Detail Letting Schedule for Garza County (FY 2020)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Garza County (FY 2020) |
CCSJ: 0053-05-052 |
|||
District: | LUBBOCK | Let Date: | Nov 2019 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | NH 2020(168) | CSJ: | 0053-05-052 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | BNSF RR BRIDGE IN POST | Fund Cat: | 1 |
Limits To: | FM 2458 | ESTIMATE: | $2,068,063 |
Length: | 13.5 | Actual | $1,732,307 |
District: | LUBBOCK | Let Date: | Nov 2019 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | NH 2020(168) | CSJ: | 0053-06-030 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | CO |
Limits From: | CR 386 | Fund Cat: | 1 |
Limits To: | SCURRY COUNTY LINE | ESTIMATE: | $1,550,000 |
Length: | 7.6 | Actual | $1 |
District: | LUBBOCK | Let Date: | Nov 2019 |
Highway: | US 62 | Let Status: | Actual |
Project ID: | NH 2020(168) | CSJ: | 0131-01-059 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | EAST 3RD ST | Fund Cat: | 1 |
Limits To: | LUBBOCK CITY LIMITS | ESTIMATE: | $422,150 |
Length: | 2.6 | Actual | $336,031 |
District: | LUBBOCK | Let Date: | Nov 2019 |
Highway: | US 385 | Let Status: | Actual |
Project ID: | STP 2020(169) | CSJ: | 0227-04-021 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | LP 430 | Fund Cat: | 1 |
Limits To: | HOCKLEY C/L | ESTIMATE: | $518,886 |
Length: | 6.7 | Actual | $412,593 |
District: | LUBBOCK | Let Date: | Nov 2019 |
Highway: | FM 1730 | Let Status: | Actual |
Project ID: | NH 2020(168) | CSJ: | 1344-02-028 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SL 289 | Fund Cat: | 1 |
Limits To: | 98TH STREET | ESTIMATE: | $273,960 |
Length: | 2.0 | Actual | $218,673 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0053-05-052 | ||
---|---|---|---|
Length: | 32.4 | ||
Estimate: | $4,833,060 | ||
Actual: | $2,699,605 | ||
CCSJ: 2767-02-004 |
|||
District: | LUBBOCK | Let Date: | Sep 2019 |
Highway: | FM 3519 | Let Status: | Actual |
Project ID: | BR 2020(012) | CSJ: | 2767-02-004 |
Description: | BRIDGE MAINTENANCE | Handling Code: | |
Limits From: | INTERSECTION OF | Fund Cat: | 6 |
Limits To: | GOBBLER CREEK & E OF US 84 | ESTIMATE: | $1,314,086 |
Length: | 0.2 | Actual | $1,306,629 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 2767-02-004 | ||
Length: | 0.2 | ||
Estimate: | $1,314,086 | ||
Actual: | $1,306,629 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |