Monthly State Let Construction Report For Paris District As Of Jul 18, 2022 Page 1 Of 3

Last Update: Monday, July 18, 2022
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUNT ETC
HighwaySH 66 ETC
FromFM 6
ToUS 69
CSJ0009-06-052
Proj IDF 2022(196)
Work TypeSEAL COAT
 
12207435.853747631.4330.6
Work Order04-06-22
Work Began04-14-22
Work Completed
Time Computed04-01-22
Contract Working Days141
Addl Days Granted0
Working Days Charged69
Percent Time Used48
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-052
KITECO PROPERTY SOLUTIONS INC. (0.89)
STRIPE-A-ZONE, LLC (10.60)
INNOVATIVE ROADWAY SOLUTIONS, LLC (8.06)
Contract #12213004
Totals12207435.852102663.483747631.4330.6

CountyHUNT
HighwaySH 66
FromSH 66
ToAT FM 1570
CSJ0009-06-054
Proj IDF 2022(549)
Work TypeTRAFFIC CONTROL DEVICES
 
0.100408232.200.000.0
CountyHUNT
HighwaySH 34
From645' N OF FM 1570 INTERSECTION
To1050' S OF FM 1570 INTERSECTION
CSJ0173-07-061
Proj IDF 2022(389)
Work TypeTRAFFIC CONTROL DEVICES
 
0.322860033.150.000.0
CountyHUNT
HighwayFM 1903
FromAT FM 1903
To.
CSJ1496-02-019
Proj IDF 2022(419)
Work TypeTRAFFIC CONTROL DEVICES
 
0.080373766.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-14-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days115
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06223243
Totals1642031.500.000.000.0

CountyHUNT
HighwaySS 302 ETC
FromSH 34
ToFM 499
CSJ0009-07-043
Proj IDF 2022(421)
Work TypeOVERLAY
 
7.9904906019.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-07-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223015
Totals4906019.960.000.000.0

CountyHOPKINS
HighwayIH 30
FromAT RILEY CREEK, LINDLEY CREEK,
ToAND ELM CREEK
CSJ0009-09-103
Proj IDBR 2B20(252)
Work TypeBRIDGE MAINTENANCE
 
0.114195740.00191390.0097.7
CountyHOPKINS
HighwayIH 30
FromAT SH 154 AND AT ROCK CR RELIEF #1
To.
CSJ0010-02-097
Proj IDBR 2B20(252)
Work TypeBRIDGE MAINTENANCE
 
0.11941347.5037962.5091.8
CountyHOPKINS
HighwayIH 30
FromAT CANEY CREEK BRANCH, DRAW CREEK
ToAND ELAINE'S CREEK
CSJ0610-01-043
Proj IDBR 2B20(252)
Work TypeBRIDGE MAINTENANCE
 
0.114160050.00139030.0086.8
Work Order10-21-20
Work Began04-19-21
Work Completed
Time Computed11-20-20
Contract Working Days70
Addl Days Granted0
Working Days Charged32
Percent Time Used45
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09203223
Totals397137.500.00368382.5092.7

CountyHOPKINS
HighwayIH 30
FromHUNT COUNTY LINE
ToTEXAS STREET
CSJ0009-09-106
Proj IDSTP 1902(034)HES
Work TypeSFT
 
14.8041555777.001633262.2599.9
CountyHOPKINS
HighwayIH 30
FromTEXAS STREET
ToCANEY CREEK
CSJ0010-02-099
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.7021169023.001212094.7599.9
CountyHOPKINS
HighwayIH 30
FromCANEY CREEK
ToFRANKLIN COUNTY LINE
CSJ0610-01-046
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.055369910.25361736.2597.7
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE
ToTITUS COUNTY LINE
CSJ0610-02-057
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.597857829.00941088.5099.9
Work Order07-16-19
Work Began09-03-19
Work Completed
Time Computed08-15-19
Contract Working Days182
Addl Days Granted44
Working Days Charged220
Percent Time Used97
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-106
CANNON ASPHALT GROUP LLC (7.77)
Contract #06193221
Totals3952539.250.004148181.7599.9

CountyHUNT ETC
HighwayIH 30 ETC
FromROCKWALL COUNTY LINE (N FR)
ToMONTY STRATTON (N FRONTAGE RD)
CSJ0009-13-176
Proj IDNH 2021(155)
Work TypeSEAL COAT
 
223.57910775428.366688666.3562.3
Work Order03-19-21
Work Began04-21-21
Work Completed
Time Computed04-08-21
Contract Working Days106
Addl Days Granted0
Working Days Charged128
Percent Time Used120
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-176
BARRICADES PLUS, LLC (1.73)
INNOVATIVE ROADWAY SOLUTIONS, LLC (7.45)
STRIPING TECHNOLOGY, L.P. (21.06)
BRYDL CONTRACTING, INC. (0.00)
L. S. EQUIPMENT CO., INC. (0.00)
Contract #12203005
Totals10775428.360.006688666.3562.3

CountyHUNT
HighwayIH 30
FromAT SABINE RIVER
To.
CSJ0009-13-183
Proj IDBR 2022(422)
Work TypeBRIDGE MAINTENANCE
 
0.189483971.250.000.0
CountyHUNT
HighwayIH 30
FromAT SABINE RIVER
To.
CSJ0009-13-184
Proj IDBR 2022(422)
Work TypeBRIDGE MAINTENANCE
 
0.189260981.250.000.0
CountyGRAYSON
HighwaySH 56
FromAT POST OAK CREEK
To.
CSJ0045-03-055
Proj IDBR 2022(395)
Work TypeBRIDGE MAINTENANCE
 
0.012668310.000.000.0
CountyLAMAR
HighwayFM 38
FromAT ROWDY CREEK
To.
CSJ0749-02-023
Proj IDBR 2022(396)
Work TypeBRIDGE MAINTENANCE
 
0.033580942.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-12-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days335
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-183
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223222
Totals1994205.000.000.000.0

CountyHOPKINS
HighwayIH 30
FromSL 301
ToCANEY CREEK
CSJ0010-02-096
Proj IDNH 2021(158)
Work TypeOVERLAY
 
7.4905239464.322665747.2650.8
CountyHOPKINS
HighwayIH 30
FromCANEY CREEK BRIDGE
ToFANKLIN COUNTY LINE
CSJ0610-01-044
Proj IDNH 2021(158)
Work TypeOVERLAY
 
7.9035210463.111874516.6235.9
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE
ToTITUS COUNTY LINE
CSJ0610-02-058
Proj IDNH 2021(158)
Work TypeOVERLAY
 
10.672448130.71600560.7999.9
Work Order01-14-21
Work Began06-02-21
Work Completed
Time Computed03-15-21
Contract Working Days118
Addl Days Granted0
Working Days Charged73
Percent Time Used61
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-02-096
BARRICADES UNLIMITED (0.12)
TEXOP CONSTRUCTION (10.61)
STRIPING TECHNOLOGY, L.P. (2.23)
WINDING ROAD CONSTRUCTION, INC. (1.90)
WEST TEXAS ROCK RESOURCES, LLC (0.20)
Contract #12203207
Totals10898058.143019630.435140824.6747.1

CountyLAMAR ETC
HighwayUS 82 ETC
FromUS 271
ToFM 1508
CSJ0045-09-104
Proj IDSTP 2020(829)HES
Work TypeTRAFFIC CONTROL DEVICES
 
10.877951964.03600875.5863.1
Work Order07-20-20
Work Began11-17-20
Work Completed
Time Computed10-19-20
Contract Working Days270
Addl Days Granted0
Working Days Charged248
Percent Time Used91
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-09-104
FC TRAFFIC CONTROL, INC. (1.58)
CANNON ASPHALT GROUP LLC (47.89)
J. TUCKER CONSTRUCTION, INC. (0.61)
Contract #05203026
Totals951964.03352627.80600875.5863.1

CountyRED RIVER ETC
HighwayUS 82 ETC
From0.903 MI W OF SH 37
ToSH 37
CSJ0045-12-087
Proj IDSTP 2B20(147)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.3192627582.902340729.2689.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began10-21-20
Work Completed
Time Computed00-00-00
Contract Working Days218
Addl Days Granted0
Working Days Charged223
Percent Time Used102
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-12-087
FLEX SUPPLY, LLC (0.63)
A. E. MOORE CONSTRUCTION, INC. (3.89)
DUSTIN ALLEN, INC. (0.00)
AREA WIDE PROTECTIVE, INC. (0.06)
Contract #08203235
Totals2627582.900.002340729.2689.2

CountyFANNIN
HighwayUS 82
From0.5 MILES WEST OF SH 121
ToSH 78 (0.478 MI EAST OF SH 78)
CSJ0045-20-018
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.03112156062.2412255415.1199.9
CountyFANNIN
HighwayUS 82
From0.478 MI E OF SH 78
ToFM 100
CSJ0045-21-011
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
14.48749116732.2350957759.2899.9
CountyFANNIN
HighwayUS 82
FromFM 100
To0.5 MILES EAST OF SH 56
CSJ0045-21-012
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.63610365091.2611218807.1499.9
Work Order08-24-18
Work Began10-18-18
Work Completed
Time Computed09-24-18
Contract Working Days928
Addl Days Granted0
Working Days Charged927
Percent Time Used99
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-018
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.13)
W.O.E. CONSTRUCTION (0.70)
STRIPING TECHNOLOGY, L.P. (0.83)
LYON BARRICADE AND CONSTRUCTION CO. (0.20)
HAMMETT EXCAVATION, INC. (23.92)
TEXAS SHAFTS, INC. (0.93)
BOWMAN ENGINEERING & CONSULTING, INC. (0.16)
MCL CONTRACTING, LLC (0.06)
RAMBO CONTRACTING, INC. (3.95)
CDM HOLDINGS, LLC (3.64)
GANT CONTRACTORS, INC. (0.11)
SOUTHERN CROSS CONTRACTORS, LLC (0.61)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.50)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.05)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.38)
ALTUS TRAFFIC MANAGEMENT LLC (0.04)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
TEXOP CONSTRUCTION (0.03)
WOOD WATERING SERVICE LLC (0.00)
WITHERS CONSTRUCTION, LLC (0.37)
O. TREVINO CONSTRUCTION, LLC (0.12)
AIMS COMPANIES (0.18)
Contract #07183002
Totals71637885.738369.0474431981.5399.9

CountyRED RIVER
HighwayUS 82
FromBU 82 J
ToBOWIE COUNTY LINE
CSJ0046-01-064
Proj IDNH 2019(724)
Work TypeWIDEN NON-FREEWAY
 
16.88513814948.6115103591.1299.9
CountyRED RIVER
HighwayUS 82
FromFM 1159
ToBU 82 J
CSJ0046-10-001
Proj IDNH 2019(724)
Work TypeWIDEN NON-FREEWAY
 
0.855387212.95299326.7077.3
Work Order05-09-19
Work Began08-26-19
Work Completed
Time Computed07-08-19
Contract Working Days367
Addl Days Granted20
Working Days Charged353
Percent Time Used91
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-064
J. H. ODEN CONTRACTING COMPANY (0.83)
WITHERS CONSTRUCTION, LLC (1.85)
JM YANEZ CONSTRUCTION, INC. (5.41)
DUSTIN ALLEN, INC. (1.92)
FARR FOUNDATION, INC. (0.76)
D. L. LENNON INCORPORATED - CONTRACTOR (10.73)
TEX OP CONSTRUCTION, LP (2.35)
LYON BARRICADE & CONSTRUCTION CO. (0.34)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.31)
SOUTHERN CROSS CONTRACTORS, LLC (0.16)
STRIPING TECHNOLOGY, L.P. (1.34)
INDUSTRIAL FABRICS, INC. (1.30)
TOTAL HIGHWAY MAINTENANCE, LLC (0.03)
Contract #04193007
Totals14202161.5618429.1415402917.8299.9

CountyGRAYSON
HighwayUS 75
FromSH 91
To0.651 MI S OF CENTER STREET
CSJ0047-02-150
Proj IDNH 2020(008)
Work TypeWIDEN FREEWAY
 
4.763154683155.29101059991.9365.3
Work Order10-10-19
Work Began01-13-20
Work Completed
Time Computed11-11-19
Contract Working Days827
Addl Days Granted290
Working Days Charged689
Percent Time Used61
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0047-02-150
TOTAL HIGHWAY MAINTENANCE, LLC (1.02)
J. H. ODEN CONTRACTING COMPANY (0.14)
MICA CORPORATION (4.27)
A BROTHERS MILLING, LLC (0.29)
DURABLE SPECIALTIES, INC. (1.89)
PREMIER PAVING, LTD. (9.00)
ANCORTEX, INC. (2.99)
W.O.E. CONSTRUCTION, INC. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
ANTIGO CONSTRUCTION, INC. (0.00)
ROYAL REBAR (0.00)
SCOTT DERR PAINTING CO, LLC (0.06)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.79)
FORTSON CONTRACTING, INC. (0.31)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
ACT SAW CUTTING & REMOVAL (0.13)
H TORRES TRUCKING, L.L.C. (0.71)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.08)
Contract #09193201
Totals154683155.292553312.28101059991.9365.3

CountyGRAYSON
HighwaySH 5
FromNEWPORT DR AT PARTIN ELEMENTARY SCHOOL
To0.645 MI S OF FM 3133 AT MOORE PARK
CSJ0047-03-096
Proj IDSTP 2021(597)TAPS
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
0.427662920.28172388.9826.0
Work Order02-15-22
Work Began04-20-22
Work Completed
Time Computed05-23-22
Contract Working Days93
Addl Days Granted0
Working Days Charged35
Percent Time Used37
Contractor(s)
THE FAIN GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-096
FORTSON CONTRACTING, INC. (2.60)
BUYERS BARRICADES, INC. (4.71)
MASSEY CONTRACTORS, LLC (1.71)
G J SEEDING, LLC (4.90)
SPORTSCAPES CONSTRUCTION, L.L.C. (9.32)
Contract #12213021
Totals662920.2886008.90172388.9826.0

CountyGRAYSON
HighwayBU 377B
FromUS 377 N
ToUS 377 S
CSJ0081-08-011
Proj IDF 2022(530)
Work TypeOVERLAY
 
4.7991709161.870.000.0
CountyGRAYSON
HighwayFM 84
FromEND OF MAINTENANCE
ToUS 75
CSJ0316-02-026
Proj IDF 2022(530)
Work TypeOVERLAY
 
5.694913381.350.000.0
CountyFANNIN
HighwaySH 11
FromSH 121
ToSH 121 D SOUTH
CSJ2139-02-012
Proj IDF 2022(530)
Work TypeOVERLAY
 
0.30333302.250.000.0
CountyFANNIN
HighwaySH 11
FromSH 121 D SOUTH
ToSH 78 (BAILEY)
CSJ2139-03-022
Proj IDF 2022(530)
Work TypeOVERLAY
 
6.7331537377.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-16-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0081-08-011
FLEX SUPPLY, LLC (0.35)
TOTAL HIGHWAY MAINTENANCE, LLC (4.94)
J. H. ODEN CONTRACTING COMPANY (0.51)
JM YANEZ CONSTRUCTION, INC. (0.99)
SOUTHERN CROSS CONTRACTORS, LLC (1.22)
TEXOP CONSTRUCTION (0.34)
Contract #05223218
Totals4193223.200.000.000.0

CountyGRAYSON
HighwayUS 377
FromFM 901 E
ToUS 82
CSJ0081-10-048
Proj IDSTP 2B20(148)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.1901740801.091618188.2592.9
Work Order09-16-20
Work Began11-03-20
Work Completed
Time Computed10-16-20
Contract Working Days159
Addl Days Granted0
Working Days Charged156
Percent Time Used98
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-10-048
TOTAL HIGHWAY MAINTENANCE, LLC (0.70)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.15)
STRIPING TECHNOLOGY, L.P. (1.56)
DUSTIN ALLEN, INC. (13.85)
AREA WIDE PROTECTIVE, INC. (0.09)
Contract #08203036
Totals1740801.0912181.001618188.2592.9

CountyHOPKINS
HighwaySH 154
FromRADIO RD
ToSH11
CSJ0083-03-056
Proj IDSTP 2021(409)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.181270345.75266420.9699.9
CountyRAINS
HighwaySH 19
FromAT FM 2324
To.
CSJ0108-11-021
Proj IDSTP 2021(409)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20037317.1437126.0799.4
CountyRAINS
HighwayUS 69
FromSH 276
ToFM 2795
CSJ0203-03-049
Proj IDSTP 2021(409)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.523102472.9783844.3881.8
Work Order04-16-21
Work Began01-31-22
Work Completed
Time Computed07-15-21
Contract Working Days43
Addl Days Granted0
Working Days Charged60
Percent Time Used139
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0083-03-056
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.71)
WG ENGINEERING & CONSTRUCTION, LLC (9.91)
Contract #03213222
Totals410135.8660213.45387391.4196.8

CountyGRAYSON
HighwayFS 121
FromFM 121
ToCOUNTY LINE ROAD
CSJ0091-10-002
Proj IDF 2021(862)
Work TypeNEW LOCATION NON-FREEWAY
 
4.4769300300.064406015.2647.3
Work Order10-20-21
Work Began11-29-21
Work Completed
Time Computed11-18-21
Contract Working Days328
Addl Days Granted0
Working Days Charged109
Percent Time Used33
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0091-10-002
BARRICADES UNLIMITED (0.10)
PEACHTREE CONSTRUCTION, LTD. (3.26)
TRP CONSTRUCTION GROUP, LLC (0.78)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
FORTSON CONTRACTING, INC. (0.62)
SOUTHERN CROSS CONTRACTORS, LLC (0.51)
RAMBO CONTRACTING, INC. (4.55)
J. H. ODEN CONTRACTING COMPANY (1.76)
Contract #09213220
Totals9300300.06775396.264406015.2647.3

CountyHUNT ETC
HighwayUS 380 ETC
FromAT WEST CADDO CREEK
To.
CSJ0135-06-034
Proj IDBR 2022(548)
Work TypeBRIDGE MAINTENANCE
 
0.270577594.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0135-06-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06223434
Totals577594.760.000.000.0

CountyHUNT
HighwaySH 224
FromAT SOUTH SULPHUR RIVER
To.
CSJ0136-01-066
Proj IDBR 2022(388)
Work TypeBRIDGE REPLACEMENT
 
0.2142620776.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-29-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0136-01-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03223008
Totals2620776.260.000.000.0

page 1 | page 2 | page 3