Monthly State Let Construction Report For Paris District As Of Mar 13, 2024 Page 2 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUNT
HighwaySH 224
FromAT SOUTH SULPHUR RIVER
To.
CSJ0136-01-066
Proj IDBR 2022(388)
Work TypeBRIDGE REPLACEMENT
 
0.2142620776.262502714.8295.4
Work Order04-29-22
Work Began07-28-22
Work Completed
Time Computed07-28-22
Contract Working Days129
Addl Days Granted0
Working Days Charged122
Percent Time Used94
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0136-01-066
TEX OP CONSTRUCTION, LP (0.19)
STRIPING TECHNOLOGY, L.P. (0.38)
SOUTHEAST GRINDING AND GROOVING LLC (0.17)
HERMANOS STEEL, LLC (0.19)
FLEX SUPPLY, LLC (0.46)
DUSTIN ALLEN, INC. (1.26)
CAP RIVER LLC (0.13)
PEACHTREE CONSTRUCTION, LTD. (2.80)
Contract #03223008
Totals2620776.260.002502714.8295.4

CountyDELTA
HighwaySH 24
FromFM 64
To.081 MILES EAST OF BS 24-D
CSJ0136-03-066
Proj IDC 136-3-66
Work TypeOVERLAY
 
1.0901104463.271184055.3899.9
CountyDELTA
HighwaySH 24
FromBS 24 D
ToSH 19
CSJ0136-04-045
Proj IDC 136-4-45
Work TypeOVERLAY
 
6.6204699413.864737543.1699.9
CountyDELTA
HighwaySH 19
FromSH 24
To1540 FT. EAST OF FM 198
CSJ0136-04-046
Proj IDC 136-4-46
Work TypeOVERLAY
 
0.990855377.221100599.4399.9
Work Order05-10-23
Work Began07-06-23
Work Completed
Time Computed06-09-23
Contract Working Days69
Addl Days Granted0
Working Days Charged89
Percent Time Used128
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0136-03-066
A. E. MOORE CONSTRUCTION, INC. (0.88)
TEXOP CONSTRUCTION (0.75)
SOUTHERN CROSS CONTRACTORS, LLC (1.01)
HIGHWAY 19 CONSTRUCTION LLC (4.93)
STRIPING TECHNOLOGY, L.P. (2.94)
BARRICADES UNLIMITED (0.23)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.37)
Contract #04233211
Totals6659254.35272200.597022197.9799.9

CountyDELTA
HighwaySH 19
FromDELTA COUNTY LINE
ToSH 24
CSJ0136-04-048
Proj IDSTP 2024(417)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1182628.000.000.0
CountyDELTA
HighwaySH 24
FromSH 19
ToFM 2716
CSJ0136-04-049
Proj IDSTP 2024(417)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
87295.000.000.0
CountyLAMAR
HighwaySH 19
FromN OF CR 22860 (END OF CONTROL SECTION)
ToDELTA CL (END OF CONTROL SECTION)
CSJ0136-05-048
Proj IDSTP 2024(417)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2155275.000.000.0
CountyLAMAR
HighwaySH 19
FromSL 286
ToN OF CR 22860 (END OF CONTROL SECTION)
CSJ0136-06-055
Proj IDSTP 2024(417)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1022755.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days196
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0136-04-048
DIAMOND ELITE BARRICADES, LLC (0.66)
Contract #12233022
Totals4447953.000.000.000.0

CountyLAMAR
HighwayBU 271B
FromCLEMENT RD
ToW SANTA FE
CSJ0136-06-056
Proj IDF 2022(801)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.602356871.00294231.0082.4
CountyLAMAR
HighwayUS 271
From0.25 MI NORTH OF STONE AVE
ToBU 271 B
CSJ0136-07-052
Proj IDF 2022(801)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.671695961.00470150.7267.5
CountyLAMAR
HighwayBU 271B
FromUS 271
ToCLEMENT RD
CSJ0136-07-053
Proj IDF 2022(801)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.490381210.00256023.5367.1
Work Order09-15-22
Work Began11-15-22
Work Completed
Time Computed10-17-22
Contract Working Days121
Addl Days Granted0
Working Days Charged121
Percent Time Used100
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0136-06-056
FLEX SUPPLY, LLC (0.96)
J. H. ODEN CONTRACTING COMPANY (3.67)
ROBIN STEEL LLC (3.17)
SOUTHERN CROSS CONTRACTORS, LLC (0.94)
STRIPING TECHNOLOGY, L.P. (0.42)
Contract #08223038
Totals1434042.000.001020405.2571.1

CountyLAMAR
HighwayUS 271
FromUS 82
ToFM 1499
CSJ0136-07-051
Proj IDC 136-7-51
Work TypeOVERLAY
 
3.6374709224.964504944.3395.6
CountyLAMAR
HighwayUS 271
From0.365 MI SOUTH OF STATE LINE
ToFM 1499
CSJ0136-08-043
Proj IDC 136-8-43
Work TypeOVERLAY
 
9.4488404748.716298586.5774.9
CountyLAMAR
HighwayUS 271
FromSTATE LINE
To0.365 MI SOUTH OF STATE LINE
CSJ0136-09-023
Proj IDC 136-9-23
Work TypeOVERLAY
 
0.365353903.93264931.5974.8
Work Order05-11-23
Work Began09-14-23
Work Completed
Time Computed07-01-23
Contract Working Days144
Addl Days Granted54
Working Days Charged109
Percent Time Used55
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0136-07-051
BAHENA CONSTRUCTION CO.,INC. (4.14)
BARRICADES UNLIMITED (0.20)
J. H. ODEN CONTRACTING COMPANY (0.31)
SCR CIVIL CONSTRUCTION, LLC (1.56)
STRIPING TECHNOLOGY, L.P. (2.75)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
TEX OP CONSTRUCTION, LP (0.93)
WITHERS CONSTRUCTION, LLC (0.30)
Contract #04233006
Totals13467877.603660460.9211068462.4982.1

CountyHUNT
HighwaySH 34
From3 MI. N OF FM 2101
ToFM 2101
CSJ0173-06-057
Proj IDF 2024(637)
Work TypeOVERLAY
 
3.0941698317.400.000.0
CountyHUNT
HighwaySH 34
FromFM 1570
To3 MI N OF FM 2101
CSJ0173-07-063
Proj IDF 2024(637)
Work TypeOVERLAY
 
5.7244116717.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-06-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243026
Totals5815035.100.000.000.0

CountyFANNIN
HighwayFM 100
FromUS 82
ToFM 2216
CSJ0174-04-040
Proj IDF 2023(409)
Work TypeREHABILITATION OF EXISTING ROAD
 
8489062.604217621.9049.6
CountyFANNIN
HighwaySH 34
FromSH 56
ToUS 82
CSJ0174-04-043
Proj IDF 2023(409)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.998760949.29157746.5320.7
Work Order03-08-23
Work Began04-17-23
Work Completed
Time Computed06-06-23
Contract Working Days397
Addl Days Granted0
Working Days Charged167
Percent Time Used42
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0174-04-040
BAHENA CONSTRUCTION CO.,INC. (8.36)
CATOCON, INC. (1.51)
CHEROKEE SERVICES (0.23)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (9.32)
SOUTHERN CROSS CONTRACTORS, LLC (2.61)
TEX OP CONSTRUCTION, LP (0.18)
TRAFFIC HIGHWAY MAINTENANCE, LLC (2.47)
Contract #02233015
Totals9250011.89253449.234375368.4347.3

CountyFRANKLIN
HighwaySH 37
From1100 FT. S OF CR 1010
ToSULPHUR RIVER
CSJ0189-05-051
Proj IDC 189-5-51
Work TypeOVERLAY
 
12.85111773841.020.000.0
CountyFRANKLIN
HighwaySH 37
From330 FT S OF IH 30 EAST BOUND FRONTAGE
ToFM 21
CSJ0190-01-039
Proj IDC 190-1-39
Work TypeOVERLAY
 
0.8891188634.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0189-05-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243206
Totals12962475.510.000.000.0

CountyHUNT
HighwayUS 69
FromFM 513 S
ToRAINS COUNTY LINE
CSJ0203-02-052
Proj IDC 203-2-52
Work TypeOVERLAY
 
1.5101649525.100.000.0
CountyRAINS
HighwayUS 69
FromHUNT COUNTY LINE
ToCR 4530
CSJ0203-03-051
Proj IDC 203-3-51
Work TypeOVERLAY
 
3.5602759297.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0203-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243021
Totals4408822.650.000.000.0

CountyLAMAR
HighwayUS 271
FromFM 196 NORTH
ToRED RIVER COUNTY LINE
CSJ0221-01-084
Proj IDF 2024(065)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1364824.00125000.009.1
CountyRED RIVER
HighwayUS 271
FromLAMAR COUNTY LINE
ToSH 37
CSJ0221-02-031
Proj IDF 2024(065)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
856455.000.000.0
Work Order10-23-23
Work Began01-02-24
Work Completed
Time Computed11-22-23
Contract Working Days92
Addl Days Granted0
Working Days Charged11
Percent Time Used11
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0221-01-084
J. H. ODEN CONTRACTING COMPANY (4.20)
BARRICADES UNLIMITED (0.58)
Contract #09233034
Totals2221279.00112500.00125000.005.6

CountyFANNIN
HighwaySH 78
FromUS 82
ToOKLAHOMA STATE LINE
CSJ0279-02-048
Proj IDSTP 2B23(050)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.2802680197.50778015.8129.0
Work Order09-07-23
Work Began10-09-23
Work Completed
Time Computed10-09-23
Contract Working Days240
Addl Days Granted0
Working Days Charged58
Percent Time Used24
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0279-02-048
SOUTHERN CROSS CONTRACTORS, LLC (8.48)
FLEX SUPPLY, LLC (1.06)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.91)
A. E. MOORE CONSTRUCTION, INC. (2.17)
Contract #08233250
Totals2680197.5050.00778015.8129.0

CountyGRAYSON
HighwayFM 1753
FromFM 1897
ToFM 120
CSJ0316-03-010
Proj IDF 2021(793)
Work TypeREHABILITATION OF EXISTING ROAD
 
9.1536464805.446764104.7099.9
Work Order09-16-21
Work Began01-03-22
Work Completed
Time Computed12-15-21
Contract Working Days151
Addl Days Granted0
Working Days Charged151
Percent Time Used100
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0316-03-010
TEXAS TRAFFIC AND BARRICADE, LLC (0.28)
BAHENA CONSTRUCTION CO.,INC. (4.91)
SOUTHERN CROSS CONTRACTORS, LLC (1.52)
TOTAL HIGHWAY MAINTENANCE, LLC (1.57)
A. E. MOORE CONSTRUCTION, INC. (1.71)
DUSTIN ALLEN, INC. (1.15)
PINNACLE GRINDING AND GROOVING LLC (0.18)
COLD CREEK CONSTRUCTION, LTD (1.22)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.16)
MOBILE ENTERPRISES, INC. (0.42)
D. L. LENNON INCORPORATED - CONTRACTOR (2.26)
Contract #08213025
Totals6464805.4414000.006764104.7099.9

CountyDELTA
HighwayFM 64
FromFM 128
ToFM 1532
CSJ0399-03-038
Proj IDC 399-3-38
Work TypeREHABILITATION OF EXISTING ROAD
 
4061048.664606559.4199.9
Work Order08-25-21
Work Began12-20-21
Work Completed
Time Computed11-23-21
Contract Working Days224
Addl Days Granted0
Working Days Charged256
Percent Time Used114
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0399-03-038
DUSTROL, INC. (1.03)
J. H. ODEN CONTRACTING COMPANY (1.77)
PANOLA SIGN & BARRICADE, INC. (0.61)
SOUTHERN CROSS CONTRACTORS, LLC (2.12)
STRIPING TECHNOLOGY, L.P. (2.01)
TEXANA LAND & ASPHALT, INC. (0.82)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.95)
MOJICA CONSTRUCTION LLC (16.52)
CATOCON, INC. (2.76)
BAHENA CONSTRUCTION CO.,INC. (4.47)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.16)
Contract #07213221
Totals4061048.660.004606559.4199.9

CountyHOPKINS
HighwaySL 301
FromSL 301 (PIPELINE RD)
ToAT TOWN BRANCH
CSJ0400-03-015
Proj IDBR 2022(802)
Work TypeBRIDGE REPLACEMENT
 
0.107484955.23454716.3493.7
CountyHOPKINS
HighwayCR
FromCR 4767
ToAT NORTH CANEY CREEK TRIBUTARY
CSJ0901-28-092
Proj IDBR 2022(132)
Work TypeBRIDGE REPLACEMENT
 
0.074293403.220.000.0
CountyHOPKINS
HighwayCR
FromCR 3545
ToAT MITCHELL CREEK TRIBUTARY
CSJ0901-28-095
Proj IDBR 2022(169)
Work TypeBRIDGE REPLACEMENT
 
0.030115211.75112632.1597.7
CountyHOPKINS
HighwayCR
FromCR 1180
ToAT BIRCH CREEK
CSJ0901-28-104
Proj IDBR 2021(925)
Work TypeBRIDGE REPLACEMENT
 
0.069453968.60441576.7797.2
Work Order09-20-22
Work Began11-01-22
Work Completed
Time Computed10-20-22
Contract Working Days250
Addl Days Granted0
Working Days Charged147
Percent Time Used58
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0400-03-015
FLEX SUPPLY, LLC (1.85)
SOUTHERN CROSS CONTRACTORS, LLC (7.62)
HERMANOS STEEL, LLC (0.37)
A. E. MOORE CONSTRUCTION, INC. (0.24)
Contract #08223039
Totals1347538.8034424.801008925.2674.8

CountyGRAYSON
HighwaySH 160 ETC
FromSH 11/US 69 INTER
To600 FT SOUTH OF SH 11/US 69 INTER
CSJ0410-02-038
Proj IDF 2022(948)
Work TypeOVERLAY
 
15.9807831624.158684493.4799.9
Work Order04-05-23
Work Began04-17-23
Work Completed
Time Computed07-04-23
Contract Working Days147
Addl Days Granted0
Working Days Charged147
Percent Time Used100
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0410-02-038
BARRICADES UNLIMITED (0.31)
MOBILE ENTERPRISES, INC. (0.14)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.36)
TEX OP CONSTRUCTION, LP (10.76)
TRP CONSTRUCTION GROUP, LLC (2.06)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.44)
WITHERS CONSTRUCTION, LLC (1.18)
JM YANEZ CONSTRUCTION, INC. (3.70)
AWP SAFETY (0.16)
DUSTIN ALLEN, INC. (2.55)
Contract #12223231
Totals7831624.158602.258684493.4799.9

CountyLAMAR
HighwayFM 38
FromFM 38
ToAT WEST FORK SANDERS CREEK
CSJ0435-01-083
Proj IDBR 2024(784)
Work TypeBRIDGE REPLACEMENT
 
0.2312032325.370.000.0
CountyLAMAR
HighwayCR
FromCR 16300
ToAT LITTLE SANDY CREEK
CSJ0901-29-093
Proj IDBR 2023(661)
Work TypeBRIDGE REPLACEMENT
 
0.081607229.970.000.0
CountyDELTA
HighwayCR
FromAT LAKE CREEK
To.
CSJ0901-31-137
Proj IDBR 2024(785)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.01126800.000.000.0
CountyLAMAR
HighwayFM 1184
FromFM 1184
ToAT ROBERTSON CREEK
CSJ1319-01-018
Proj IDBR 2024(784)
Work TypeBRIDGE REPLACEMENT
 
0.1651066243.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days238
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243216
Totals3732598.350.000.000.0

CountyHUNT
HighwayFM 512
FromSH 34
ToFM 118
CSJ0579-02-014
Proj IDF 2B23(052)
Work TypeREHABILITATION OF EXISTING ROAD
 
9.62210425420.9763777.600.6
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed12-06-23
Contract Working Days432
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0579-02-014
BAHENA CONSTRUCTION CO.,INC. (10.09)
CATOCON, INC. (4.61)
J. H. ODEN CONTRACTING COMPANY (1.06)
MOJICA CONSTRUCTION LLC (2.12)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.09)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.39)
STRIPING TECHNOLOGY, L.P. (3.03)
TEXANA LAND & ASPHALT, INC. (2.32)
TEXAS TRAFFIC AND BARRICADE, LLC (0.45)
TEXOP CONSTRUCTION (0.12)
Contract #08233016
Totals10425420.970.0063777.600.6

CountyFRANKLIN
HighwayIH 30
From3.46 MILES WEST OF SH 37
To2.31 MILES WEST OF SH 37
CSJ0610-02-064
Proj IDSTP 2022(803)TP
Work TypeTRANSPORTATION NON-ROADWAY
 
1.1508869678.565569637.8162.7
Work Order03-13-23
Work Began05-04-23
Work Completed
Time Computed04-12-23
Contract Working Days254
Addl Days Granted0
Working Days Charged128
Percent Time Used50
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0610-02-064
CAP RIVER LLC (0.48)
ISAACS CONSTRUCTION SERVICES LLC (0.10)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.15)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.45)
STRAIGHT LINE SAWING & SEALING, INC. (0.61)
STRIPING TECHNOLOGY, L.P. (5.82)
TORO BRAVO CONSTRUCTION, LLC (0.93)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.16)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
WITHERS CONSTRUCTION, LLC (0.96)
Contract #02233009
Totals8869678.56231726.605569637.8162.7

CountyFANNIN
HighwayFM 68
FromSH 78
ToFM 271
CSJ0620-01-018
Proj IDSTP 2024(080)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.2606203272.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days247
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0620-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233211
Totals6203272.060.000.000.0

CountyHOPKINS
HighwayFM 900
FromIH 30 SOUTH FRONTAGE ROAD
To0.28 MILE N OF FM 3019
CSJ0680-05-014
Proj IDSTP 2B23(053)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.5703356595.052132836.4263.5
Work Order09-06-23
Work Began10-05-23
Work Completed
Time Computed10-06-23
Contract Working Days223
Addl Days Granted0
Working Days Charged54
Percent Time Used24
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-05-014
BAHENA CONSTRUCTION CO.,INC. (15.15)
CATOCON, INC. (5.95)
DUSTIN ALLEN, INC. (0.88)
MURRAY CONSTRUCTION (1.94)
PANOLA SIGN & BARRICADE, INC. (0.75)
STRIPING TECHNOLOGY, L.P. (5.12)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.48)
Contract #08233032
Totals3356595.0513400.002132836.4263.5

page 1 | page 2 | page 3 | page 4