Monthly State Let Construction Report For Austin District As Of May 10, 2024 Page 7 Of 7

Last Update: Friday, May 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHAYS
HighwayFM 2770
From0.484 MILES E OF FM 1626
ToFM 1626
CSJ3210-01-020
Proj IDC 3210-1-20
Work TypeOVERLAY
 
294471.83244000.9582.8
Work Order02-15-24
Work Began04-15-24
Work Completed
Time Computed04-15-24
Contract Working Days13
Addl Days Granted0
Working Days Charged8
Percent Time Used61
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3210-01-020
ENVIRONMENTAL SAFETY SERVICES, INC. (1.69)
FLASHER EQUIPMENT COMPANY (12.75)
Contract #01243241
Totals294471.83244000.95244000.9582.8

CountyTRAVIS
HighwayFM 3177
From0.05 MI SOUTH OF LOYOLA LN
To0.15 MI SOUTH OF CANOGA AVE
CSJ3277-01-025
Proj IDSTP 2023(990)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.7422361951.00931074.1539.4
Work Order08-03-23
Work Began10-09-23
Work Completed
Time Computed09-02-23
Contract Working Days104
Addl Days Granted0
Working Days Charged106
Percent Time Used101
Contractor(s)
LONE STAR SITEWORK, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3277-01-025
G. CARTER CONSTRUCTION COMPANY, INC. (14.45)
ENVIRONMENTAL SAFETY SERVICES, INC. (6.26)
FLASHER EQUIPMENT COMPANY (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
LONE STAR PAVING COMPANY (0.00)
SIX SITE SERVICES, LLC (1.97)
AARON CONCRETE CONTRACTORS, LLC (0.27)
Contract #06233436
Totals2361951.00106214.20931074.1539.4

CountyBLANCO ETC
HighwayRM 3232 ETC
FromRM 2766
ToUS 290
CSJ3351-02-006
Proj IDF 2024(363)
Work TypeSEAL COAT
 
8.7704405351.1529960.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3351-02-006
KELLER TRUCKING, INC. (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
MPB, INC. (0.00)
Contract #11233015
Totals4405351.1529960.0029960.000.6

CountyTRAVIS
HighwayFM 734
FromSAMSUNG BLVD
To0.02 MI EAST OF HARRIS BRANCH
CSJ3417-03-021
Proj IDF 2023(337)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.5105597210.355368869.5195.9
Work Order01-12-23
Work Began06-07-23
Work Completed
Time Computed02-11-23
Contract Working Days155
Addl Days Granted0
Working Days Charged155
Percent Time Used100
Contractor(s)
AARON CONCRETE CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-021
ENVIRONMENTAL SAFETY SERVICES, INC. (4.56)
FLASHER EQUIPMENT COMPANY (2.24)
TEXAS MATERIALS GROUP, INC. (35.84)
CAVE TRUCKING, LLC (9.94)
Contract #12223031
Totals5597210.35874222.295368869.5195.9

CountyTRAVIS
HighwayFM 734
FromEAST US 290
ToLOOP 275
CSJ3417-03-027
Proj IDC 3417-3-27
Work TypeTRAFFIC CONTROL DEVICES
 
7.6554925236.004749181.1596.4
Work Order06-14-23
Work Began09-18-23
Work Completed
Time Computed09-18-23
Contract Working Days372
Addl Days Granted10
Working Days Charged145
Percent Time Used37
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-027
FIBERTEL, LLC (20.42)
ROADWAY SPECIALTIES, INC. (1.73)
CALAME CONTRACTING, LLC (0.10)
BREDA COMPANY, INC. (0.15)
TEXAS TRAFFIC AND BARRICADE, LLC (1.22)
APTUS GROUP USA, LLC (3.75)
TRP CONSTRUCTION GROUP, LLC (0.48)
LAWLEY CONTRACTING, LLC (7.76)
Contract #05233213
Totals4925236.00210989.474749181.1596.4

CountyTRAVIS
HighwayFM 734
FromW OF MCCALLEN PASS
ToSAMSUNG BLVD
CSJ3417-03-033
Proj IDC 3417-3-33
Work TypeOVERLAY
 
3643668.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243219
Totals3643668.430.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7