Monthly State Let Construction Report For Paris District As Of Aug 12, 2014 Page 2 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLAMAR
Highway FM 137
From @ DENTON CREEK
To .
CSJ 0435-01-053
Proj ID BR 2013(680)
Work Type BRIDGE REPLACEMENT
 
0.216 960387.80 0.00 667590.56 69.5
CountyLAMAR
Highway CS
From CR E050-1
To AT DENTON CREEK
CSJ 0901-29-055
Proj ID BR 1102(219)
Work Type BRIDGE REPLACEMENT
 
0.138 428290.88 0.00 378128.98 88.2
Work Order 06-26-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 79
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-053
DUSTIN ALLEN, INC. (5.64%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.90%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.05%)
MCL CONTRACTING, LLC (0.51%)
SCOTT PAVING, INC. (0.76%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.62%)
FRITCHER CONSTRUCTION SERVICES (2.33%)
Contract # 05133226
Totals 1388678.68 0.00 1045719.54 75.3

CountyLAMAR
Highway FM 38
From LCR 34150
To FM 2820
CSJ 0435-01-063
Proj ID STP 2014(334)
Work Type REHABILITATION OF EXISTING ROAD
 
2.829 1267350.13 384730.58 844493.10 66.6
Work Order 03-18-14
Work Began 05-06-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 46
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-063
MOORE CONSTRUCTION, INC. (1.81%)
PANOLA SIGN & BARRICADE, INC.(0.43%)
CATACON, INC.(3.00%)
BAHENA CONSTRUCTION CO.,INC. ( 11.63%)
SAMMY G. SMALLWOOD (1.17%)
STRIPING TECHNOLOGY, L.P.(1.67%)
Contract # 01143015
Totals 1267350.13 384730.58 844493.10 66.6

CountyGRAYSON
Highway FM 902
From SH 5
To SH 11
CSJ 0510-02-028
Proj ID STP 2013(839)
Work Type REHABILITATION OF EXISTING ROAD
 
7.973 4317753.44 317207.67 2132876.68 49.3
Work Order 09-06-13
Work Began 01-03-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 32
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-02-028
CROSSROADS, L.P. (1.02%)
MOORE CONSTRUCTION, INC. (1.38%)
CATOCON, INC.(1.05%)
DUSTIN ALLEN, INC. (0.25%)
BAHENA CONSTRUCTION CO.,INC. (4.05%)
PEACHTREE CONSTRUCTION, LTD. (7.61%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.48%)
Contract # 07133220
Totals 4317753.44 317207.67 2132876.68 49.3

CountyFANNIN
Highway SH 121
From US 82
To SH 56
CSJ 0549-01-029
Proj ID STP 2012(575)
Work Type UPGRADE TO NON - FREEWAY STANDARDS
 
1.863 6855007.15 32193.47 2320416.93 33.8
Work Order 10-18-12
Work Began 03-11-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 284
Addl Days Granted 36
Working Days Charged 225
Percent Time Used 70
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-029
BAHENA CONSTRUCTION CO.,INC. ( 12.33%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.70%)
NE-TEX CONSTRUCTION, LTD.( 32.14%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (4.54%)
STRIPING TECHNOLOGY, L.P.(0.98%)
TEX OP CONSTRUCTION, LP(0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.13%)
Contract # 08123015
Totals 6855007.15 32193.47 2320416.93 33.8

CountyFANNIN
Highway SH 121
From 0.209 MILES NORTH OF BS 121D
To SH 56
CSJ 0549-01-034
Proj ID STP 2013(548)
Work Type HEAVY OVERLAY
 
5.696 3739245.50 6500.00 1657385.77 44.3
Work Order 07-08-13
Work Began 01-14-14
Work Completed  
Time Computed 07-24-13
Contract Working Days 95
Addl Days Granted 34
Working Days Charged 96
Percent Time Used 74
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0549-01-034
SALT CREEK PAVING AND CONSTRUCTION CO., INC. (1.44%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.27%)
STRIPING TECHNOLOGY, L.P.(2.02%)
NE-TEX CONSTRUCTION, LTD.(1.74%)
TEX OP CONSTRUCTION, LP(0.12%)
MOORE CONSTRUCTION, INC. (0.52%)
Contract # 04133213
Totals 3739245.50 6500.00 1657385.77 44.3

CountyHUNT
Highway SH 276
From 5.92 MILES EAST OF FM 751
To 0.17 MILES EAST OF FM 513
CSJ 0641-01-033
Proj ID C 641-1-33
Work Type BRIDGE REPLACEMENT
 
2.803 47845878.71 1691674.03 27975230.18 58.4
Work Order 08-28-12
Work Began 09-25-12
Work Completed  
Time Computed 02-25-13
Contract Working Days 671
Addl Days Granted 0
Working Days Charged 411
Percent Time Used 61
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-01-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03%)
SCOTT DERR PAINTING CO (0.58%)
SAMMY G. SMALLWOOD (0.21%)
NORTH TEXAS REBAR, LLC (7.01%)
BAHENA CONSTRUCTION CO.,INC. (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
PEACHTREE CONSTRUCTION, LTD. (0.48%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.07%)
Contract # 07123202
Totals 47845878.71 1691674.03 27975230.18 58.4

CountyHOPKINS
Highway FM 1567
From AT RUNNING CREEK
To .
CSJ 0641-05-016
Proj ID BR 2013(781)
Work Type BRIDGE REPLACEMENT
 
0.276 2644004.60 148014.77 1699256.55 64.2
Work Order 08-19-13
Work Began 11-04-13
Work Completed  
Time Computed 11-18-13
Contract Working Days 236
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 58
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0641-05-016
ODUM SERVICES, L.P.(4.37%)
PANOLA SIGN & BARRICADE, INC.(0.85%)
HOUSTON SAWING & DRILLING(0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.53%)
STRIPING TECHNOLOGY, L.P.(2.53%)
DUSTIN ALLEN, INC. (1.34%)
Contract # 06133217
Totals 2644004.60 148014.77 1699256.55 64.2

CountyGRAYSON
Highway FM 691
From FM 131 NORTH
To SH 91
CSJ 0666-01-024
Proj ID STP 2013(782)
Work Type WIDEN NON - FREEWAY
 
1.334 3093915.10 64640.76 436613.25 14.1
Work Order 01-17-14
Work Began 06-16-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 14
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0666-01-024
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
EROSION CONTROL MANAGEMENT SERVICES(0.20%)
CATACON, INC.(1.02%)
HIGHWAY 19 CONSTRUCTION, LLC ( 19.42%)
MCMAHON CONTRACTING, L.P.( 29.06%)
MOORE CONSTRUCTION, INC. (0.31%)
SCOTT DERR PAINTING CO, LLC(0.08%)
SAMMY G. SMALLWOOD (1.18%)
TEX OP CONSTRUCTION, LP(0.42%)
STRIPING TECHNOLOGY, L.P.(1.66%)
Contract # 10133026
Totals 3093915.10 64640.76 436613.25 14.1

CountyLAMAR
Highway FM 196
From FM 1501
To 1.0 MILE NORTH OF FM 1503
CSJ 0680-01-014
Proj ID STP 2014(295)
Work Type REHABILITATION OF EXISTING ROAD
 
2.121 858792.36 11787.36 890837.09 99.9
Work Order 01-09-14
Work Began 01-28-14
Work Completed  
Time Computed 01-28-14
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 67
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0680-01-014
FLAT LINE, INC.(1.33%)
CATACON, INC.(2.64%)
MOORE CONSTRUCTION, INC. (1.70%)
BAHENA CONSTRUCTION CO.,INC. (8.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.80%)
Contract # 12133217
Totals 858792.36 11787.36 890837.09 99.9

CountyLAMAR
Highway FM 1497 ETC
From AT CANEY CREEK
To .
CSJ 0688-03-023
Proj ID BR 2014(202)
Work Type BRIDGE REPLACEMENT
 
0.585 2196575.03 8800.00 406556.67 18.5
Work Order 12-10-13
Work Began 03-18-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 381
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 20
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0688-03-023
SOUTHWEST ENVIRONMENT SERVICES LLC (1.42%)
SAMMY G. SMALLWOOD (3.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.91%)
TEX OP CONSTRUCTION, LP(0.73%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.54%)
ACTION SERVICES(0.33%)
SOTO"S STEEL (0.31%)
PENHALL COMPANY(0.18%)
Contract # 11133009
Totals 2196575.03 8800.00 406556.67 18.5

CountyGRAYSON
Highway SH 91
From AT U.P. RAILROAD IN NORTH DENISON
To RR DOT # 410 961N
CSJ 0705-01-023
Proj ID STP 2010(911)RGS
Work Type MISCELLANEOUS CONSTRUCTION
 
0.584 6566674.51 0.00 6546172.41 99.9
Work Order 08-02-10
Work Began 01-24-11
Work Completed  
Time Computed 08-18-10
Contract Working Days 354
Addl Days Granted 102
Working Days Charged 630
Percent Time Used 138
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0705-01-023
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.28%)
J.V. CONCRETE CONSTRUCTION ( 10.15%)
DUSTROL, INC. (ROANOKE)(1.35%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.64%)
WEBBER BARRIER SERVICES, INC.(3.40%)
T-BAR FENCE, INC.(0.18%)
S & S BRIDGE PAINTING, INC.(0.36%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56%)
NORTH TEXAS REBAR, LLC (0.04%)
PRIMATE CONSTRUCTION, INC. (0.14%)
Contract # 06103204
Totals 6566674.51 0.00 6546172.41 99.9

CountyRAINS
Highway FM 514
From FM 275
To SH 19
CSJ 0725-02-016
Proj ID STP 2014(296)
Work Type REHABILITATION OF EXISTING ROAD
 
2.185 987747.98 247008.05 919235.73 93.0
Work Order 02-06-14
Work Began 04-07-14
Work Completed  
Time Computed 04-07-14
Contract Working Days 111
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 63
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0725-02-016
PANOLA SIGN & BARRICADE, INC.(0.42%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.97%)
CATOCON, INC.(3.44%)
MOORE CONSTRUCTION, INC. (1.69%)
SAMMY G. SMALLWOOD (1.68%)
BAHENA CONSTRUCTION CO.,INC. ( 11.31%)
Contract # 12133022
Totals 987747.98 247008.05 919235.73 93.0

CountyLAMAR
Highway FM 195
From 5.215 MI N OF US 82
To 2.0 MI S OF FM 906
CSJ 0730-02-013
Proj ID STP 2013(783)
Work Type REHABILITATION OF EXISTING ROAD
 
4.962 1632328.37 3000.00 1500955.74 91.9
Work Order 07-31-13
Work Began 08-15-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 77
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0730-02-013
STRIPING TECHNOLOGY, L.P.(2.60%)
R. K. HALL CONSTRUCTION, LTD.( 46.27%)
LYON BARRICADE AND CONSTRUCTION CO.(0.57%)
DUSTROL, INC.(2.61%)
MOORE CONSTRUCTION, INC. (0.76%)
RK HALL, LLC ( 46.27%)
Contract # 06133018
Totals 1632328.37 3000.00 1500955.74 91.9

CountyHOPKINS
Highway FM 69
From 1.553 MI S OF FM 1537
To 3.830 MI N OF FM 1537
CSJ 0766-01-027
Proj ID STP 2014(203)
Work Type REHABILITATION OF EXISTING ROAD
 
5.383 1863527.19 0.00 372600.98 19.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 04-09-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 186
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 30
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0766-01-027
SAMMY G. SMALLWOOD (1.49%)
DUSTIN ALLEN, INC. (0.72%)
CATACON, INC.(4.34%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MOORE CONSTRUCTION, INC. (3.75%)
SCOTT PAVING, INC. ( 15.94%)
BAHENA CONSTRUCTION CO.,INC. (9.68%)
LYON BARRICADE AND CONSTRUCTION CO.(0.95%)
Contract # 11133210
Totals 1863527.19 0.00 372600.98 19.9

CountyRED RIVER
Highway FM 410
From 3.2 MILES N OF US 82
To FM 195
CSJ 0772-01-027
Proj ID STP 2014(033)
Work Type REHABILITATION OF EXISTING ROAD
 
7.420 2516692.96 0.00 2065619.76 82.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-13
Work Began 01-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 330
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 36
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0772-01-027
LYON BARRICADE AND CONSTRUCTION CO.(1.04%)
CATACON, INC.(1.47%)
HIGHWAY 19 CONSTRUCTION, LLC ( 15.39%)
SAMMY G. SMALLWOOD (4.03%)
STRIPING TECHNOLOGY, L.P.(3.04%)
MOORE CONSTRUCTION, INC. (2.77%)
Contract # 09133031
Totals 2516692.96 0.00 2065619.76 82.0

CountyLAMAR
Highway VA
From VARIOUS LOCATIONS IN HUNT AND
To HOPKINS COUNTIES
CSJ 0901-00-052
Proj ID STP 2014(632)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1777289.00 247923.00 247923.00 13.9
Work Order 06-20-14
Work Began 07-07-14
Work Completed  
Time Computed 07-06-14
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 8
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-00-052
TOTAL HIGHWAY MAINTENANCE, LLC (0.60%)
ACTION SERVICES(0.44%)
Contract # 05143222
Totals 1777289.00 247923.00 247923.00 13.9

CountyLAMAR
Highway VA
From VARIOUS LOCATIONS IN PARIS DISTRICT
To .
CSJ 0901-00-053
Proj ID STP 2014(702)
Work Type MISCELLANEOUS CONSTRUCTION
 
0.001 217690.25 62353.40 62353.40 28.6
Work Order 06-20-14
Work Began 00-00-00
Work Completed  
Time Computed 08-19-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-00-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143037
Totals 217690.25 62353.40 62353.40 28.6

CountyGRAYSON
Highway CR
From CR 274-02 (SPRING CREEK RD)
To AT SPRING CREEK TRIBUTARY
CSJ 0901-19-134
Proj ID BR 1102(011)
Work Type BRIDGE REPLACEMENT
 
0.139 546772.50 0.00 481113.35 93.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-12
Work Began 09-27-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 147
Contractor(s)
EMPIRE CIVIL CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-134
CF SOUTHWEST ENVIRONMENT SERVICES LLC(9.65%)
DALLAS LITE AND BARRICADE INC. (1.11%)
FORTSON CONTRACTING, INC.(3.78%)
FOUNDATION DRILLERS, INC.(8.76%)
BOLEN CONSTRUCTION (2.74%)
Contract # 06123011
Totals 546772.50 0.00 481113.35 93.3

CountyHUNT
Highway CR
From INDIAN TRAIL RD IN HAWK COVE
To @ HAWK COVE TRIBUTARY
CSJ 0901-22-097
Proj ID BR 2012(621)
Work Type BRIDGE REPLACEMENT
 
0.090 549983.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143033
Totals 549983.20 0.00 0.00 0.0

CountyHUNT
Highway VA
From AT IH 30/SH 34 INTERCHANGE
To .
CSJ 0901-22-102
Proj ID STP 1102(456)
Work Type LANDSCAPE AND SCENIC ENHANCEMENT
 
0.100 104820.00 1510.00 238567.00 99.9
Work Order 09-13-11
Work Began 12-14-11
Work Completed  
Time Computed 09-29-11
Contract Working Days 64
Addl Days Granted 45
Working Days Charged 112
Percent Time Used 102
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-22-102
LONE STAR TRAFFIC SERVICE, INC.(1.71%)
DOWN UNDER CONSTRUCTION(1.71%)
Contract # 08113072
Totals 104820.00 1510.00 238567.00 99.9

page 1 | page 2 | page 3