Monthly State Let Construction Report For Austin District As Of Feb 09, 2018 Page 3 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBURNET
HighwaySH 29
From0.862 MI WEST OF RM 243
To0.230 MI WEST OF RM 243
CSJ0151-01-051
Proj IDSTP 2018(180)
Work TypeCONSTRUCTION OF CONTINUOUS LTL
 
0.632612820.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DENBOW COMPANY INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-01-051
TEX OP CONSTRUCTION, LP (1.86)
STATEWIDE MATERIALS TRANSPORT LTD (2.25)
ROADWAY SPECIALTIES, INC. (2.59)
R K STEPHENS CONSTRUCTION, LLC (5.82)
LONE STAR PAVING (33.39)
FLASHER LIMITED (3.65)
D. I. J. CONSTRUCTION, INC. (3.17)
Contract #10173007
Totals612820.240.000.000.0

CountyTRAVIS
HighwayUS 183
FromEASTSIDE OF IH 35
ToEASTSIDE OF US 290
CSJ0151-09-145
Proj IDNH 2017(946)
Work TypeREPAIR, MILL, SEAL & OVERLAY
 
4.3482711157.552333711.2086.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days54
Addl Days Granted0
Working Days Charged50
Percent Time Used92
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-09-145
FLASHER EQUIPMENT COMPANY (4.40)
CHEROKEE SERVICES (2.41)
ROADWAY SPECIALTIES, INC. (14.44)
GREEN MILLING GROUP (2.94)
Contract #04173220
Totals2711157.550.002333711.2086.0

CountyCALDWELL
HighwayUS 183
FromINTERSECTION OF US 183 AND IH 10
To.
CSJ0153-01-013
Proj IDNH 2018(469)
Work TypeINTERSECTION IMPROVEMENTS
 
0.1001769284.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0153-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173013
Totals1769284.150.000.000.0

CountyWILLIAMSON
HighwayUS 79
FromFM 397
ToCR 402
CSJ0204-03-043
Proj IDSTP 1702(037)
Work TypeMILL,SEAL & OVERLAY
 
2.010911970.84987532.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began09-05-17
Work Completed
Time Computed08-01-17
Contract Working Days43
Addl Days Granted0
Working Days Charged36
Percent Time Used83
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0204-03-043
CHEROKEE SERVICES (2.53)
DUSTROL, INC. (6.87)
ROADWAY SPECIALTIES, INC. (0.08)
TRP CONSTRUCTION GROUP, LLC (6.69)
Contract #05173215
Totals911970.840.00987532.3999.9

CountyLEE
HighwayUS 77 ETC
From3.5 MI S OF MILAM C/L
ToSL 123
CSJ0211-02-026
Proj IDNH 2018(531)
Work TypeLEVEL-UP, FULL DEPTH REPAIR AND TOM
 
17.5575387885.790.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-02-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183021
Totals5387885.790.000.000.0

CountyBASTROP
HighwaySH 71
From0.268 MI. WEST OF SH 95
To0.477 MI. EAST OF SH 95
CSJ0265-05-067
Proj IDSTP 2012(629)
Work TypeCONST. OVERPASS AND 4 MAIN LNS
 
0.74515379463.0114114205.7092.3
CountyBASTROP
HighwaySH 71
From0.358 MI. WEST OF SH 95
To0.268 MI. WEST OF SH 95
CSJ0265-05-078
Proj IDNH 1502(667)
Work TypeADD ENTRANCE RAMP BRIDGE
 
0.0911129745.521099920.6097.3
Work Order05-17-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days350
Addl Days Granted49
Working Days Charged382
Percent Time Used95
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-067
ABC EROSION CONTROL, INC. (0.73)
FLASHER EQUIPMENT COMPANY (0.53)
AARON CONCRETE CONTRACTORS, L.P. (5.19)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.22)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.90)
ANCORTEX, INC. (5.88)
AUSTIN WOOD RECYCLING (0.10)
BRICK PAVING PLUS, INC. (0.43)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.10)
GK CONSTRUCTION, LLC (0.25)
HOUSTON SAWING & DRILLING (0.03)
MURRAY CONSTRUCTION (0.20)
ROADWAY SPECIALTIES, INC. (2.15)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00)
RAMI MATERIALS TRANSPORT, LLC (0.00)
KRL CONSTRUCTION INC. (0.16)
AUSTIN FORMULA UTILITIES (0.19)
Contract #12153204
Totals16509208.53285235.9315214126.3092.7

CountyBASTROP
HighwaySH 71
From0.40 MI E OF LP 150
To1.514 MI E OF LP 230
CSJ0265-05-079
Proj IDNH 2017(788)
Work TypeLEVEL-UP & TOM
 
15.9665983021.724298485.7571.8
Work Order04-24-17
Work Began07-10-17
Work Completed
Time Computed05-24-17
Contract Working Days95
Addl Days Granted0
Working Days Charged68
Percent Time Used71
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-079
DUSTROL, INC. (3.76)
TRP CONSTRUCTION GROUP, LLC (5.73)
Contract #03173034
Totals5983021.7266264.774298485.7571.8

CountyBASTROP
HighwaySH 71
FromAT TAHITIAN
To.
CSJ0265-05-081
Proj IDNH 1702(548)
Work TypeLANDSCAPE AND IRRIGATION
 
0.128606000.00193663.3331.9
Work Order08-23-17
Work Began12-26-17
Work Completed
Time Computed11-21-17
Contract Working Days120
Addl Days Granted0
Working Days Charged16
Percent Time Used13
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-081
FLASHER EQUIPMENT COMPANY (1.29)
Contract #07173221
Totals606000.00190663.33193663.3331.9

CountyBURNET
HighwayUS 183
FromLAMPASAS COUNTY LINE
ToEAST OF RM 963
CSJ0273-02-024
Proj IDSTP 1702(009)HES
Work TypeCONVERT 4-LN UNDIV TO SUPER 2 W/SHL
 
20.5311383923.159100.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0273-02-024
INTERSTATE BARRICADES & MARKINGS, INC. (37.37)
ROADWAY SPECIALTIES, INC. (1.60)
Contract #03173041
Totals1383923.150.009100.000.6

CountyBASTROP
HighwaySH 95
FromAT PERSHING BLVD
To.
CSJ0322-01-046
Proj IDSTP 1702(549)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
0.500158863.0059718.2537.5
Work Order08-08-17
Work Began01-04-18
Work Completed
Time Computed09-07-17
Contract Working Days54
Addl Days Granted0
Working Days Charged20
Percent Time Used37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0322-01-046
KRL CONSTRUCTION INC. (16.07)
D.I.J. CONSTRUCTION, INC (1.88)
PHILLIPS TRAFFIC CONTROL (1.22)
DELA LAGUNA CONTRACTING (4.21)
Contract #07173010
Totals158863.0058518.2559718.2537.5

CountyWILLIAMSON
HighwaySH 29
FromSOUTH AUSTIN AVE.
ToGEORGETOWN INNER LOOP
CSJ0337-02-040
Proj IDSTP 2016(635)
Work TypeOVERLAY
 
2.9051319538.691190056.9790.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began08-15-17
Work Completed
Time Computed08-01-17
Contract Working Days37
Addl Days Granted0
Working Days Charged24
Percent Time Used64
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0337-02-040
ROADWAY SPECIALTIES, INC. (5.24)
TRP CONSTRUCTION GROUP, LLC (4.30)
LONE STAR SITEWORK, LLC (1.25)
Contract #02173008
Totals1319538.690.001190056.9790.1

CountyWILLIAMSON
HighwaySH 29
FromSH 130
ToSH 95
CSJ0337-02-043
Proj IDSTP 2018(470)HES
Work TypeUPGRADE MBGF & SAFETY TREAT FIX OBJ
 
12.079682271.700.000.0
CountyWILLIAMSON
HighwayFM 1063
FromFM 1331
ToUS 79
CSJ1202-03-014
Proj IDSTP 2018(470)HES
Work TypeUPGRADE MBGF & SAFETY TREAT FIX OBJ
 
5.759566307.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days287
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0337-02-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173019
Totals1248578.850.000.000.0

CountyHAYS
HighwaySH 123
From3500 FT NORTH OF RM 12
To3500 FT SOUTH OF RM 12
CSJ0366-01-066
Proj IDC 366-1-66
Work TypeCONST GRADE SEPARATION
 
1.32611596550.4811643891.5899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-27-14
Work Began03-31-15
Work Completed
Time Computed02-22-15
Contract Working Days465
Addl Days Granted116
Working Days Charged505
Percent Time Used86
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-066
BMP SPECIALIST, LLC (1.56)
FLASHER EQUIPMENT COMPANY (1.80)
HOUSTON SAWING & DRILLING (0.04)
THE LEVY COMPANY, L.P. (3.95)
MCL CONTRACTING, LLC (0.24)
MURRAY CONSTRUCTION (0.22)
R K STEPHENS CONSTRUCTION, LLC (1.77)
VEGETATION MANAGEMENT SPECIALIST, INC. (0.06)
VOGES DRILLING CO. (0.73)
Contract #06143202
Totals11596550.480.0011643891.5899.9

CountyCALDWELL
HighwayFM 1854
FromSH 21
To0.039 MI N OF FM 672
CSJ0384-04-030
Proj IDSTP 2017(947)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
13.740986625.98609407.3761.7
Work Order05-30-17
Work Began07-12-17
Work Completed
Time Computed06-29-17
Contract Working Days109
Addl Days Granted0
Working Days Charged98
Percent Time Used89
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0384-04-030
MV HENKE COMPANY, LLC (1.31)
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (7.20)
FLASHER EQUIPMENT COMPANY (0.52)
DIIBS SPECIALISTS (8.24)
Contract #04173207
Totals986625.98128030.80609407.3761.7

CountyMASON
HighwaySH 29
FromMENARD COUNTY LINE
ToUS 377
CSJ0396-02-026
Proj IDSTP 1702(551)HES
Work TypeUPGRADE MBGF, SFTY TRT, PROF MRKRS
 
12.5701204213.50912251.6575.7
Work Order08-11-17
Work Began09-18-17
Work Completed
Time Computed09-18-17
Contract Working Days168
Addl Days Granted0
Working Days Charged74
Percent Time Used44
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0396-02-026
ROADWAY SPECIALTIES, INC. (25.34)
Contract #07173235
Totals1204213.50216104.64912251.6575.7

CountyLLANO
HighwayRM 152
From0.085 MI E OF POST OAK ST
To0.031 MI W OF MALONE ST
CSJ0396-09-021
Proj IDSTP 2017(426)TAPS
Work TypePEDESTRIAN TRAIL- SIDEWALKS
 
1.4001011049.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days161
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0396-09-021
ENVIRONMENTAL SAFETY SERVICES, INC. (2.28)
FLASHER EQUIPMENT COMPANY (0.75)
ROADWAY SPECIALTIES, INC. (1.60)
D. I. J. CONSTRUCTION, INC. (0.32)
Contract #09173016
Totals1011049.850.000.000.0

CountyTRAVIS
HighwaySH 130
FromSH 130 @ FM 812
To.
CSJ0440-06-014
Proj IDNH 1502(385)
Work TypeLANDSCAPING AND IRRIGATION
 
0.100642322.00625783.5097.4
Work Order08-31-15
Work Began10-26-15
Work Completed
Time Computed10-26-15
Contract Working Days60
Addl Days Granted0
Working Days Charged60
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-06-014
N-LINE TRAFFIC MAINTENANCE, L.P. (0.70)
CLASSIC TEJAS CONSTRUCTION, INC. (12.85)
M & M UNDERGROUND CONSTRUCTION (1.08)
Contract #07153257
Totals642322.003000.00625783.5097.4

CountyTRAVIS
HighwaySH 130
FromSH 45
ToUS 290
CSJ0440-06-017
Proj IDCC 440-6-17
Work TypeADD ONE LANE IN EACH DIRECTION
 
9.00836726431.310.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days595
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-06-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173201
Totals36726431.310.000.000.0

CountyHAYS
HighwaySH 21
From0.9 MI WEST OF YARRINGTON ROAD
ToFM 2001
CSJ0471-02-071
Proj IDNH 2018(272)
Work TypeREPAIR LEVEL UP AND SEAL COAT
 
9.264630023.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0471-02-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173008
Totals630023.000.000.000.0

CountyWILLIAMSON
HighwayRM 620
FromWEST OF CORNERWOOD DRIVE
ToEAST OF WYOMING SPRINGS DRIVE
CSJ0683-01-094
Proj IDSTP 2018(181)
Work TypeMILL,OV,RESTRIPE FROM 4 TO 6 LNS
 
2.003471769.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0683-01-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173017
Totals471769.150.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5