AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - AUSTIN DISTRICT

Last Update: Friday, January 29, 2016
ITEMS 700 6001 TO 785 6011
Items Items Bid Code Range
0100 - 0193
0204 - 0275
0310 - 0360
0400 - 0499
0500 - 0560
0610 - 0690
0700 - 0785
1002 - 1122
2256 - 2257
3002 - 3271
5000 - 5926
6000 - 6834
7042 - 7060
8020 - 8851
700 6001 - 785 6011
Item No Description Units January 31, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
700 6001 POTHOLE REPAIR (STANDARD) SY     450.000 25.00000 2
730 6107 FULL - WIDTH MOWING CYC     9.000 2,003.33333 2
738 6001 CLEANING / SWEEPING (CENTER MEDIAN) CYC     14.000 1,325.00000 1
738 6003 CLEANING / SWEEPING (OUTSIDE MAIN LANE CYC     14.000 1,325.00000 1
738 6005 CLEANING / SWEEPING (FRONTAGE ROAD) CYC     20.000 1,527.50000 2
738 6007 CLEANING / SWEEPING (ENTRANCE / EXIT RAMP CYC     14.000 690.00000 1
740 6005 ANTI - GRAFFITI COATNG (PERMNENT - TY III SF     37,757.000 1.00000 1
752 2022 TREE REMOVAL (4" - 12" DIA) EA     11.000 529.54545 2
752 2023 TREE REMOVAL (12" - 18" DIA) EA     7.000 1,200.00000 3
752 2024 TREE REMOVAL (18" - 24" DIA) EA     5.000 1,480.00000 2
752 2026 TREE REMOVAL (30" - 36" DIA) EA     1.000 1,000.00000 1
764 6011 STORM SEWER CLEANING (PIPE) (37" - 42"DIA LF     295.000 30.00000 1
764 6012 STORM SEWER CLEANING (PIPE) (43" - 54"DIA LF     211.000 35.00000 1
772 6001 POST AND CABLE FENCE (REMOVAL) LF     1,118.000 10.00000 1
772 6002 POST AND CABLE FENCE (REMV CONC ANCHOR EA     1.000 250.00000 1
772 6003 POST AND CABLE FENCE (NEW INSTALLATION LF     1,766.000 20.83000 1
772 6004 POST AND CABLE FENCE (NEW CONC ANCHOR) EA     5.000 2,015.00000 1
780 6002 CNC CRACK REPAIR (DISCRETE) (INJECT) LF     128.000 120.00000 2
784 6002 REP STL BRIDGE MEMBER (BEAM) EA     10.000 12,000.00000 1
785 6011 BRIDGE JOINT REPLACEMENT (SEJ) LF     267.000 108.61000 1