Section 1: Federal Highway Administration Q & A for the DBE Program
Bidders List
Question:
Does your DBE Program create
and maintain a bidders list of all firms who bid and quote and captures
the age and average gross receipts of the firms? (49 CFR 26.11(c))Answer:
You must create and
maintain a bidders list that includes the following: Firm name;
firm’s address; firm’s status as a DBE or non-DBE; Age of the firm;
and annual gross receipts of the firm. The USDOT has given the flexibility
to the State Department of Transportation to determine the most
effective means in capturing this information. Most often the identity
of bidders and quoters is captured through the handling of bidding documents
and/or contract administration procedures. The other information,
age and gross receipts may be captured through surveys and questionnaires
at a later time from the firms once identified.Assurance Statement
Question:
Do all prime and subcontracts
have required DBE program assurance statements incorporated? (49
CFR 26.13(b))Answer:
Each contract a State
Transportation Agency (STA) signs with a contractor and sub-recipient
must have physically incorporated in it the standardized assurance
statement prescribed under 26.13(b) which states that: 1) these
parties will not discriminate based on race, color, national origin,
or sex in the performance of any DOT-assisted contract; 2) The contractor
shall carry out the requirements of 49 CFR 26 in the award and administration of
DOT-assisted contracts; and 3) Failure by the contractor to carry
out these requirements is a material breach of contract, which may
result in contract termination or other remedy as deemed appropriate
by the recipient.Local Agencies
Question:
Does the STA’s DBE program
apply to all sub-recipients? (49 CFR 26.21(a)(1))Answer:
The FHWA’s approval
of STA’s program applies to all of STA’s DOT-assisted programs including
those federal funds transferred to other state and local agencies
(i.e., MPOs, City and County governments) and are expended on federally
assisted contracts.Design-Build Projects
Question:
If a goal has been established
in a design-build project, does the recipient maintain oversight
of the project goal and other requirements? (49 CFR 26.53(e))Answer:
Recipients must maintain
oversight of the developer’s activities to ensure they are conducted
consistent with the requirements of this part. This monitoring is
especially important in the case of a design-build project because
the developer can only provide a plan of action (DBE performance
plan) it intends to take throughout the project since the exact
contracting opportunities and timing of any subsequent awards is
unknown at the start of a design-build.Contract Goals
Question:
Does the STA establish contract
goals based upon factors such as type of work, location, DBE and
availability that cumulatively results in meeting only the portion
of the overall goal that cannot be met through race-neutral means?
(49 CFR 26.51(e)(2))Answer:
Contract goals can
be based upon factors such as type of work, location, and DBE availability.
The goal should essentially represent the percent of the dollar
amount of contracting opportunities for DBEs that exist on that
contract. Goals must be set so they will cumulatively result in
meeting that portion of the overall goal not being met through race-neutral
means.Race–Neutral Participation
Question:
Does the STA count as race-neutral
contracts won by DBE primes, DBE subcontracts when there is no contract
goal, and primes that do not consider DBE status? (49 CFR 26.51(a))Answer:
Contracts won by DBE
primes, DBE subcontracts when there is no contract goal, and DBE
subcontracts where a prime did not consider the DBE status in awarding the
subcontract are all methods of race-neutral DBE participation. The
measurement of when a prime did not consider the firm’s DBE status
in its selection, is to count all work going to a DBE above the
contract goal figure as race-neutral.Question:
Does a DBE have to be certified
with the proper NAICS code if it will be used by the prime contractor
as race-neutral DBE participation?Answer:
DBEs must be certified
in the work categories in which the Prime wants to count that participation
towards the contract goal (race-conscious). However, any work done
by a non-committed (race-neutral) DBE regardless of NAICS codes
should be counted as race-neutral participation provided they are
performing a CUF. Prime contractors may be allowing a DBE to expand
its capabilities on projects, the work is legitimate and the DBE could
then build its resume to expand its NAICS codes in the future.Commitments
Question:
Are all bidders required to
submit DBE information, i.e., name, description of work, and dollar
amount before award of the contract? (49 CFR 26.53(b)(2) and (c))Answer:
Dependent on whether
STA makes the receipt of the information as a matter of responsiveness
or responsibility, you can receive information from all bidders
or just the apparent low bidder. The receipt of this information
in the form of a commitment, when in the presence of a contract
goal, is a condition upon which the award of the contract is given
by the STA.
(As a matter of responsibility, TxDOT receives information from
the apparent low bidder.)Question:
Does the STA require as a condition
of award, the submission DBE information including the name, description
of work, dollar amount, written documentation of commitment, and
written confirmation from the DBE that it is participating in the
contract (49 CFR 26.53(b)(2)(c))Answer:
The STA must make
sure all DBE information is complete and adequately document the
bidder’s good faith efforts as a condition of awarding the contract.Question:
A prime submitted a subcontractor
request document. The District found that three (3) of the items
on the subcontract agreement were less then what was originally
committed. This reduced amount is $43,503.51. Even with this reduction,
the prime contractor is still far over the DBE goal. Can TxDOT accept
the prime contractor’s reduced subcontract amount in this situation?Answer:
Regulations prohibit
the reduction of a submitted DBE commitment without the request
and written approval of the STA. The District should investigate
the matter and contact the DBE to discuss why the subcontract is
less than the commitment (and if they were aware). Depending on
the findings, TxDOT should take appropriate action. At the very
least, if the DBE knew and was ok with the reduction in commitment,
TxDOT should request the Prime contractor to submit something in
writing showing the reduced commitment with reasoning for TxDOT
approval. This will cover both the Prime and TxDOT.Good Faith Efforts – Prior to Contract Execution
Question:
Does the evidence of good faith
efforts provided by the bidder document those efforts to meet the
goal, even though such efforts did not succeed in obtaining enough
DBE participation to do so? (49 CFR 26.53(a)(2))Answer:
The STA must not deny
award of the contract on the basis that the bidder simply failed
to meet the goal if the bidder documents adequate good faith efforts.
The adequate good faith efforts are those the bidder undertook prior
to submitting its bid on the contract.Administrative Consideration
Question:
Does the STA provide an opportunity
for administrative consideration when it determines the apparent
successful bidder failed to meet good faith efforts? (49 CFR 26.53(d))Answer:
The STA should have
an administrative reconsideration process that affords a bidder
the opportunity to seek a further ruling on the adequacy of its
good faith efforts.Question:
Are reconsideration decisions
made by an official who did not take part in the original good faith
effort determinations? (49 CFR 26.53(d)(2))Answer:
An official who did
not take part in the initial determinations by the STA of inadequate
good faith efforts by the bidder must make reconsideration decisions.Determining Credit When a DBE Firm is Ineligible – Prior to Subcontract Execution
Question:
When the prime contractor executes
a subcontract prior to your notification that the DBE firm is ineligible,
do you count the subcontract amount toward the prime contractor’s
goal? (49 CFR 26.87(j)(2))Answer:
If a prime contractor
has executed a subcontract with a DBE firm before you have notified
the firm of its ineligibility, the prime contractor may continue
to use the firm on the contract and my continue to receive credit
toward its DBE goal for the firm’s work.Goal Credit – Materials and Supplies
Question:
Does the STA count towards
the contract goal the value of materials and supplies used on the
contract work only if the DBE is responsible for paying for the
material and supply?
(Factor – joint checks) (49 CFR 26.55(c)(1))Answer:
The DBE must be responsible,
with respect to materials and supplies used on the contract, for
paying for the material. The use of joint checks has been allowed
in the DBE program under certain conditions and/or circumstances.
Even under this situation all payments need to be made by the DBE.Reporting DBE Participation on Contracts With and Without Goals
Question:
Does the STA in its running
tally capture DBE participation on all contracts with or without
contract goals? (49 CFR 26.51(g))Answer:
The STA must report
DBE participation in all contracts with and without contract goals
awarded during the fiscal year in order to effectively adjust due
to both race-neutral and race-conscious achievements to use of contract
goals only as necessary to just meet the annual goal. One important
consideration in being prepared to make such adjustments is to know
the dollar amount that needs to be achieved based on the overall goal
before the contract year begins for comparison purposes against
the actual RC/RN achievements for making the key decision of when
and how much to make any adjustment.Commercially Useful Function
Question:
Does the STA count toward contract
goals the value of work only if the DBE performs a Commercially
Useful Function (CUF) when a DBE is responsible for a distinct element
of the contract work and it carries out its responsibilities by
actually performing, managing and supervising the work involved?
(49 CFR 26.55(c)(1))Answer:
You count the total
contract value of the work the DBE performs itself. The STA needs
to have sufficient resources and procedures that effectively determine
whether a DBE performs a CUF. In addition to this monitoring responsibility,
the STA needs to have appropriate supporting documentation for counting
this work as performed by a DBE.Question:
Does the STA count toward contract
goals the value of work performed by the DBE’s own forces and does
not count the DBE’s cost of equipment leased from the prime contractor
and/or material purchased from the prime contractor? (49 CFR 26.55(a)(1))Answer:
DBE subcontractor’s
purchases of supplies and equipment and leases from the prime contractor
cannot be counted.Question:
Does the STA DBE program require
the DBE to perform at least 30% of its work and does not allow DBEs
to serve as an extra participant in the contract? (49 CFR 26.55(c)(2)(3))Answer:
A DBE is not performing
a CUF when it is not performing the work itself and if the DBE under
this rule subs out more than 70% of the work. There are additional instances
when a DBE could be considered as serving as an extra participant
in the contract or project such as being a pass through in the payment
of materials and supplies.Question:
When a STA presumes a DBE is
not performing a CUF, do they allow the DBE to present evident to
rebut this presumption? (49 CFR 26.55(c)(4))Answer:
The DBE may present
evidence to rebut the presumption of not performing a CUF when a
STA has initially determined that a DBE is not performing a CUF.
The STA must have a CUF reconsideration process established as part
of its normal contract administration procedures.When a DBE Subcontracts its Work to a Non-DBE
Question:
When a DBE subcontracts part
of its work to a non-DBE, does the STA have a mechanism to deduct
that amount from the overall contract goal? (49 CFR 26.55(a)(3))Answer:
Work that a DBE subcontracts
to a non-DBE firm does not count toward DBE goals. The STA’s normal
subcontracting approval procedure is an effective way to monitor such
possible situations. Joint Venture
Question:
In a joint venture does the
STA count only the defined portion of work a DBE performs with its
own forces? (49 CFR 26.55(b))Answer:
Count the dollar value
of the contract equal to the defined portion of the work that the
DBE performs with its own forces toward the DBE goals.Termination / Substitution
Question:
Does the STA have a procedure
that requires STA approval of the substitution and/or replacement
of DBEs for good cause when replacing DBE subcontractors for any
reason?
(49 CFR 26.53(f)(1)&(2))Answer:
The STA must give
written consent prior to a prime contractor terminating a DBE subcontractor
(or an approved substitute DBE firm) when that DBE is either unable or
unwilling to perform the work. There are procedures in some States
that require the DBE to actually signoff on its termination. There
are DBE program rules that effectively prohibit termination for
convenience and then performing the work by the prime itself or use
an affiliate.Question:
Does the STA require prime
contractors to make good faith efforts when replacing DBE subcontractors
for any reason? (49 CFR 26.53(f)(1)&(2)).Answer:
The STA must require
the prime contractors to make good faith efforts to find another
DBE subcontractor to substitute for the original DBE when the DBE
is either unable or unwilling to perform.Counting Credit for Manufacturers, Regular Dealers, Packagers and Brokers
Question:
Does the STA DBE program allow
for appropriate counting for manufacturers, regular dealers and
packagers and brokers? (49 CFR 26.55(e)(1)&(2)(ii)(c))Answer:
If materials and supplies are obtained from a DBE manufacturer,
count 100% of the cost of the materials or supplies.
If materials or supplies are purchased from a DBE regular
dealer, count 60% of the cost of materials or supplies. To be a
regular dealer, the firm must be an established, regular dealer
that engages as its principal business and under its own name, in
the purchase and sale or lease of the products in question.
Packagers, brokers, manufacturers’ representatives, or other
persons who arrange or expedite transactions are not regular dealers.
Often times the definition of what constitutes a manufacturer from
a regular dealer and a regular dealer from a broker becomes a matter of
circumstances of the particular situation and to be determined on
a case-by-case basis.
For example, if the material is crushed aggregate, then in
order to be a manufacturer the firm needs to have the prerequisite
equipment to crush and screen the aggregate for sell pursuant to
the STA’s gradation requirements. If no such process is being performed
by the DBE, but has the necessary distribution equipment to pick
up and drop off as a normal course of business the firm is considered
to be a regular dealer.
Trucking – Counting Credit
Question:
Does the STA DBE program allow
DBE truckers to count leased trucks from DBEs and non-DBE truckers
toward the goal appropriately? (49 CFR 26.55(4)(5))Answer:
The DBE that leases trucks from another DBE receives credit
for the total value of the transportation services the lessee DBE
provides on the contract.
If the STA adopted the revised trucking counting rule in the
June 16, 2003 DBE Program Final Rule, the DBE who leases trucks
from a non-DBE is entitled to credit for the total value of transportation
services provided by non-DBE lessees not to exceed the value of transportation
services provided by DBE-owned trucks on the contract.
Additional participation by non-DBE lessees receives credit
only for the fee or commission it receives as a result of the lease
agreement.
The appropriate Department Operating Administration
must approve this approach.
Goal Credit – Final Compliance (Payment to DBEs)
Question:
Does the STA have a process
to ensure a contractor’s final compliance with DBE obligations based
on payments to the DBEs? (49 CFR 26.55(h))Answer:
Until the amount being
counted has been paid to the DBE, do not count the participation
of a DBE subcontractor toward a contractor’s final compliance with
its DBE obligations on a contract.Joint Checks
Question:
Does the STA count towards
the contract goal the value of materials and supplies used on the
contract work only if the DBE is responsible for paying for the
material and supply?
(Factor – joint checks) (49 CFR 26.55(c)(1))Answer:
The DBE must be responsible,
with respect to materials and supplies used on the contract, for
paying for the material. The use of joint checks has been allowed
in the DBE program under certain conditions and/or circumstances.
Even under this situation all payments need to be made by the DBE.Prompt Payment / Retainage
Question:
Does your DBE program provide
appropriate means to enforce prompt payment and return of retainage?
(49 CFR 26.29(a)(1))Answer:
The STA must have
the necessary mechanisms to monitor and enforce the prime contractor’s
prompt and full payment of retainage. Again, with the flexibility
USDOT built into the program, it was the STA to determine its approach
towards meeting this and other requirements of the program. The
USDOT did not present one prescribed way of meeting it, so there
may be various methods employed by a recipient to meet this requirement.
The most common enforcement practice is for the prime contractor
to provide a payment certification that would certify that all payments
have been made and would normally be submitted with a progress estimate
for payment. The enforcement of this method is through non-payment
of the progress payment, until proper evidence that all previous
payments due are paid.Monitoring - Payments and CUF Reviews
Question:
Does the STA conduct compliance
reviews, audits and/or assessments of all program participants,
(e.g., contractors, and other state and local governments/agencies?
(49 CFR 26.37(a))Answer:
The STA must ensure
that all program participants are in compliance with 49 CFR Part
26. TxDOT must have appropriate mechanisms for monitoring and enforcement set
forth in its DBE program.Question:
Does the STA have a monitoring
and enforcement mechanism that ensures work committed to DBE is
actually performed? (49 CFR 26.37(b))Answer:
The STA must ensure
DBEs do the work committed to them. To ensure this is happening,
the STA must in its normal contract administration take the necessary
steps to compare actual subcontract awards to commitments and payments
to awards.Unified Certification Program
Question:
Does your UCP have a process
to determine specific types of work a potential DBE has the ability
to control and possess the equipment and key personnel to perform
the work?
(49 CFR 26.71(m)(n) & 26.83(c)(4))Answer:
The UCP must have a provision that allows the STA or certifying
agency to consider whether the firm owns equipment necessary to
perform its work. However, the STA or certifying agency must recognize
that leasing equipment is a normal industry practice and should
not use this practice to determine that a DBE owner does not control
his or her company. The STA or certifying agency must make sure
that the leasing of equipment does not involve a relationship with
a prime contractor or other party that compromises the independence
of the firm.
You must grant certification only for specific types of work
in which the socially and economically disadvantaged owner has been
able to demonstrate his or her ability to control the firm. This
specific type of work needs to be clearly defined in forms consistent with
the type of work such firm will be competing to perform. Such designation
as “general contractor” does not fit this definition.
Administrative Remedies
Question:
Does the STA contract provisions
include administrative remedies that will be invoked if prime contractors
fail to comply with good faith efforts? (49 CFR 26.15(b))Answer:
If prime contractors
fail to comply with good faith efforts, the STA contract provisions
must include appropriate administrative remedies that will be invoked.
The most common administrative remedy is to withhold payment to
the prime equal to the short fall that occurred since the prime
failed to comply with the good faith efforts provision. It is not
intended that the STA exercise this oversight activity at the very
end of the contract, but should be monitoring the actual participation
of DBE firms throughout the contract so any necessary adjustments
can be made by the prime in a timely fashion towards meeting the
goal.