Administrative Remedies

Question:
Does the STA contract provisions include administrative remedies that will be invoked if prime contractors fail to comply with good faith efforts? (49 CFR 26.15(b))
Answer:
If prime contractors fail to comply with good faith efforts, the STA contract provisions must include appropriate administrative remedies that will be invoked. The most common administrative remedy is to withhold payment to the prime equal to the short fall that occurred since the prime failed to comply with the good faith efforts provision. It is not intended that the STA exercise this oversight activity at the very end of the contract, but should be monitoring the actual participation of DBE firms throughout the contract so any necessary adjustments can be made by the prime in a timely fashion towards meeting the goal.