Letting Schedule for Laredo District (FY 2008)
Letting Schedule for Laredo District (FY 2008) | ||||
Last Update: Monday, February 2, 2009 |
Laredo District (FY 2008) |
Dimmit | Duval | Kinney | La Salle | Maverick | Val Verde | Webb | Zavala | ||||||
Dimmit County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0963-01-025 | FM 190 | Actual | SEP 2007 | $2,785,601 | 11 | RESTORATION OF AN EXISTING HIGHWAY |
2636-02-007 | FM 2644 | Actual | SEP 2007 | $6,353,642 | 1 | REHABILITATION OF AN EXISTING HIGHWAY |
Duval County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0623-02-025 | SH 339 | Actual | NOV 2007 | $7,208,950 | 1 | RESTORATION OF AN EXISTING HIGHWAY |
1083-02-014 | FM 716 | Actual | SEP 2007 | $2,356,106 | 1 | REHABILITATION OF AN EXISTING HIGHWAY AND ADD SHOULDERS |
1982-01-016 | FM 1329 | Actual | MAR 2008 | $1,035,735 | 11 | RESTORATION OF AN EXISTING HIGHWAY |
Kinney County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
1814-01-010 | FM 1908 | Actual | JAN 2008 | $3,559,817 | 11 | RESTORATION OF AN EXISTING ROADWAY |
La Salle County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0018-02-052 | IH 35 | Actual | DEC 2007 | $6,443,077 | 1 | FOR THE CONSTRUCTION OF SEAL COAT TYPE OF WORK |
0483-01-039 | SH 97 | Actual | JAN 2008 | $3,010,300 | 1 | RESTORATION OF AN EXISTING HIGHWAY |
Maverick County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0276-01-033 | US 57 | Actual | MAR 2008 | $7,139,448 | 10 | WIDEN RDWY TO PROVIDE PASSING LANES (SUPER 2) |
Val Verde County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0022-06-046 | US 90 | Actual | JAN 2008 | $4,259,434 | 6 | FOR THE CONSTRUCTION OF THE REHABILITATION OF A |
0160-06-022 | US 277 | Actual | OCT 2007 | $2,272,431 | 1 | REHABILITATION OF AN EXISTING ROADWAY |
0922-11-019 | CR | Actual | MAR 2008 | $2,583,768 | 10 | FOR THE CONSTRUCTION OF A 2 LANE UNDIVIDED SECTION |
Webb County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0922-33-077 | CR | Actual | OCT 2007 | $738,793 | 6 | FOR THE CONSTRUCTION OF THE REPLACEMENT OF AN EXISTING |
0922-33-121 | CS | Actual | JUL 2008 | $200,000 | 8 | INSTALLATION OF RAILROAD SIGNALS |
2022-01-010 | SH 44 | Actual | NOV 2007 | $3,634,959 | 11 | REHABILITATION OF AN EXISTING ROADWAY |
Zavala County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0276-04-022 | US 57 | Actual | OCT 2007 | $7,190,083 | 1 | WIDEN RDWY TO PROVIDE PASSING LANES (SUPER 2) |
|
|