Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6180-46-001
Proj ID BPM - 618046001
Work Type MISC. BRIDGE REPAIRS
 
0.001 132930.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6180-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10080401
Totals 132930.00 0.00 0.00 0.0

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6182-72-001
Proj ID SUP - 618272001
Work Type LITTER PICKUP (LIDS)
 
0.001 93992.44 3348.23 12756.84 13.5
Work Order 07-24-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 27
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6182-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07080420
Totals 93992.44 3348.23 12756.84 13.5