Letting Schedule for Austin District (FY 2016)
Austin District (FY 2016) |
Bastrop | Blanco | Burnet | Caldwell | Hays | Lee | Llano | Mason | Travis | Williamson | ||||||
Bastrop County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0114-04-068 | US 290 | Actual | FEB 2016 | $2,027,917 | 3 | SAFETY LIGHTING |
0265-03-040 | SH 71 | Actual | MAR 2016 | $579,475 | 6 | UPGRADE BRIDGE AND APPROACH RAILING |
0265-03-047 | SH 71 | Actual | FEB 2016 | $97,196 | 10 | REMOVE DAMAGE CONCRETE RIPRAP, REPLACE STONE PROTECTION |
0265-05-067 | SH 71 | Actual | DEC 2015 | $16,509,209 | 1 | CONSTRUCT OVERPASS AND 4 MAINLANES |
0322-01-048 | SH 95 | Actual | FEB 2016 | $137,764 | 10 | REMOVE DAMAGED CONCRETE, FLOWABLE BACKFILL, TEMPORARY SHORING |
0472-01-041 | SH 21 | Actual | JUN 2016 | $423,191 | 1 | CONVERT 4 - LANE UNDIVIDED TO A MODIFIED SUPER 2 WITH SHOULDER |
0914-18-091 | CS | Actual | AUG 2016 | $529,318 | 6 | REPLACE BRIDGE & APPROACHES |
2176-01-008 | FM 1209 | Actual | JUL 2016 | $1,990,498 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
2686-01-013 | FM 2571 | Actual | FEB 2016 | $360,815 | 10 | EXCAVATION, TEMPORARY SHORING, SOIL NAIL ANCHORS AND SOIL |
Blanco County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0113-05-047 | US 281 | Actual | JAN 2016 | $1,397,340 | 1 | LEVEL UP, SEAL, THIN OVERLAY |
0252-03-051 | US 281 | Actual | AUG 2016 | $896,923 | 8 | CNSTRCT PVD SHLDRS, CORRECT SUPRELV |
0954-02-018 | RM 165 | Actual | FEB 2016 | $3,345,957 | 10 | REPLACE BRIDGE |
0954-02-019 | RM 165 | Actual | FEB 2016 | $199,605 | 10 | STONE RIPRAP REPLACEMENT, REMOVE AND REPLACE MBGF, ONE WAY |
Burnet County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0151-01-050 | SH 29 | Actual | JUL 2016 | $97,200 | 10 | REPLACE RAILROAD GRADE CROSSING |
0252-01-074 | US 281 | Actual | APR 2016 | $2,392,271 | 1 | FULL DEPTH REPAIR, MILL, SEAL AND THIN OVERLAY |
0273-02-023 | US 183 | Actual | SEP 2015 | $2,450,974 | 1 | REPLACE BRIDGE AND APPROACHES |
0700-01-040 | SH 71 | Actual | JUN 2016 | $113,531 | 8 | INSTALL INTERSECTION FLASHING BEACON |
Caldwell County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0152-03-056 | US 183 | Actual | SEP 2015 | $2,746,130 | 6 | REPLACE BRIDGE AND APPROACHES |
0286-02-032 | SH 80 | Actual | DEC 2015 | $349,926 | 8 | INSTALL CONTINUOUS TURN LANE |
0287-01-015 | SH 80 | Actual | OCT 2015 | $2,205,030 | 1 | MILL, SEAL & INLAY |
0471-04-029 | SH 21 | Actual | MAR 2016 | $2,356,388 | 1 | WIDEN AND REHABILITATE ROADWAY |
0914-22-064 | CR | Actual | NOV 2015 | $1,385,690 | 3 | GRADING, ASPHALTIC CEMENT PAVEMENT & MARKINGS FOR CR 110 |
0914-22-068 | CR | Actual | JUL 2016 | $4,879,112 | 3 | GRADING, ASPHALTIC CEMENT PAVEMENT & MARKINGS FOR CR 222 |
1375-01-010 | FM 1322 | Actual | OCT 2015 | $2,572,763 | 1 | ACP, LEVEL - UP, FULL DEPTH REPAIR & SEAL COAT |
1850-01-015 | FM 1966 | Actual | MAY 2016 | $88,314 | 8 | CENTERLINE TEXTURING |
Hays County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0016-02-145 | IH 35 | Actual | DEC 2015 | $8,969,401 | 3 | REVERSE NORTHBOUND & SOUTHBOUND RAMP CONFIGURATION |
0016-03-096 | IH 35 | Actual | JAN 2016 | $1,166,529 | 1 | MILL & INLAY NB & SB FRONTAGE ROADS |
0016-03-101 | IH 35 | Actual | APR 2016 | $386,404 | 1 | MILL & INLAY SOUTHBOUND FRONTAGE ROAD |
0016-03-116 | IH 35 | Actual | AUG 2016 | $58,100 | 10 | MILL AND INLAY, PAVEMENT MARKINGS ON NORTHBOUND FRONTAGE |
0016-03-120 | IH 35 | Actual | JUL 2016 | $36,100 | 10 | REPLACE RAILROAD GRADE CROSSING |
0016-03-121 | IH 35 | Actual | JUL 2016 | $36,100 | 10 | REPLACE RAILROAD GRADE CROSSING |
0113-07-067 | US 290 | Actual | JUL 2016 | $816,443 | 1 | OVERLAY |
0285-03-060 | RM 12 | Actual | FEB 2016 | $669,492 | 10 | BRIDGE STRUCTURE REPAIRS |
0805-01-020 | RM 150 | Actual | OCT 2015 | $4,680,894 | 3 | ADD CENTER TURN LANE AND SHOULDERS |
0805-04-025 | RM 150 | Actual | MAY 2016 | $849,078 | 3 | CONSTRUCT SIDEWALK & BICYCLE LANES IN KYLE TEXAS |
0914-33-071 | CR | Actual | SEP 2015 | $1,532,523 | 6 | REPLACE BRIDGE AND APPROACHES |
1539-01-013 | FM 1626 | Actual | JUN 2016 | $20,562,622 | 3 | RECONSTRUCT TO 4 - LANE W / CONT LTL |
1754-02-026 | RM 1826 | Actual | AUG 2016 | $250,000 | 3 | ADD LEFT TURN LANE |
2293-01-027 | FM 2439 | Actual | NOV 2015 | $274,000 | 1 | RESURFACE ROADWAY |
3210-01-013 | FM 2770 | Actual | OCT 2015 | $839,995 | 1 | RESURFACE ROADWAY |
Lee County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0211-03-036 | US 77 | Actual | MAR 2016 | $876,077 | 1 | LEVEL - UP SEAL COAT & OVERLAY |
1537-01-016 | FM 1624 | Actual | AUG 2016 | $1,148,469 | 1 | IMPROVE GUARDRAIL & SAFETY TREAT FIXED OBJECTS |
Llano County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0700-04-047 | SH 71 | Actual | DEC 2015 | $2,570,877 | 1 | FULL DEPTH, LEVEL UP AND SEAL COAT |
Mason County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0071-05-029 | US 87 | Actual | MAY 2016 | $983,038 | 8 | IMPROVE GUARDRAIL & SAFETY TREAT FIXED OBJECTS |
0149-04-016 | US 377 | Actual | AUG 2016 | $765,168 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS & SAFETY TREAT FIXED |
0150-01-025 | SH 29 | Actual | DEC 2015 | $3,757,542 | 1 | LEVEL UP & SEAL COAT |
0577-01-026 | SH 71 | Actual | APR 2016 | $944,571 | 1 | ADD LEFT TURN LANE & ADD RIGHT TURN ACCELERATION LANE |
Travis County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0015-13-378 | IH 35 | Actual | JUL 2016 | $42,617,265 | ROW | ADD SHOULDERS, AUXILIARY LNS, RAMP IMPROVEMENTS, PAVEMENT |
0015-13-379 | IH 35 | Actual | NOV 2015 | $78,833,227 | ROW | ADD SHOULDERS, AUXILIARY LNS, RAMP IMPROVEMENTS, PAVEMENT |
0015-13-380 | IH 35 | Actual | JUN 2016 | $16,555,013 | ROW | ADD SHOULDERS, AUXILIARY LNS, RAMP IMPROVEMENTS, PAVEMENT |
0015-13-385 | IH 35 | Actual | FEB 2016 | $320,535 | 10 | LANDSCAPING |
0015-13-391 | IH 35 | Actual | DEC 2015 | $412,025 | 1 | INSTALL OVERHEAD BRIDGE DETECTION |
0015-13-405 | IH 35 | Actual | APR 2016 | $848,590 | 1 | FULL DEPTH REPAIR |
0016-01-110 | IH 35 | Actual | JAN 2016 | $2,011,906 | 1 | MILL, SEAL, & OVERLAY FRTG RDS |
0016-01-115 | SL 275 | Actual | FEB 2016 | $293,000 | 6 | UPGRADE BRIDGE AND APPROACH RAILING |
0016-01-117 | IH 35 | Actual | DEC 2015 | $9,232,872 | 8 | BRIDGE REPLACEMENT CROSSING I - 35 |
0113-13-157 | SL 360 | Actual | SEP 2015 | $6,447,812 | 1 | INTERSECTION IMPROVEMENTS |
0114-02-102 | US 290 | Actual | AUG 2016 | $2,645,302 | 3 | CONSTRUCT RIGHT TURN LANE ON SB FRONTAGE RD OF SH 130 AND |
0151-09-036 | US 183 | Actual | AUG 2016 | 629,405,700 | 3 | CONSTRUCT TOLL LANES AND FRONTAGE ROADS |
0152-01-076 | US 183 | Actual | NOV 2015 | $937,585 | 1 | OVERLAY |
0152-01-078 | US 183 | Actual | MAR 2016 | $432,341 | 3 | WIDEN BRIDGE AND INSTALL LEFT TURN LANE |
0683-02-063 | RM 620 | Actual | SEP 2015 | $1,419,536 | 1 | OPERATIONAL IMPROVEMENTS |
0700-03-130 | SH 71 | Actual | APR 2016 | $425,202 | 1 | SEAL & OVERLAY |
0914-00-367 | VA | Actual | SEP 2015 | $278,621 | 1 | FY 2016 SIGNING |
0914-00-368 | VA | Actual | JUL 2016 | $1,041,313 | 1 | FY 2016 SITE - SPECIFIC SIGNALS |
0914-00-369 | VA | Actual | MAR 2016 | $1,104,881 | 1 | FY 2016 NON - SITE SPECIFIC SIGNALS |
0914-00-384 | VA | Actual | DEC 2015 | $50,000,000 | 3 | CONSTRUCT AUSTIN DOWNTOWN STATION AND PURCHASE FOUR (4) |
0914-00-392 | VA | Actual | JUL 2016 | $339,000 | 3 | 2045 REGIONAL ACTIVE TRANSPORTATION PLAN |
0914-04-297 | VA | Actual | FEB 2016 | $172,878 | 10 | MILL AND OVERLAY TPWD HEADQUARTER ENTRANCE ROAD |
0914-04-298 | VA | Actual | JUL 2016 | $1,177,598 | 10 | LANDSCAPING AND IRRIGATION |
1186-01-089 | FM 969 | Actual | MAR 2016 | $2,067,552 | 1 | MILL, SEAL & TY D OVERLAY |
1378-01-036 | RM 1431 | Actual | AUG 2016 | $1,136,825 | 1 | IMPRV GRDRAIL & SAFETY TREAT OBJECTS |
2102-01-066 | RM 2244 | Actual | NOV 2015 | $28,752,815 | ROW | CONST 4 - LN URBAN RDWY W / CONT LTL |
3136-01-161 | SL 1 | Actual | SEP 2015 | $1,080,840 | 1 | SEAL & THIN OVERLAY |
3136-01-177 | SL 1 | Actual | FEB 2016 | $787,594 | 1 | OVERLAY FRONTAGE ROADS |
3277-01-022 | FM 3177 | Actual | MAR 2016 | $2,045,353 | 3 | CONSTRUCT SIDEWALKS |
3417-01-028 | FM 734 | Actual | FEB 2016 | $839,341 | 3 | CONSTRUCT TURN LANES AND SIGNAL |
Williamson County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0015-08-146 | IH 35 | Actual | JUL 2016 | $730,891 | 10 | LANDSCAPING AND IRRIGATION |
0015-09-173 | IH 35 | Actual | DEC 2015 | $28,127,004 | ROW | ADDITION OF SHOULDERS, AUXILIARY LANES, RAMP IMPROVEMENTS, |
0015-09-180 | IH 35 | Actual | JUN 2016 | $9,242,850 | ROW | RAMPS REVERSALS |
0151-08-008 | SL 332 | Actual | JUL 2016 | $72,000 | 10 | REPLACE RAILROAD GRADE CROSSING |
0204-01-067 | US 79 | Actual | JUL 2016 | $265,696 | 1 | MEDIAN MODIFICATIONS |
0320-03-093 | SH 95 | Actual | JUL 2016 | $1,507,709 | 3 | CONSTRUCT PEDESTRIAN AND BIKE PATH |
0320-03-095 | SH 95 | Actual | DEC 2015 | $861,567 | 1 | LEVEL UP & SEAL COAT |
0337-01-036 | SH 29 | Actual | APR 2016 | $662,749 | 1 | OVERLAY |
0337-01-038 | SH 29 | Actual | JAN 2016 | $2,014,970 | 1 | UNDERSEAL & THIN OVERLAY |
0337-02-041 | SH 29 | Actual | JAN 2016 | $1,499,000 | 1 | UNDERSEAL & THIN OVERLAY |
0440-02-015 | SH 195 | Actual | SEP 2015 | $520,095 | 3 | CONSTRUCT MEDIAN AND LEFT TURN LANES |
0914-05-188 | CS | Actual | JUL 2016 | $263,500 | 3 | WILLIAMS DRIVE CORRIDOR & CENTERS PLAN FOR MULTIMODAL AND |
1202-01-017 | FM 972 | Actual | SEP 2015 | $4,156,414 | 1 | REHABILITATE PAVEMENT, ADD SHOULDERS & SAFETY TREAT |
1202-03-016 | FM 1063 | Actual | FEB 2016 | $89,906 | 10 | RIPRAP AND EDGE REPAIR |
1378-02-048 | RM 1431 | Actual | JUN 2016 | $286,219 | 3 | CONSTRUCT SIDEWALK & PEDESTRIAN BRIDGE |
1566-01-014 | FM 1660 | Actual | AUG 2016 | $1,511,340 | 3 | CONSTRUCT PEDESTRIAN AND BIKE PATH |
|