Monthly State Let Construction Report For Paris District As Of Mar 11, 2021 Page 1 Of 3

Last Update: Wednesday, March 17, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUNT
HighwaySH 66
FromAT FM 1570
To.
CSJ0009-06-053
Proj IDSTP 2B20(141)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.424523372.14119957.6022.9
Work Order09-23-20
Work Began11-02-20
Work Completed
Time Computed10-23-20
Contract Working Days64
Addl Days Granted0
Working Days Charged39
Percent Time Used60
Contractor(s)
PAVECON LTD. CO.
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-053
J & M CONTRACTING, COMPANY (4.92)
STATEWIDE SAFETY SYSTEMS (2.90)
FORTSON CONTRACTING, INC. (4.16)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.81)
TRP CONSTRUCTION GROUP, LLC (2.70)
MARCOM"S MOWING SERVICE, LLC (2.29)
MEADE SERVICING GROUP, INC. (1.25)
Contract #08203047
Totals523372.1471777.60119957.6022.9

CountyHOPKINS
HighwayIH 30
FromAT RILEY CREEK, LINDLEY CREEK,
ToAND ELM CREEK
CSJ0009-09-103
Proj IDBR 2B20(252)
Work TypeBRIDGE MAINTENANCE
 
0.114195740.000.000.0
CountyHOPKINS
HighwayIH 30
FromAT SH 154 AND AT ROCK CR RELIEF #1
To.
CSJ0010-02-097
Proj IDBR 2B20(252)
Work TypeBRIDGE MAINTENANCE
 
0.11941347.500.000.0
CountyHOPKINS
HighwayIH 30
FromAT CANEY CREEK BRANCH, DRAW CREEK
ToAND ELAINE'S CREEK
CSJ0610-01-043
Proj IDBR 2B20(252)
Work TypeBRIDGE MAINTENANCE
 
0.114160050.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09203223
Totals397137.500.000.000.0

CountyHOPKINS
HighwayIH 30
FromHUNT COUNTY LINE
ToTEXAS STREET
CSJ0009-09-106
Proj IDSTP 1902(034)HES
Work TypeSFT
 
14.8041555777.001586312.2599.9
CountyHOPKINS
HighwayIH 30
FromTEXAS STREET
ToCANEY CREEK
CSJ0010-02-099
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.7021169023.001163944.7599.5
CountyHOPKINS
HighwayIH 30
FromCANEY CREEK
ToFRANKLIN COUNTY LINE
CSJ0610-01-046
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.055369910.25290611.2578.5
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE
ToTITUS COUNTY LINE
CSJ0610-02-057
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.597857829.00747713.5087.1
Work Order07-16-19
Work Began09-03-19
Work Completed
Time Computed08-15-19
Contract Working Days182
Addl Days Granted44
Working Days Charged217
Percent Time Used96
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-106
CANNON ASPHALT GROUP LLC (7.77)
Contract #06193221
Totals3952539.25102150.003788581.7595.8

CountyHOPKINS ETC
HighwayIH 30 ETC
FromS FR AT FM 499
ToSH 19
CSJ0009-09-107
Proj IDNH 2020(392)
Work TypeSEAL COAT
 
386.29311119928.7310584735.0595.1
Work Order02-19-20
Work Began05-18-20
Work Completed
Time Computed03-20-20
Contract Working Days67
Addl Days Granted0
Working Days Charged49
Percent Time Used73
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-107
INNOVATIVE ROADWAY SOLUTIONS, LLC (12.22)
CENTERLINE TECHNOLOGIES, LLC (17.98)
LINEAR TRAFFIC MARKINGS LLC (0.69)
RED SIXTEEN CONSTRUCTION, INC (0.62)
FLAT LINE, INC. (0.00)
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (0.00)
Contract #12193009
Totals11119928.730.0010584735.0595.1

CountyHUNT ETC
HighwayIH 30 ETC
FromROCKWALL COUNTY LINE (N FR)
ToMONTY STRATTON (N FRONTAGE RD)
CSJ0009-13-176
Proj IDNH 2021(155)
Work TypeSEAL COAT
 
223.57910775428.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-176
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12203005
Totals10775428.360.000.000.0

CountyHUNT
HighwayUS 69
FromSH 66
ToFM 1570
CSJ0009-15-028
Proj IDSTP 2020(828)HES
Work TypeTRAFFIC CONTROL DEVICES
 
4.001318721.00179614.5056.3
CountyHUNT
HighwaySH 34
FromPANTHER PATH
ToSS 264
CSJ0173-06-049
Proj IDSTP 2020(828)HES
Work TypeTRAFFIC CONTROL DEVICES
 
1.999107968.0050831.0047.0
CountyHUNT
HighwaySH 34
FromSTANFORD
ToFM 1570
CSJ0173-07-057
Proj IDSTP 2020(828)HES
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
3.442472924.68145125.8030.6
CountyHUNT
HighwayUS 69
FromUS 380
ToSH 66
CSJ0202-10-025
Proj IDSTP 2020(828)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.395127835.0064056.3050.1
Work Order07-20-20
Work Began11-02-20
Work Completed
Time Computed10-19-20
Contract Working Days150
Addl Days Granted0
Working Days Charged61
Percent Time Used40
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-15-028
THOMAS 11 DEVELOPMENT LLC (6.61)
TX DOWN UNDER CONSTRUCTION, LLC (0.45)
RGJ SERVICES, LLC (1.91)
ACT SAW CUTTING & REMOVAL (0.00)
Contract #05203017
Totals1027448.6895632.00439627.6042.7

CountyHUNT
HighwayFM 499
FromAT LYNN CREEK
To.
CSJ0009-22-005
Proj IDBR 2B20(256)
Work TypeBRIDGE REPLACEMENT
 
0.130620676.47501721.5580.8
Work Order10-21-20
Work Began11-20-20
Work Completed
Time Computed11-20-20
Contract Working Days96
Addl Days Granted0
Working Days Charged42
Percent Time Used43
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-22-005
LINEAR TRAFFIC MARKINGS LLC (0.65)
DUSTIN ALLEN, INC. (6.02)
TEXAS TRAFFIC AND BARRICADE, LLC (0.79)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.60)
PEACHTREE CONSTRUCTION, LTD. (7.95)
TEXOP CONSTRUCTION (1.02)
TORO BRAVO CONSTRUCTION, LLC (0.32)
PENHALL COMPANY (0.56)
Contract #09203023
Totals620676.47167946.55501721.5580.8

CountyHOPKINS
HighwayIH 30
FromSL 301
ToCANEY CREEK
CSJ0010-02-096
Proj IDNH 2021(158)
Work TypeOVERLAY
 
7.4905239464.320.000.0
CountyHOPKINS
HighwayIH 30
FromCANEY CREEK BRIDGE
ToFANKLIN COUNTY LINE
CSJ0610-01-044
Proj IDNH 2021(158)
Work TypeOVERLAY
 
7.9035210463.110.000.0
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE
ToTITUS COUNTY LINE
CSJ0610-02-058
Proj IDNH 2021(158)
Work TypeOVERLAY
 
10.672448130.710.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-21
Work Began00-00-00
Work Completed
Time Computed03-15-21
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-02-096
BARRICADES UNLIMITED (0.12)
TEXOP CONSTRUCTION (10.61)
STRIPING TECHNOLOGY, L.P. (2.23)
WINDING ROAD CONSTRUCTION, INC. (1.90)
WEST TEXAS ROCK RESOURCES, LLC (0.20)
Contract #12203207
Totals10898058.140.000.000.0

CountyGRAYSON ETC
HighwaySH 56 ETC
FromWHITESBORO CITY LIMITS
ToWEST OF DAGNAN RD
CSJ0045-02-039
Proj IDSTP 2B20(143)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.8011769871.501127905.5363.7
Work Order09-18-20
Work Began10-12-20
Work Completed
Time Computed10-19-20
Contract Working Days96
Addl Days Granted0
Working Days Charged63
Percent Time Used65
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-02-039
BRYDL CONTRACTING, INC. (5.30)
Contract #08203241
Totals1769871.5025132.841127905.5363.7

CountyLAMAR ETC
HighwayUS 82 ETC
FromUS 271
ToFM 1508
CSJ0045-09-104
Proj IDSTP 2020(829)HES
Work TypeTRAFFIC CONTROL DEVICES
 
10.877951964.032100.000.2
Work Order07-20-20
Work Began11-17-20
Work Completed
Time Computed10-19-20
Contract Working Days270
Addl Days Granted0
Working Days Charged29
Percent Time Used10
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-09-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05203026
Totals951964.030.002100.000.2

CountyLAMAR
HighwayBU 82-H
From0.1 MI W OF FM 79
To0.1 MI E OF 33RD SE ST
CSJ0045-09-105
Proj IDSTP 2020(939)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.755737000.00790092.7299.9
CountyFANNIN
HighwaySH 78
From0.1 MI N OF US 82
To0.1 MI S OF SH 56
CSJ0279-02-047
Proj IDSTP 2020(939)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.10265170.000.000.0
CountyFANNIN
HighwaySH 121
From0.1 MI W OF W RUSSELL ST
To0.1 MI E OF SH 56
CSJ0549-01-039
Proj IDSTP 2020(939)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.77081680.000.000.0
Work Order09-02-20
Work Began12-09-20
Work Completed
Time Computed12-01-20
Contract Working Days85
Addl Days Granted0
Working Days Charged41
Percent Time Used48
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0045-09-105
FLEX SUPPLY, LLC (1.01)
Contract #07203236
Totals883850.00119749.96790092.7289.3

CountyRED RIVER ETC
HighwayUS 82 ETC
From0.903 MI W OF SH 37
ToSH 37
CSJ0045-12-087
Proj IDSTP 2B20(147)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.3192627582.90556889.7021.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began10-21-20
Work Completed
Time Computed00-00-00
Contract Working Days218
Addl Days Granted0
Working Days Charged37
Percent Time Used16
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-12-087
FLEX SUPPLY, LLC (0.63)
A. E. MOORE CONSTRUCTION, INC. (3.89)
DUSTIN ALLEN, INC. (0.00)
Contract #08203235
Totals2627582.905000.00556889.7021.1

CountyLAMAR ETC
HighwayFM 1510 ETC
FromFM 38
ToUS 82
CSJ0045-15-012
Proj IDSTP 2020(394)
Work TypeSEAL COAT
 
64.3412390010.192352439.8098.4
Work Order01-14-20
Work Began08-03-20
Work Completed
Time Computed02-13-20
Contract Working Days20
Addl Days Granted0
Working Days Charged18
Percent Time Used90
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0045-15-012
INNOVATIVE ROADWAY SOLUTIONS, LLC (2.89)
CENTERLINE TECHNOLOGIES, LLC (5.56)
RED SIXTEEN CONSTRUCTION, INC (0.94)
BARRICADES PLUS, LLC (1.73)
Contract #12193024
Totals2390010.1914980.002352439.8098.4

CountyGRAYSON
HighwayUS 82
FromFM 131
ToFM 1897
CSJ0045-19-053
Proj IDSTP 1802(488)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
12.5721489216.501760081.7399.9
CountyGRAYSON
HighwayUS 69
FromUS 75
To0.148 MI N OF FM 120
CSJ0047-01-062
Proj IDSTP 1802(489)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
2.954317399.00514710.2299.9
CountyGRAYSON
HighwayUS 69
FromSS 503
ToUS 82
CSJ0410-01-029
Proj IDSTP 1802(489)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
10.1331369065.001715731.9499.9
CountyGRAYSON
HighwayUS 69
FromUS 82
ToSH 56
CSJ0410-02-032
Proj IDSTP 1802(489)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
1.700285764.50356856.5699.9
Work Order01-02-19
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days140
Addl Days Granted185
Working Days Charged293
Percent Time Used90
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-053
LYNCO CONSTRUCTION (6.54)
JR WEST TEXAS CONCRETE LLC (7.44)
COMEN ENTERPRISE LLC (2.82)
WEBBER, LLC (4.71)
ADRIAN CONTRACTING (0.00)
Contract #08183023
Totals3461445.000.004347380.4599.9

CountyFANNIN
HighwayUS 82
From0.5 MILES WEST OF SH 121
ToSH 78 (0.478 MI EAST OF SH 78)
CSJ0045-20-018
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.03112156062.2411251294.4592.5
CountyFANNIN
HighwayUS 82
From0.478 MI E OF SH 78
ToFM 100
CSJ0045-21-011
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
14.48749116732.2345825997.7993.3
CountyFANNIN
HighwayUS 82
FromFM 100
To0.5 MILES EAST OF SH 56
CSJ0045-21-012
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.63610365091.2610046851.8296.9
Work Order08-24-18
Work Began10-18-18
Work Completed
Time Computed09-24-18
Contract Working Days928
Addl Days Granted0
Working Days Charged698
Percent Time Used75
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-018
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.13)
W.O.E. CONSTRUCTION (0.70)
STRIPING TECHNOLOGY, L.P. (0.83)
LYON BARRICADE AND CONSTRUCTION CO. (0.20)
HAMMETT EXCAVATION, INC. (23.92)
TEXAS SHAFTS, INC. (0.93)
BOWMAN ENGINEERING & CONSULTING, INC. (0.16)
MCL CONTRACTING, LLC (0.06)
RAMBO CONTRACTING, INC. (3.95)
CDM HOLDINGS, LLC (3.64)
GANT CONTRACTORS, INC. (0.11)
SOUTHERN CROSS CONTRACTORS, LLC (0.61)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.50)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.05)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.38)
ALTUS TRAFFIC MANAGEMENT LLC (0.04)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
TEXOP CONSTRUCTION (0.03)
WOOD WATERING SERVICE LLC (0.00)
WITHERS CONSTRUCTION, LLC (0.37)
O. TREVINO CONSTRUCTION, LLC (0.12)
AIMS COMPANIES (0.18)
Contract #07183002
Totals71637885.731727951.9667124144.0693.6

CountyRED RIVER
HighwayUS 82
FromBU 82 J
ToBOWIE COUNTY LINE
CSJ0046-01-064
Proj IDNH 2019(724)
Work TypeWIDEN NON-FREEWAY
 
16.88513814948.616136682.7744.4
CountyRED RIVER
HighwayUS 82
FromFM 1159
ToBU 82 J
CSJ0046-10-001
Proj IDNH 2019(724)
Work TypeWIDEN NON-FREEWAY
 
0.855387212.9514444.713.7
Work Order05-09-19
Work Began08-26-19
Work Completed
Time Computed07-08-19
Contract Working Days367
Addl Days Granted20
Working Days Charged230
Percent Time Used59
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-064
J. H. ODEN CONTRACTING COMPANY (0.83)
WITHERS CONSTRUCTION, LLC (1.85)
JM YANEZ CONSTRUCTION, INC. (5.41)
DUSTIN ALLEN, INC. (1.92)
FARR FOUNDATION, INC. (0.76)
D. L. LENNON INCORPORATED - CONTRACTOR (10.73)
TEX OP CONSTRUCTION, LP (2.35)
LYON BARRICADE & CONSTRUCTION CO. (0.34)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.31)
SOUTHERN CROSS CONTRACTORS, LLC (0.16)
STRIPING TECHNOLOGY, L.P. (1.34)
INDUSTRIAL FABRICS, INC. (1.30)
Contract #04193007
Totals14202161.56275622.416151127.4843.3

CountyGRAYSON
HighwayUS 69
FromAT RED RIVER (SB & NB)
To.
CSJ0047-01-063
Proj IDBR 2021(048)
Work TypeBRIDGE MAINTENANCE
 
0.3111354337.450.000.0
Work Order11-19-20
Work Began02-24-21
Work Completed
Time Computed02-17-21
Contract Working Days123
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0047-01-063
WEST TEXAS ROCK RESOURCES, LLC (0.40)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.38)
SOUTHERN CROSS CONTRACTORS, LLC (2.38)
STRIPING TECHNOLOGY, L.P. (4.59)
TEXAS CUTTING & CORING GP, INC. (0.00)
ADCOCK 4 INVESTMENTS, LLC (2.87)
Contract #10203221
Totals1354337.450.000.000.0

CountyGRAYSON
HighwayUS 75
FromSH 91
To0.651 MI S OF CENTER STREET
CSJ0047-02-150
Proj IDNH 2020(008)
Work TypeWIDEN FREEWAY
 
4.763154683155.2948106051.0131.0
Work Order10-10-19
Work Began01-13-20
Work Completed
Time Computed11-11-19
Contract Working Days827
Addl Days Granted87
Working Days Charged299
Percent Time Used32
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0047-02-150
TOTAL HIGHWAY MAINTENANCE, LLC (1.02)
J. H. ODEN CONTRACTING COMPANY (0.14)
MICA CORPORATION (4.27)
A BROTHERS MILLING, LLC (0.29)
DURABLE SPECIALTIES, INC. (1.89)
PREMIER PAVING, LTD. (9.00)
ANCORTEX, INC. (2.99)
W.O.E. CONSTRUCTION, INC. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
ANTIGO CONSTRUCTION, INC. (0.00)
ROYAL REBAR (0.00)
SCOTT DERR PAINTING CO, LLC (0.06)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.79)
FORTSON CONTRACTING, INC. (0.31)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
Contract #09193201
Totals154683155.292498955.7248106051.0131.0

CountyGRAYSON
HighwaySS 503 ETC
FromFANNIN ST
ToW COFFIN ST
CSJ0047-02-154
Proj IDSTP 2021(104)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.9581257374.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-11-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0047-02-154
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11203023
Totals1257374.000.000.000.0

CountyGRAYSON
HighwayUS 75
From0.6 MILES N OF RANDALL LAKE ROAD
To0.4 MILES S OF RANDALL LAKE ROAD
CSJ0047-18-081
Proj IDNH 2017(244)
Work TypeREPAIR SLOPE FAILURE AND ROADWAY
 
1.0001629373.401736643.3199.9
Work Order04-16-19
Work Began05-16-19
Work Completed
Time Computed05-16-19
Contract Working Days213
Addl Days Granted0
Working Days Charged194
Percent Time Used91
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-081
RELIANT HAULERS LLC (0.05)
STRIPING TECHNOLOGY, L.P. (0.34)
CHAMPION FUEL SOLUTIONS (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.00)
Contract #03193024
Totals1629373.400.001736643.3199.9