Goal Credit – Materials and Supplies
Question:
Does the STA count towards
the contract goal the value of materials and supplies used on the
contract work only if the DBE is responsible for paying for the
material and supply?
(Factor – joint checks) (49 CFR 26.55(c)(1))Answer:
The DBE must be responsible,
with respect to materials and supplies used on the contract, for
paying for the material. The use of joint checks has been allowed
in the DBE program under certain conditions and/or circumstances.
Even under this situation all payments need to be made by the DBE.