Monthly State Let Construction Report For Austin District As Of Jan 10, 2018 Page 5 Of 6

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLEE
HighwayCR
FromON CR 418 AT ALLEN CREEK
ToSTR AA01-81-001
CSJ0914-21-031
Proj IDBR 2016(252)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.064313217.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183011
Totals313217.770.000.000.0

CountyMASON
HighwayCR
FromKATEMCY RD @ DRY PRONG KATEMCY CRK
ToSTR AA0180001
CSJ0914-26-007
Proj IDBR 1402(184)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.064264228.00193065.8073.0
Work Order08-16-17
Work Began11-13-17
Work Completed
Time Computed10-15-17
Contract Working Days63
Addl Days Granted0
Working Days Charged27
Percent Time Used42
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-26-007
D. I. J. CONSTRUCTION, INC. (0.40)
FLASHER EQUIPMENT COMPANY (1.04)
ROADWAY SPECIALTIES, INC. (2.84)
INCE ENTERPRISES, INC. (3.68)
FOUR-B PAVING, INC. (23.25)
Contract #07173011
Totals264228.00115191.80193065.8073.0

CountyHAYS
HighwayCR
FromON POST RD (CR 140)
ToAT THE BLANCO RIVER
CSJ0914-33-072
Proj IDBR 2016(787)
Work TypeBRIDGE REPLACEMENT
 
0.126905345.35877610.3096.9
Work Order07-06-17
Work Began08-04-17
Work Completed
Time Computed08-04-17
Contract Working Days139
Addl Days Granted0
Working Days Charged93
Percent Time Used66
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-072
AUSTIN MATERIALS, LLC (3.21)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.04)
VOGES DRILLING CO. (2.96)
FLASHER EQUIPMENT COMPANY (1.59)
ROADWAY SPECIALTIES, INC. (4.77)
Contract #05173018
Totals905345.3573103.05877610.3096.9

CountyTRAVIS
HighwayFM 969
FromDECKER CREEK DRIVE
ToBASTROP COUNTY LINE
CSJ1186-01-087
Proj IDSTP 2015(277)HES
Work TypePROVIDE ADD'L PAVED SURFACE WIDTH
 
7.1015894316.376163873.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began03-17-15
Work Completed
Time Computed03-17-15
Contract Working Days398
Addl Days Granted0
Working Days Charged385
Percent Time Used96
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
ENVIRONMENTAL SAFETY SERVICES, INC. (7.14)
TRP CONSTRUCTION GROUP, LLC (2.30)
LONE STAR PAVING, INC. (47.54)
Contract #11143219
Totals5894316.370.006163873.4499.9

CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-090
Proj IDPTF 2017(143)
Work TypeREHAB ROADWAY; ADD TWLTL & SHLDRS
 
2.1944540893.021323578.7529.1
CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-096
Proj IDROW 1186-1-96
Work TypeUTILITY ADJUSTMENTS
 
2.1942107410.60107325.005.0
Work Order02-27-17
Work Began06-05-17
Work Completed
Time Computed03-29-17
Contract Working Days321
Addl Days Granted0
Working Days Charged75
Percent Time Used23
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-090
LONE STAR PAVING (15.32)
ESSL,LLC (6.81)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33)
BRYANT & FREY CONSTRUCTION (0.96)
TRP CONSTRUCTION GROUP, LLC (0.48)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.92)
AUSTIN WOOD RECYCLING (0.71)
Contract #01173041
Totals6648303.62149164.101430903.7521.5

CountyWILLIAMSON
HighwayFM 1660
FromFM 973
ToSH 95
CSJ1200-01-023
Proj IDSTP 2017(949)
Work TypeREHAB RDWY
 
3.3434076992.452164136.1453.0
Work Order05-18-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days145
Addl Days Granted0
Working Days Charged86
Percent Time Used59
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-01-023
AWP, INC. (0.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.86)
FLASHER EQUIPMENT COMPANY (1.68)
MURRAY CONSTRUCTION (0.63)
ROADWAY SPECIALTIES, INC. (6.22)
RUCOBA & MAYA CONSTRUCTION (23.18)
AUSTIN WOOD RECYCLING (0.65)
THE DAVEY TREE EXPERT COMPANY (0.07)
TEXAS CUTTING & CORING, INC. (0.09)
Contract #04173229
Totals4076992.45145895.452164136.1453.0

CountyTRAVIS ETC
HighwayFM 973 ETC
From0.1 MI S OF SHADOWGLEN TRL
To0.1 MI N OF SHADOWGLEN TRL
CSJ1200-02-032
Proj IDSTP 2018(084)HES
Work TypeINSTALL INTER FLASHING BEACON
 
9.556878897.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days271
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1200-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173022
Totals878897.950.000.000.0

CountyWILLIAMSON
HighwayFM 972
From0.128 MILES WEST OF CR 150
ToEASTERN CITY LIMITS OF WALBURG
CSJ1202-01-018
Proj IDSTP 1702(334)
Work TypeREHAB PVMNT, ADD SHLDR & SFTY TREAT
 
1.3583320330.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173214
Totals3320330.510.000.000.0

CountyWILLIAMSON
HighwayRM 1431
FromCOTTONWOOD CREEK TR
ToMARKET STREET
CSJ1378-02-038
Proj IDC 1378-2-38
Work TypeWIDEN TO 6-LN DIVIDED ROADWAY
 
1.14212847144.695897484.4545.9
Work Order11-22-16
Work Began02-27-17
Work Completed
Time Computed01-21-17
Contract Working Days333
Addl Days Granted0
Working Days Charged186
Percent Time Used55
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-038
FLASHER EQUIPMENT COMPANY (0.40)
AUSTIN WOOD RECYCLING (0.38)
CKJ TRUCKING (0.27)
ROADWAY SPECIALTIES, INC. (0.64)
GC CARTER CONSTRUCTION COMPANY, LLC (1.39)
BEAIRD DRILLING (2.25)
ROYAL VISTA INC. (12.22)
TEXAS HIGHWAY WALLS (5.78)
OSCAR ORDUNO, INC. (3.48)
AARON CONCRETE CONTRACTORS, L.P. (3.96)
PENHALL COMPANY (3.69)
AUSTIN MATERIALS, LLC (11.34)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13)
(USE 07366)J.R. RAMON & SONS, INC (0.50)
BRICK PAVING PLUS, INC. (0.71)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
CUSTOM TRENCH, INC. (1.10)
CP REBAR AND PT INSTALLATION (0.28)
BREDA COMPANY, INC. (0.38)
TEXOP CONSTRUCTION (0.72)
Contract #10163003
Totals12847144.69458580.995897484.4545.9

CountyLEE
HighwayFM 2239
FromBASTROP COUNTY LINE
ToFM 448
CSJ2098-02-008
Proj IDSTP 2017(323)
Work TypeWIDEN, REPAIR & SEAL COAT
 
4.9412468925.072326712.3594.2
Work Order01-25-17
Work Began02-13-17
Work Completed
Time Computed02-13-17
Contract Working Days128
Addl Days Granted0
Working Days Charged121
Percent Time Used94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2098-02-008
COMEN ENTERPRISE LLC (0.83)
EGGEMEYER LAND CLEARING, LLC (2.77)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.99)
TRP CONSTRUCTION GROUP, LLC (2.33)
NEWMAN & KENG PAVING COMPANY, INC. (3.72)
Contract #12163033
Totals2468925.071088.472326712.3594.2

CountyTRAVIS
HighwayRM 2244
From1000 FT. WEST OF BUCKEYE TRAIL
ToWALSH TARLTON
CSJ2102-01-064
Proj IDROW 2102-1-64
Work TypeUTILITY ADJUSTMENTS
 
1.2307057669.402385282.8233.7
CountyTRAVIS
HighwayRM 2244
From0.1 MILE EAST OF REDBUD TRAIL
To1000 FT. WEST OF BUCKEYE TRAIL
CSJ2102-01-066
Proj IDSTP 1502(598)
Work TypeCONST 4-LN URBAN RDWY W/ CONT LTL
 
1.79921695145.838417558.9538.7
Work Order03-11-16
Work Began11-01-16
Work Completed
Time Computed06-09-16
Contract Working Days524
Addl Days Granted0
Working Days Charged126
Percent Time Used24
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2102-01-064
AUSTIN WOOD RECYCLING (1.55)
BRICK PAVING PLUS, INC. (0.02)
BRYANT & FREY CONSTRUCTION (6.08)
CHLOR-SERV, INC. (0.03)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.61)
OSCAR ORDUNO, INC. (1.35)
GK CONSTRUCTION, LLC (0.10)
SCOTT DERR PAINTING CO, LLC (0.10)
MICKIE SERVICE, INC. (0.28)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (4.09)
LONE STAR PAVING (14.80)
G. CARTER CONSTRUCTION COMPANY, INC. (5.11)
CUSTOM TRENCH, INC. (0.28)
ROYAL VISTA INC. (5.84)
Contract #11153004
Totals28752815.23201628.8110802841.7737.5

CountyWILLIAMSON
HighwayRM 2243
FromNORWOOD W. STREET
ToSS 26
CSJ2103-01-031
Proj IDSTP 2017(573)
Work TypeMILL, SEAL & THIN OVERLAY
 
1.480677720.76656693.6596.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began06-12-17
Work Completed
Time Computed06-12-17
Contract Working Days30
Addl Days Granted0
Working Days Charged15
Percent Time Used50
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2103-01-031
FLASHER EQUIPMENT COMPANY (3.11)
K.L. DURHAM CONSTRUCTION, LLC (7.13)
Contract #02173222
Totals677720.760.00656693.6596.8

CountyWILLIAMSON
HighwayFM 1460
From0.1 MI. N. OF QUAIL VALLEY DRIVE
To0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ2211-02-017
Proj IDSTP 1402(060)
Work TypeCONST 4-LN DIV<L
 
2.02211875032.0610209891.7385.9
CountyWILLIAMSON
HighwayFM 1460
From0.1 MI. N. OF QUAIL VALLEY DRIVE
To0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ2211-02-019
Proj IDHP 2012(774)
Work TypeROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
2.232490003.34547758.0999.9
CountyWILLIAMSON
HighwayFM 1460
From0.6 MI. N OF CR 111 (WESTINGHOUSE)
To0.05 MI. N. OF UNIVERSITY BLVD
CSJ2211-02-026
Proj IDSTP 1402(059)MM
Work TypeCONSTRUCT 4-LANE DIVIDED SECTION
 
1.6009154356.305340855.4558.3
Work Order05-14-15
Work Began02-08-16
Work Completed
Time Computed11-10-15
Contract Working Days390
Addl Days Granted36
Working Days Charged390
Percent Time Used91
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-017
R K STEPHENS CONSTRUCTION, LLC (3.23)
TRP CONSTRUCTION GROUP, LLC (0.25)
FLASHER EQUIPMENT COMPANY (0.08)
AUSTIN WOOD RECYCLING (0.18)
AARON CONCRETE CONTRACTORS, L.P. (4.21)
G. CARTER CONSTRUCTION COMPANY, INC. (3.87)
BREDA COMPANY, INC. (0.10)
BEAIRD DRILLING (0.44)
TEXAS TRUCKING COMPANY, INC. (0.00)
ROADWAY SPECIALTIES, INC. (0.60)
SMITH CONTRACTING, INC., S.A. (0.12)
AUSTIN MATERIALS, LLC (3.37)
PRIMATE CONSTRUCTION, INC. (0.01)
LONE STAR SITEWORK, LLC (0.05)
LONE STAR PAVING (0.12)
GREEN MILLING GROUP (0.09)
Contract #08143204
Totals21519391.70324578.0516098505.2774.8

CountyTRAVIS
HighwayFM 2304
FromAT SLAUGHTER LN
To.
CSJ2689-01-026
Proj IDSTP 1702(681)HES
Work TypeCHANNELIZATION (STRIPING)
 
0.316355908.71155382.7543.6
Work Order09-12-17
Work Began09-25-17
Work Completed
Time Computed09-25-17
Contract Working Days36
Addl Days Granted0
Working Days Charged11
Percent Time Used30
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2689-01-026
LONE STAR PAVING (33.27)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.93)
FLASHER EQUIPMENT COMPANY (9.83)
Contract #08173047
Totals355908.7110347.44155382.7543.6

CountyTRAVIS
HighwaySL 1
FromNORTH OF SLAUGHTER LANE
ToSOUTH OF LACROSSE
CSJ3136-01-015
Proj IDNH 1702(792)
Work TypeGRADE SEPARATION OF MAIN LANES
 
2.06951446533.5836979.000.0
CountyTRAVIS
HighwaySL 1
FromNORTH OF SLAUGHTER LANE
ToSOUTH OF LACROSSE
CSJ3136-01-184
Proj IDROW 3136-1-184
Work TypeUTILITIES
 
2.0692066898.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days740
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-015
BRADCO (2.75)
FLASHER EQUIPMENT COMPANY (0.62)
SCOTT DERR PAINTING CO, LLC (0.12)
TEXAS HIGHWAY WALLS (5.95)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
THE LEVY COMPANY, INC. (4.12)
AARON CONCRETE CONTRACTORS, L.P. (2.67)
ROADWAY SPECIALTIES, INC. (2.16)
AUSTIN WOOD RECYCLING (0.14)
GK CONSTRUCTION, LLC (0.13)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.08)
LONE STAR PAVING (9.80)
Contract #08173009
Totals53513431.9836979.0036979.000.0

CountyTRAVIS
HighwayLP 1
FromNORTH OF LP 360
ToNORTH OF US 290
CSJ3136-01-172
Proj IDC 3136-1-172
Work TypeADD BICYCLE BRIDGE
 
0.4487396549.398667753.9499.9
CountyTRAVIS
HighwayLP 1
FromLP 360
To0.5 MI NORTH OF SOUTHWEST PARKWAY
CSJ3136-01-173
Proj IDC 3136-1-173
Work TypeMILL & OVERLAY FOR RESTRIPE SBML
 
1.050376467.39526416.4599.9
Work Order01-23-14
Work Began02-10-14
Work Completed
Time Computed02-08-14
Contract Working Days549
Addl Days Granted194
Working Days Charged771
Percent Time Used103
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-172
FLASHER EQUIPMENT COMPANY (1.33)
RUSSO CORPORATION (7.36)
ROADWAY SPECIALTIES, INC. (4.32)
AUSTIN WOOD RECYCLING (0.88)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.29)
A BROTHERS (OLD PRIME) (0.21)
APAC-TEXAS, INC. (5.66)
CARMA CONSTRUCTION, LLC (2.31)
CHEROKEE SERVICES (0.32)
THE LEVY COMPANY, L.P. (12.72)
MCL CONTRACTING, LLC (0.45)
R K STEPHENS CONSTRUCTION, LLC (2.38)
SCOTT DERR PAINTING CO, LLC (0.25)
SOUTHEAST GRINDING & GROOVING, LLC (0.04)
TEXAS HIGHWAY WALLS (3.07)
OSCAR ORDUNO, INC. (1.10)
Contract #10133028
Totals7773016.7894622.289194170.3999.9

CountyTRAVIS
HighwayLP 1
FromBARTON CREEK
ToSOUTHWEST PARKWAY
CSJ3136-01-178
Proj IDSTP 2014(561)
Work TypeOVERLAY FRONTAGE ROADS
 
0.501740923.26651115.2787.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-14
Work Began06-26-17
Work Completed
Time Computed06-26-14
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-178
AARON CONCRETE CONTRACTORS, L.P. (1.83)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.19)
DUSTROL, INC. (6.77)
FLASHER EQUIPMENT COMPANY (2.65)
ROADWAY SPECIALTIES, INC. (7.39)
CHEROKEE SERVICES (4.87)
Contract #04143220
Totals740923.260.00651115.2787.8

CountyTRAVIS
HighwayFM 3177
From0.1 MI NORTH OF DAFFAN LN
To0.1 MI SOUTH OF LOYOLA LN
CSJ3277-01-022
Proj IDSTP 2014(116)TE
Work TypeCONSTRUCT SIDEWALKS
 
1.6102045353.102117218.6599.9
Work Order08-05-16
Work Began09-19-16
Work Completed
Time Computed09-04-16
Contract Working Days240
Addl Days Granted0
Working Days Charged239
Percent Time Used99
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3277-01-022
ENVIRONMENTAL SAFETY SERVICES, INC. (12.84)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.44)
VOGES DRILLING CO. (1.25)
LONE STAR PAVING COMPANY (1.55)
L & R FOUNDATION DRILLING, INC. (0.78)
FLASHER EQUIPMENT COMPANY (0.04)
Contract #03163005
Totals2045353.10153597.482117218.6599.9

CountyTRAVIS
HighwayFM 734
FromLP 1
ToSL 275
CSJ3417-01-024
Proj IDNH 2017(793)
Work TypePAVEMENT REPAIR,UNDERSEAL & OVERLAY
 
1.8051497761.601360622.9390.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days71
Addl Days Granted0
Working Days Charged26
Percent Time Used36
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3417-01-024
GREEN MILLING GROUP (5.34)
TRP CONSTRUCTION GROUP, LLC (3.81)
THE LEVY COMPANY, L.P. (4.59)
SCR CIVIL CONSTRUCTION, LLC (1.85)
Contract #03173005
Totals1497761.600.001360622.9390.8

CountyTRAVIS
HighwayFM 734
FromSH 130
To0.17 MI E OF SH 130
CSJ3417-03-023
Proj IDCC 3417-3-23
Work TypeCONSTRUCTION OF MEDIAN AND LTL
 
0.170248444.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days46
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173026
Totals248444.300.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6