Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOTTER
Highway LP0335
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-73-001
Proj ID RMC - 615773001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 174048.00 26397.00 105512.50 63.2
Work Order 10-23-07
Work Began 10-25-07
Work Completed  
Time Computed 10-30-07
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 29
Contractor(s)
JA-GE FARMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6157-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07070401
Totals 174048.00 26397.00 105512.50 63.2

CountyHUTCHINSON
Highway SH0207
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-74-001
Proj ID RMC - 615774001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 178020.00 0.00 60812.00 34.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-07
Work Began 11-15-07
Work Completed  
Time Computed 11-20-07
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 25
Contractor(s)
JA-GE FARMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6157-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07070402
Totals 178020.00 0.00 60812.00 34.1

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-75-001
Proj ID RMC - 615775001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 253776.00 0.00 126948.00 51.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-27-07
Work Began 10-08-07
Work Completed  
Time Computed 10-08-07
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 27
Contractor(s)
JA-GE FARMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6157-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07070403
Totals 253776.00 0.00 126948.00 51.0

CountyARMSTRONG
Highway US0287
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-76-001
Proj ID RMC - 615776001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 208870.72 0.00 69219.20 33.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-04-07
Work Began 10-22-07
Work Completed  
Time Computed 10-15-07
Contract Working Days 147
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 6
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6157-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04070404
Totals 208870.72 0.00 69219.20 33.1

CountyCARSON
Highway US0060
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-77-001
Proj ID RMC - 615777001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 138195.84 0.00 58881.08 44.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-16-07
Work Began 10-26-07
Work Completed  
Time Computed 10-29-07
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 6
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6157-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04070405
Totals 138195.84 0.00 58881.08 44.8

CountyOLDHAM
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-78-001
Proj ID RMC - 615778001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 167110.00 32164.00 88011.00 53.2
Work Order 08-22-07
Work Began 09-10-07
Work Completed  
Time Computed 09-12-07
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 45
Contractor(s)
JA-GE FARMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6157-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07070404
Totals 167110.00 32164.00 88011.00 53.2

CountyGRAY
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6157-79-001
Proj ID RMC - 615779001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 206349.10 24094.57 74372.66 36.6
Work Order 10-08-07
Work Began 10-23-07
Work Completed  
Time Computed 10-18-07
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 22
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6157-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04070407
Totals 206349.10 24094.57 74372.66 36.6

CountyOLDHAM
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6160-46-001
Proj ID SUP - 616046001
Work Type DEBRIS PICKUP AND DISPOSAL
 
0.001 102336.00 1968.00 62976.00 61.5
Work Order 04-16-07
Work Began 05-01-07
Work Completed  
Time Computed 05-01-07
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 487
Percent Time Used 67
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6160-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03070421
Totals 102336.00 1968.00 62976.00 61.5

CountyHARTLEY
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6161-42-001
Proj ID RMC - 616142001
Work Type PICNIC AREA MAINTENANCE & LITTER PICKUP
 
0.001 66326.00 1776.00 42207.00 63.6
Work Order 06-21-07
Work Began 06-28-07
Work Completed  
Time Computed 06-28-07
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 438
Percent Time Used 60
Contractor(s)
PBS PARK SERVICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6161-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05070402
Totals 66326.00 1776.00 42207.00 63.6

CountyOLDHAM
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6162-60-001
Proj ID SUP - 616260001
Work Type SPOT LITTER (STATE USE)
 
0.001 13374.24 557.26 10030.68 75.0
Work Order 04-16-07
Work Began 05-01-07
Work Completed  
Time Computed 05-01-07
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 487
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6162-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04070420
Totals 13374.24 557.26 10030.68 75.0

CountyOLDHAM
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6162-61-001
Proj ID SUP - 616261001
Work Type PICNIC AREA MAINTENANCE
 
0.001 98604.00 3375.52 71451.56 72.4
Work Order 04-16-07
Work Began 05-01-07
Work Completed  
Time Computed 05-01-07
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 487
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6162-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04070421
Totals 98604.00 3375.52 71451.56 72.4

CountyHANSFORD
Highway SH0015
From FIVE (5) COUNTIES
To FIVE (5) COUNTIES
CSJ 6165-51-001
Proj ID RMC - 616551001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
1.000 125400.00 10450.00 52250.00 41.6
Work Order 10-01-07
Work Began 10-08-07
Work Completed  
Time Computed 10-08-07
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 354
Percent Time Used 48
Contractor(s)
AUBREY NELSON
SUBCONTRACTOR(S) FOR CCSJ: 6165-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08070403
Totals 125400.00 10450.00 52250.00 41.6

CountyCARSON
Highway US0060
From SEE PLANS
To SEE PLANS
CSJ 6166-52-001
Proj ID RMC - 616652001
Work Type SWEEPING OF HIGHWAYS AND BRIDGES
 
1.000 323500.00 0.00 90980.00 28.1
Work Order 12-03-07
Work Began 12-19-07
Work Completed  
Time Computed 12-17-07
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 294
Percent Time Used 40
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6166-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10070403
Totals 323500.00 0.00 90980.00 28.1

CountyCARSON
Highway US0060
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6167-64-001
Proj ID RMC - 616764001
Work Type PICNIC AREA MAINTENANCE
 
1.000 13590.04 307.32 4426.80 32.5
Work Order 01-11-08
Work Began 02-04-08
Work Completed  
Time Computed 02-01-08
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 257
Percent Time Used 35
Contractor(s)
LEONARD MORRIS
SUBCONTRACTOR(S) FOR CCSJ: 6167-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12070401
Totals 13590.04 307.32 4426.80 32.5

CountyARMSTRONG
Highway US0287
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6167-68-001
Proj ID RMC - 616768001
Work Type PINIC AREA MAINTENANCE
 
1.000 46499.80 1311.20 16767.80 36.0
Work Order 12-03-07
Work Began 12-03-07
Work Completed  
Time Computed 12-03-07
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 297
Percent Time Used 41
Contractor(s)
PBS PARK SERVICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6167-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10070404
Totals 46499.80 1311.20 16767.80 36.0

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6167-92-001
Proj ID RMC - 616792001
Work Type PICNIC AREA MAINTENANCE
 
0.001 24998.06 370.32 9420.38 37.6
Work Order 11-15-07
Work Began 11-26-07
Work Completed  
Time Computed 11-26-07
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 310
Percent Time Used 43
Contractor(s)
LEONARD MORRIS
SUBCONTRACTOR(S) FOR CCSJ: 6167-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10070405
Totals 24998.06 370.32 9420.38 37.6

CountyHUTCHINSON
Highway SH0136
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6171-25-001
Proj ID RMC - 617125001
Work Type LANE BLADING OF ROADWAY SNOW AND / OR ICE
 
1.000 112500.00 0.00 2700.00 2.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-13-07
Work Began 12-13-07
Work Completed  
Time Computed 12-13-07
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 25
Contractor(s)
E. D. BAKER COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6171-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11070401
Totals 112500.00 0.00 2700.00 2.4

CountyCARSON
Highway IH0040
From EASTERN POTTER COUNTY LINE
To WESTERN WHEELER COUNTY LINE
CSJ 6172-14-001
Proj ID SUP - 617214001
Work Type DEBRIS PICKUP AND DISPOSAL
 
64.000 34112.00 1968.00 20992.00 61.5
Work Order 01-02-08
Work Began 01-14-08
Work Completed  
Time Computed 01-14-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 322
Percent Time Used 88
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6172-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12070420
Totals 34112.00 1968.00 20992.00 61.5

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6175-56-001
Proj ID RMC - 617556001
Work Type ASBESTOS ABATEMENT OF CTB
 
0.001 86322.60 54162.00 54162.00 62.7
Work Order 10-15-08
Work Began 11-03-08
Work Completed  
Time Computed 11-03-08
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 52
Contractor(s)
CLASSIC CITY UTILITY, INC
SUBCONTRACTOR(S) FOR CCSJ: 6175-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09080403
Totals 86322.60 54162.00 54162.00 62.7

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6175-62-001
Proj ID RMC - 617562001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 131001.04 10083.42 90750.78 69.2
Work Order 03-07-08
Work Began 03-11-08
Work Completed  
Time Computed 03-13-08
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 263
Percent Time Used 72
Contractor(s)
J. H. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6175-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02080402
Totals 131001.04 10083.42 90750.78 69.2