Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6179-39-001
Proj ID RMC - 617939001
Work Type FULL DEPTH CONCRETE REPAIR
 
0.001 195799.15 110106.80 170383.25 87.0
Work Order 10-16-08
Work Began 10-21-08
Work Completed  
Time Computed 10-21-08
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 50
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6179-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09080402
Totals 195799.15 110106.80 170383.25 87.0

CountyCARSON
Highway IH0040
From SEE PLANS
To SEE PLANS
CSJ 6179-90-001
Proj ID SUP - 617990001
Work Type LITTER REMOVAL, GROUNDS MAINTENANCE
 
1.000 12877.76 1012.72 5244.88 40.7
Work Order 06-26-08
Work Began 07-01-08
Work Completed  
Time Computed 07-01-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6179-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06080420
Totals 12877.76 1012.72 5244.88 40.7

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6180-46-001
Proj ID BPM - 618046001
Work Type MISC. BRIDGE REPAIRS
 
0.001 132930.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6180-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10080401
Totals 132930.00 0.00 0.00 0.0

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6182-72-001
Proj ID SUP - 618272001
Work Type LITTER PICKUP (LIDS)
 
0.001 93992.44 5062.72 17819.56 18.9
Work Order 07-24-08
Work Began 07-24-08
Work Completed  
Time Computed 07-24-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 35
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6182-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07080420
Totals 93992.44 5062.72 17819.56 18.9