Monthly State Let Construction Report For Austin District As Of Nov 22, 2017 Page 6 Of 7

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILLIAMSON
HighwayRM 1431
FromFM 734
ToCR 175
CSJ1378-02-036
Proj IDPTF 2014(560)
Work TypeWIDEN TO 6-LANE URBAN ROADWAY
 
1.49117353255.7519763318.63100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-14
Work Began08-17-14
Work Completed09-20-17
Time Computed06-21-14
Contract Working Days269
Addl Days Granted150
Working Days Charged419
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-036
AARON CONCRETE CONTRACTORS, L.P. (4.48)
ABC EROSION CONTROL, INC. (0.65)
AUSTIN WOOD RECYCLING (0.11)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.30)
FLASHER EQUIPMENT COMPANY (1.47)
G. CARTER CONSTRUCTION COMPANY, INC. (7.06)
GK CONSTRUCTION, LLC (0.07)
KELLYSTONE, INC (0.94)
ROADWAY SPECIALTIES, INC. (2.95)
ROYAL VISTA INC. (16.40)
VOGES DRILLING CO. (0.14)
TEXAS CUTTING & CORING, INC. (0.03)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.25)
SCOTT DERR PAINTING CO, LLC (0.02)
SPEEDY PAVING (0.99)
PRIMATE CONSTRUCTION, INC. (0.02)
FORSYTHE BROTHERS INFRASTRUCTURE, LLC (0.84)
Contract #04143201
Totals17353255.750.0019763318.63100.0

CountyWILLIAMSON
HighwayRM 1431
FromCOTTONWOOD CREEK TR
ToMARKET STREET
CSJ1378-02-038
Proj IDC 1378-2-38
Work TypeWIDEN TO 6-LN DIVIDED ROADWAY
 
1.14212847144.695131924.1939.9
Work Order11-22-16
Work Began02-27-17
Work Completed
Time Computed01-21-17
Contract Working Days333
Addl Days Granted0
Working Days Charged151
Percent Time Used45
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-038
FLASHER EQUIPMENT COMPANY (0.40)
AUSTIN WOOD RECYCLING (0.38)
CKJ TRUCKING (0.27)
ROADWAY SPECIALTIES, INC. (0.64)
GC CARTER CONSTRUCTION COMPANY, LLC (1.39)
BEAIRD DRILLING (2.25)
ROYAL VISTA INC. (12.22)
TEXAS HIGHWAY WALLS (5.78)
OSCAR ORDUNO, INC. (3.48)
AARON CONCRETE CONTRACTORS, L.P. (3.96)
PENHALL COMPANY (3.69)
AUSTIN MATERIALS, LLC (11.34)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13)
(USE 07366)J.R. RAMON & SONS, INC (0.50)
BRICK PAVING PLUS, INC. (0.71)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
CUSTOM TRENCH, INC. (1.10)
CP REBAR AND PT INSTALLATION (0.28)
BREDA COMPANY, INC. (0.38)
TEXOP CONSTRUCTION (0.72)
Contract #10163003
Totals12847144.69771751.455131924.1939.9

CountyBURNET
HighwayRM 1431
From0.155 MI WEST OF RM 1980
To0.084 MI WEST OF PHILLIPS RANCH RD
CSJ1378-04-048
Proj IDSTP 1602(491)
Work TypeMILL, SEAL AND OVERLAY
 
6.4541437078.591408276.6797.9
Work Order11-16-16
Work Began02-28-17
Work Completed
Time Computed02-28-17
Contract Working Days53
Addl Days Granted0
Working Days Charged41
Percent Time Used77
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-04-048
ROADWAY SPECIALTIES, INC. (9.37)
D. I. J. CONSTRUCTION, INC. (5.92)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46)
Contract #09163209
Totals1437078.5932208.761408276.6797.9

CountyBURNET
HighwayRM 1431
FromWEST OF RM 2342
To0.09 MI. EAST OF FM 1980
CSJ1378-04-050
Proj IDSTP 2017(912)HES
Work TypeCONVERT 4-LN UNDIV TO SUPER 2 W/SHL
 
17.900790288.761065960.1999.9
Work Order04-24-17
Work Began06-16-17
Work Completed
Time Computed06-16-17
Contract Working Days19
Addl Days Granted10
Working Days Charged21
Percent Time Used72
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-04-050
D. I. J. CONSTRUCTION, INC. (26.97)
FLASHER EQUIPMENT COMPANY (0.81)
BRYDL CONTRACTING, INC. (0.53)
Contract #03173023
Totals790288.76176517.211065960.1999.9

CountyLEE
HighwayFM 1624
FromSL 123
ToUS 77
CSJ1537-01-016
Proj IDSTP 1602(496)HES
Work TypeIMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
17.8641148468.601101715.46100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began12-14-16
Work Completed11-03-17
Time Computed11-25-16
Contract Working Days108
Addl Days Granted0
Working Days Charged100
Percent Time Used92
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1537-01-016
D & D ENTERPRISES (22.75)
LYNCO CONSTRUCTION (22.75)
Contract #08163047
Totals1148468.600.001101715.46100.0

CountyHAYS
HighwayFM 1626
FromFM 2770
ToIH 35
CSJ1539-03-001
Proj IDSTP 2017(322)
Work TypeREPAIR AND OVERLAY
 
2.9951037967.60837423.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began05-22-17
Work Completed10-12-17
Time Computed05-22-17
Contract Working Days40
Addl Days Granted0
Working Days Charged20
Percent Time Used50
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1539-03-001
DIIBS SPECIALISTS (4.71)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20)
TRP CONSTRUCTION GROUP, LLC (3.07)
GREEN MILLING GROUP (1.30)
Contract #01173033
Totals1037967.600.00837423.75100.0

CountyLEE
HighwayFM 1697
FromFM 141
ToWASHINGTON C/L
CSJ1564-02-010
Proj IDSTP 2017(950)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
6.644455922.00425899.2093.4
Work Order05-11-17
Work Began07-17-17
Work Completed
Time Computed07-10-17
Contract Working Days57
Addl Days Granted0
Working Days Charged53
Percent Time Used92
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1564-02-010
AREA WIDE PROTECTIVE, INC. (11.91)
D&S TEXAS ICON CONSTRUCTION (5.57)
ROADWAY SPECIALTIES, INC. (11.54)
Contract #04173020
Totals455922.0056918.00425899.2093.4

CountyHAYS
HighwayRM 1826
FromTRAVIS COUNTY LINE
ToNUTTY BROWN ROAD
CSJ1754-02-025
Proj IDSTP 1502(597)
Work TypeGRADING, BASE, ACP & PVMNT MARKINGS
 
2.1864013235.583911081.2298.9
Work Order01-22-16
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days252
Addl Days Granted0
Working Days Charged312
Percent Time Used123
Contractor(s)
BPI - BAUERLE PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-025
A BROTHERS MILLING, LLC (0.85)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57)
FLASHER EQUIPMENT COMPANY (0.35)
RAMMING PAVING COMPANY (52.04)
ROADWAY SPECIALTIES, INC. (6.33)
PRO-LINE PAVEMENT MAINTENANCE (0.96)
Contract #08153029
Totals4013235.5823649.353911081.2298.9

CountyLEE
HighwayFM 2239
FromBASTROP COUNTY LINE
ToFM 448
CSJ2098-02-008
Proj IDSTP 2017(323)
Work TypeWIDEN, REPAIR & SEAL COAT
 
4.9412468925.072294823.9192.9
Work Order01-25-17
Work Began02-13-17
Work Completed
Time Computed02-13-17
Contract Working Days128
Addl Days Granted0
Working Days Charged121
Percent Time Used94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2098-02-008
COMEN ENTERPRISE LLC (0.83)
EGGEMEYER LAND CLEARING, LLC (2.77)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.99)
TRP CONSTRUCTION GROUP, LLC (2.33)
NEWMAN & KENG PAVING COMPANY, INC. (3.72)
Contract #12163033
Totals2468925.07218573.222294823.9192.9

CountyTRAVIS
HighwayRM 2244
From1000 FT. WEST OF BUCKEYE TRAIL
ToWALSH TARLTON
CSJ2102-01-064
Proj IDROW 2102-1-64
Work TypeUTILITY ADJUSTMENTS
 
1.2307057669.402218153.8231.4
CountyTRAVIS
HighwayRM 2244
From0.1 MILE EAST OF REDBUD TRAIL
To1000 FT. WEST OF BUCKEYE TRAIL
CSJ2102-01-066
Proj IDSTP 1502(598)
Work TypeCONST 4-LN URBAN RDWY W/ CONT LTL
 
1.79921695145.837815767.9436.0
Work Order03-11-16
Work Began11-01-16
Work Completed
Time Computed06-09-16
Contract Working Days524
Addl Days Granted0
Working Days Charged111
Percent Time Used21
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2102-01-064
AUSTIN WOOD RECYCLING (1.55)
BRICK PAVING PLUS, INC. (0.02)
BRYANT & FREY CONSTRUCTION (6.08)
CHLOR-SERV, INC. (0.03)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.61)
OSCAR ORDUNO, INC. (1.35)
GK CONSTRUCTION, LLC (0.10)
SCOTT DERR PAINTING CO, LLC (0.10)
MICKIE SERVICE, INC. (0.28)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (4.09)
LONE STAR PAVING (14.80)
G. CARTER CONSTRUCTION COMPANY, INC. (5.11)
CUSTOM TRENCH, INC. (0.28)
ROYAL VISTA INC. (5.84)
Contract #11153004
Totals28752815.23685604.4910033921.7634.8

CountyWILLIAMSON
HighwayRM 2243
FromNORWOOD W. STREET
ToSS 26
CSJ2103-01-031
Proj IDSTP 2017(573)
Work TypeMILL, SEAL & THIN OVERLAY
 
1.480677720.76656693.6596.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began06-12-17
Work Completed
Time Computed06-12-17
Contract Working Days30
Addl Days Granted0
Working Days Charged15
Percent Time Used50
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2103-01-031
FLASHER EQUIPMENT COMPANY (3.11)
K.L. DURHAM CONSTRUCTION, LLC (7.13)
Contract #02173222
Totals677720.760.00656693.6596.8

CountyBURNET
HighwayRM 2341
From0.85 MI N OF CR 114
ToSH 29
CSJ2206-01-015
Proj IDSTP 1502(390)HES
Work TypeSAFETY TREATMENTS, ADD PAVE WIDTH
 
5.4003547716.583413233.24100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-11-15
Work Began10-12-15
Work Completed11-15-17
Time Computed10-11-15
Contract Working Days187
Addl Days Granted0
Working Days Charged198
Percent Time Used105
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2206-01-015
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54)
ROADWAY SPECIALTIES, INC. (8.86)
DELGADO"S CONSTRUCTION (1.37)
AUSTIN WOOD RECYCLING (1.73)
LONE STAR PAVING COMPANY (6.71)
INCE ENTERPRISES, INC. (3.53)
Contract #07153212
Totals3547716.580.003413233.24100.0

CountyWILLIAMSON
HighwayFM 1460
From0.1 MI. N. OF QUAIL VALLEY DRIVE
To0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ2211-02-017
Proj IDSTP 1402(060)
Work TypeCONST 4-LN DIV<L
 
2.02211875032.069654301.8081.2
CountyWILLIAMSON
HighwayFM 1460
From0.1 MI. N. OF QUAIL VALLEY DRIVE
To0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ2211-02-019
Proj IDHP 2012(774)
Work TypeROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
2.232490003.34547758.0999.9
CountyWILLIAMSON
HighwayFM 1460
From0.6 MI. N OF CR 111 (WESTINGHOUSE)
To0.05 MI. N. OF UNIVERSITY BLVD
CSJ2211-02-026
Proj IDSTP 1402(059)MM
Work TypeCONSTRUCT 4-LANE DIVIDED SECTION
 
1.6009154356.305101487.6655.7
Work Order05-14-15
Work Began02-08-16
Work Completed
Time Computed11-10-15
Contract Working Days390
Addl Days Granted36
Working Days Charged362
Percent Time Used84
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-017
R K STEPHENS CONSTRUCTION, LLC (3.23)
TRP CONSTRUCTION GROUP, LLC (0.25)
FLASHER EQUIPMENT COMPANY (0.08)
AUSTIN WOOD RECYCLING (0.18)
AARON CONCRETE CONTRACTORS, L.P. (4.21)
G. CARTER CONSTRUCTION COMPANY, INC. (3.87)
BREDA COMPANY, INC. (0.10)
BEAIRD DRILLING (0.44)
TEXAS TRUCKING COMPANY, INC. (0.00)
ROADWAY SPECIALTIES, INC. (0.60)
SMITH CONTRACTING, INC., S.A. (0.12)
AUSTIN MATERIALS, LLC (3.37)
PRIMATE CONSTRUCTION, INC. (0.01)
LONE STAR SITEWORK, LLC (0.05)
LONE STAR PAVING (0.12)
GREEN MILLING GROUP (0.09)
Contract #08143204
Totals21519391.70225731.9915303547.5571.1

CountyBLANCO
HighwayRM 2766
FromUS 281
To0.03 MI E OF RM 3232(END ST MAINT)
CSJ2677-01-008
Proj IDSTP 2015(717)HES
Work TypeGUARDRAIL&SAFETY TREAT FIXED OBJCTS
 
9.194263702.00321247.40100.0
CountyBLANCO
HighwayRM 2766
FromUS 281
To0.03 MILES EAST OF RM 3232
CSJ2677-01-009
Proj IDSTP 2015(718)HES
Work TypePROVIDE ADDITIONAL PAVED SURFACE WI
 
9.1944031197.974906139.86100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-22-15
Work Began06-08-15
Work Completed09-26-17
Time Computed05-08-15
Contract Working Days184
Addl Days Granted104
Working Days Charged306
Percent Time Used106
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2677-01-008
D.I.J. CONSTRUCTION, INC (3.46)
ENVIRONMENTAL SAFETY SERVICES, INC. (6.46)
Contract #03153210
Totals4294899.970.005227387.26100.0

CountyBASTROP
HighwayFM 2571
FromSH 304
ToSH 95
CSJ2686-01-012
Proj IDSTP 2017(792)
Work TypeFULL DEPTH, LEVEL-UP & SEAL COAT
 
14.9791637667.961469369.6889.7
Work Order04-24-17
Work Began05-15-17
Work Completed
Time Computed05-15-17
Contract Working Days43
Addl Days Granted0
Working Days Charged42
Percent Time Used97
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2686-01-012
BROCK CONSTRUCTION, LLC (11.59)
GREEN MILLING GROUP (1.64)
TRP CONSTRUCTION GROUP, LLC (6.56)
Contract #03173235
Totals1637667.9694196.261469369.6889.7

CountyTRAVIS
HighwayFM 2304
FromAT SLAUGHTER LN
To.
CSJ2689-01-026
Proj IDSTP 1702(681)HES
Work TypeCHANNELIZATION (STRIPING)
 
0.316355908.71130035.3136.5
Work Order09-12-17
Work Began09-25-17
Work Completed
Time Computed09-25-17
Contract Working Days36
Addl Days Granted0
Working Days Charged11
Percent Time Used30
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2689-01-026
LONE STAR PAVING (33.27)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.93)
FLASHER EQUIPMENT COMPANY (9.83)
Contract #08173047
Totals355908.71130035.31130035.3136.5

CountyTRAVIS
HighwaySL 1
FromNORTH OF SLAUGHTER LANE
ToSOUTH OF LACROSSE
CSJ3136-01-015
Proj IDNH 1702(792)
Work TypeGRADE SEPARATION OF MAIN LANES
 
2.06951446533.580.000.0
CountyTRAVIS
HighwaySL 1
FromNORTH OF SLAUGHTER LANE
ToSOUTH OF LACROSSE
CSJ3136-01-184
Proj IDROW 3136-1-184
Work TypeUTILITIES
 
2.0692066898.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days740
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173009
Totals53513431.980.000.000.0

CountyTRAVIS
HighwayLP 1
FromNORTH OF LP 360
ToNORTH OF US 290
CSJ3136-01-172
Proj IDC 3136-1-172
Work TypeADD BICYCLE BRIDGE
 
0.4487396549.398573131.6699.9
CountyTRAVIS
HighwayLP 1
FromLP 360
To0.5 MI NORTH OF SOUTHWEST PARKWAY
CSJ3136-01-173
Proj IDC 3136-1-173
Work TypeMILL & OVERLAY FOR RESTRIPE SBML
 
1.050376467.39526416.4599.9
Work Order01-23-14
Work Began02-10-14
Work Completed
Time Computed02-08-14
Contract Working Days549
Addl Days Granted194
Working Days Charged771
Percent Time Used103
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-172
FLASHER EQUIPMENT COMPANY (1.33)
RUSSO CORPORATION (7.36)
ROADWAY SPECIALTIES, INC. (4.32)
AUSTIN WOOD RECYCLING (0.88)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.29)
A BROTHERS (OLD PRIME) (0.21)
APAC-TEXAS, INC. (5.66)
CARMA CONSTRUCTION, LLC (2.31)
CHEROKEE SERVICES (0.32)
THE LEVY COMPANY, L.P. (12.72)
MCL CONTRACTING, LLC (0.45)
R K STEPHENS CONSTRUCTION, LLC (2.38)
SCOTT DERR PAINTING CO, LLC (0.25)
SOUTHEAST GRINDING & GROOVING, LLC (0.04)
TEXAS HIGHWAY WALLS (3.07)
OSCAR ORDUNO, INC. (1.10)
Contract #10133028
Totals7773016.789358.309099548.1199.9

CountyTRAVIS
HighwayLP 1
FromTUSCAN TERRACE AT LOOP 1 (MOPAC)
ToAPPROX 500 FT N. OF BARTON CREEK
CSJ3136-01-174
Proj IDSTP 1402(061)MM
Work TypeCONSTRUCT BICYCLE & PED BRDG (PH 1)
 
0.4982985697.493170429.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-14
Work Began01-26-15
Work Completed11-13-17
Time Computed12-17-14
Contract Working Days250
Addl Days Granted38
Working Days Charged272
Percent Time Used94
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-174
METALINK CORPORATION (0.04)
AVERY"S LAWN CARE & LANDSCAPE (1.55)
GK CONSTRUCTION, LLC (0.27)
D. I. J. CONSTRUCTION, INC. (0.28)
ROADWAY SPECIALTIES, INC. (3.23)
TURNKEY OPERATIONS (0.93)
VOGES DRILLING CO. (1.85)
S & S BRIDGE PAINTING, INC. (0.62)
THE LEVY COMPANY, L.P. (10.22)
Contract #08143214
Totals2985697.490.003170429.41100.0

CountyTRAVIS
HighwayLP 1
FromBARTON CREEK
ToSOUTHWEST PARKWAY
CSJ3136-01-178
Proj IDSTP 2014(561)
Work TypeOVERLAY FRONTAGE ROADS
 
0.501740923.26651115.2787.8
Work Order06-10-14
Work Began06-26-17
Work Completed
Time Computed06-26-14
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-178
AARON CONCRETE CONTRACTORS, L.P. (1.83)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.19)
DUSTROL, INC. (6.77)
FLASHER EQUIPMENT COMPANY (2.65)
ROADWAY SPECIALTIES, INC. (7.39)
CHEROKEE SERVICES (4.87)
Contract #04143220
Totals740923.2611480.20651115.2787.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7