Monthly Local Let Maintenance Report For Amarillo District As Of Jan 11, 2017 Page 2 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRANDALL
HighwayIH0027
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6292-61-001
Proj IDSUP - 629261001
Work TypeLITTER PICKUP (LIDS)
 
0.001140776.10135194.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed08-31-16
Time Computed09-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged363
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150420
Totals140776.100.00135194.40100.0

CountyGRAY
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6298-66-001
Proj IDSUP - 629866001
Work TypeSTATE USE DEBRIS PICKUP
 
0.00176800.0076800.0099.9
Work Order00-00-00
Work Began01-05-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150420
Totals76800.006400.0076800.0099.9

CountyDEAF SMITH
HighwayUS0385
FromHEREFORD MAINT OFFICE
ToHEREFORD MAINT OFFICE
CSJ6300-17-001
Proj IDSUP - 630017001
Work TypeJANITORIAL SERVICE
 
0.0015887.924440.9675.4
Work Order00-00-00
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged306
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02160420
Totals5887.92374.254440.9675.4

CountyPOTTER
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6300-74-001
Proj IDRMC - 630074001
Work TypeCLEAN & SWEEPING HIGHWAYS (RURAL)
 
0.001149753.3668346.1845.6
Work Order00-00-00
Work Began06-03-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160401
Totals149753.360.0068346.1845.6

CountyMOORE
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6301-34-001
Proj IDRMC - 630134001
Work TypeON CALL GUARDRAIL REPAIR
 
0.001124895.0049772.0039.8
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed05-09-16
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6301-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160402
Totals124895.000.0049772.0039.8

CountyMOORE
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6302-26-001
Proj IDRMC - 630226001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001153923.7070205.8545.6
Work Order00-00-00
Work Began07-18-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160401
Totals153923.7033575.5070205.8545.6

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6302-38-001
Proj IDRMC - 630238001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001293289.60165024.3556.2
Work Order00-00-00
Work Began06-15-16
Work Completed
Time Computed06-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160402
Totals293289.6023232.05165024.3556.2

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-17-001
Proj IDRMC - 630317001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001149867.8367215.9244.8
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed09-01-16
Contract Working Days44
Addl Days Granted0
Working Days Charged7
Percent Time Used15
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6303-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160404
Totals149867.832000.0067215.9244.8

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-18-001
Proj IDRMC - 630318001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001202845.7692703.8845.7
Work Order00-00-00
Work Began12-13-16
Work Completed
Time Computed09-01-16
Contract Working Days86
Addl Days Granted0
Working Days Charged11
Percent Time Used12
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6303-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160403
Totals202845.762000.0092703.8845.7

CountyLIPSCOMB
HighwayFM1454
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-28-001
Proj IDBPM - 630328001
Work TypeMISC BRIDGE REPAIRS
 
0.001123018.26122706.4699.7
Work Order00-00-00
Work Began06-20-16
Work Completed
Time Computed06-15-16
Contract Working Days60
Addl Days Granted21
Working Days Charged5
Percent Time Used6
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6303-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160405
Totals123018.260.00122706.4699.7

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-65-001
Proj IDRMC - 630365001
Work TypeTRAFFIC CONTROL
 
0.001295000.0095277.5032.2
Work Order00-00-00
Work Began07-12-16
Work Completed
Time Computed07-12-16
Contract Working Days365
Addl Days Granted0
Working Days Charged173
Percent Time Used47
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6303-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160401
Totals295000.0022293.7595277.5032.2

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-93-001
Proj IDSUP - 630393001
Work TypePICNIC AREA MAINT.AND LITTER PICKUP
 
0.00163457.6842101.7366.3
Work Order00-00-00
Work Began05-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160420
Totals63457.685491.5342101.7366.3

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-94-001
Proj IDSUP - 630394001
Work TypeSTATE USE SPOT LITTER PICKUP
 
0.0019909.246606.1666.6
Work Order00-00-00
Work Began05-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160421
Totals9909.24825.776606.1666.6

CountyRANDALL
HighwayFM1541
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6304-44-001
Proj IDSUP - 630444001
Work TypeSTATE USE JANITORIAL
 
0.00114904.639045.2060.6
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160420
Totals14904.632294.559045.2060.6

CountyGRAY
HighwayIH0040
FromAT BRIDGE
ToSTATION 248+35
CSJ6307-49-001
Proj IDRMC - 630749001
Work TypeBRIDGE REPAIR
 
0.00529729.0636594.9499.9
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed10-31-16
Contract Working Days25
Addl Days Granted5
Working Days Charged20
Percent Time Used66
Contractor(s)
DFB CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6307-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160401
Totals29729.0615512.5236594.9499.9

CountyRANDALL
HighwayIH0027
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6307-65-001
Proj IDSUP - 630765001
Work TypeDISTRICT OFFICE JANITORIAL SERVICE
 
0.00174226.0431484.1042.4
Work Order00-00-00
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160420
Totals74226.048968.4231484.1042.4

CountyCARSON
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6307-66-001
Proj IDRMC - 630766001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
0.00198949.6245287.3445.7
Work Order00-00-00
Work Began09-26-16
Work Completed
Time Computed09-26-16
Contract Working Days365
Addl Days Granted0
Working Days Charged82
Percent Time Used22
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160401
Totals98949.6222643.6745287.3445.7

CountyPOTTER
HighwayIH0040
FromVARIOUS
To.
CSJ6308-19-001
Proj IDSUP - 630819001
Work TypeJANITORIAL AND GROUNDS
 
0.001335405.8056054.1216.7
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160402
Totals335405.8014243.2656054.1216.7

CountyPOTTER
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6308-76-001
Proj IDSUP - 630876001
Work TypeSTATE USE LITTER PICKUP(LIDS)
 
0.00192692.1527337.1629.4
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160420
Totals92692.156834.2927337.1629.4

CountyRANDALL
HighwayUS0060
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6309-52-001
Proj IDSUP - 630952001
Work TypeSTATE USE JANITORIAL CANYON MAINT.
 
0.0019900.083010.0230.4
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160421
Totals9900.08908.343010.0230.4