Monthly State Let Construction Report For San Antonio District As Of Jun 08, 2018 Page 3 Of 7

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayUS 281
FromIH 35
ToIH 410
CSJ0073-08-181
Proj IDNH 2016(872)
Work TypeMILL, SC, PFC OV & PAVMENT MARKINGS
 
6.1998673181.4210326437.3099.9
Work Order04-19-16
Work Began07-05-16
Work Completed
Time Computed05-19-16
Contract Working Days333
Addl Days Granted20
Working Days Charged313
Percent Time Used88
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-181
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
PRIMATE CONSTRUCTION, INC. (12.09)
RPV CONSTRUCTION (5.74)
CRG (16.72)
FLASHER EQUIPMENT COMPANY (4.27)
GREEN MILLING GROUP (3.80)
Contract #02163205
Totals8673181.4214364.7010326437.3099.9

CountyBEXAR
HighwayUS 281
From0.6 MI S OF NAKOMA
ToIH 410
CSJ0073-08-184
Proj IDNH 2017(561)
Work TypeSURFACE & PAVEMENT MARKINGS
 
1.7491512876.021828716.1299.9
CountyBEXAR
HighwayUS 281
FromBROOKHOLLOW
To0.6 MI S OF NAKOMA
CSJ0253-04-152
Proj IDNH 2017(561)
Work TypeSURFACE & PAVEMENT MARKINGS
 
2.6431735744.961561573.1389.9
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed03-06-17
Contract Working Days173
Addl Days Granted0
Working Days Charged169
Percent Time Used97
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-184
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (7.49)
D&S TEXAS ICON CONSTRUCTION (6.10)
E-Z BEL CONSTRUCTION, LLC (14.63)
FLASHER EQUIPMENT COMPANY (5.02)
RELMCO, INC. (1.45)
BMP SPECIALIST, LLC (1.08)
PERFORMANCE EQUIPMENT SERVICE (5.37)
HEARN CO. (2.01)
Contract #02173234
Totals3248620.98139046.083390289.2599.9

CountyBEXAR
HighwayIH 37
FromIH 10
ToIH 35
CSJ0073-08-186
Proj IDNH 2017(155)
Work TypeBSE, SC, SURF, PAV'T MRKNGS
 
3.1296072878.926362793.0799.9
CountyBEXAR
HighwayIH 37
FromFAIR AVENUE
ToIH 10
CSJ0073-08-187
Proj IDNH 2017(155)
Work TypeBSE, SC, SURF, PAV'T MRKNGS
 
0.9251972515.911669346.4584.6
Work Order12-20-16
Work Began03-20-17
Work Completed
Time Computed01-19-17
Contract Working Days132
Addl Days Granted42
Working Days Charged146
Percent Time Used83
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-186
FLASHER EQUIPMENT COMPANY (2.93)
ROADWAY SPECIALTIES, INC. (0.83)
RPV CONSTRUCTION (5.93)
PRIMATE CONSTRUCTION, INC. (9.20)
THE LEVY COMPANY, L.P. (0.82)
TEXAS CUTTING & CORING, INC. (0.46)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.50)
DRILL TECH DRILLING & SHORING, INC. (2.09)
Contract #10163006
Totals8045394.83322164.158032139.5299.8

CountyBEXAR
HighwayIH 37
From0.3 MILES S OF IH 410
To0.4 MILES N OF LP 13
CSJ0073-08-190
Proj IDNH 1702(030)
Work TypeLANDSCAPE DEVELOPMENT
 
2.500557600.00415085.0074.4
Work Order06-08-17
Work Began00-00-00
Work Completed
Time Computed07-08-17
Contract Working Days81
Addl Days Granted0
Working Days Charged81
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-190
FLASHER LIMITED (1.50)
Contract #05173029
Totals557600.003000.00415085.0074.4

CountyBEXAR
HighwayIH 37
FromAT E. CESAR CHAVEZ BLVD
To.
CSJ0073-08-193
Proj IDNH 1802(204)
Work TypeLANDSCAPE DEVELOPMENT
 
0.100107737.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0073-08-193
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183007
Totals107737.990.000.000.0

CountyWILSON
HighwayUS 181
From0.1 MI NORTH OF FM 541
ToKARNES/WILSON COUNTY LINE
CSJ0100-04-038
Proj IDNH 2016(748)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
5.9929084167.296939540.9476.3
Work Order03-31-16
Work Began01-09-17
Work Completed
Time Computed05-30-16
Contract Working Days289
Addl Days Granted73
Working Days Charged308
Percent Time Used85
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-04-038
COWBELL TRAFFIC SERVICES, INC. (0.24)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.52)
FLASHER EQUIPMENT COMPANY (2.68)
LONE STAR EROSION CONTROL (1.37)
STRIPE-A-ZONE, INC. (0.24)
RELMCO, INC. (0.62)
Contract #02163208
Totals9084167.29683392.036939540.9476.3

CountyKERR
HighwaySH 27
FromFM 1350
ToSPUR 100
CSJ0142-05-080
Proj IDSTP 2013(719)
Work TypeWIDEN RDWY PASS LANES & OP IMPROV
 
9.0368690979.58276460.003.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days261
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0142-05-080
ADCOCK 4 INVESTMENTS, LLC (4.87)
ROADWAY SPECIALTIES, INC. (3.69)
FLASHER LIMITED (1.84)
MURRAY CONSTRUCTION (0.78)
MV HENKE COMPANY, LLC (0.24)
AREA WIDE PROTECTIVE, INC. (0.22)
WEST TEXAS RUMBLE STRIP (0.08)
Contract #02183002
Totals8690979.58102690.00276460.003.1

CountyKENDALL
HighwayRM 473
From2.464 MI W OF US 281
To2.04 MI W OF US 281
CSJ0142-10-024
Proj IDSTP 2018(070)HESG
Work TypeCHEVRONS & PAVEMENT MARKINGS
 
0.42417307.32960.005.5
CountyGUADALUPE
HighwaySH 123
FromSH 46
To0.1 MI N OF FM 1681
CSJ0366-03-067
Proj IDSTP 2018(071)HESG
Work TypePAVEMENT MARKINGS
 
9.929146084.5140449.1027.6
CountyCOMAL
HighwayFM 3424
FromRM 32
ToFM 306
CSJ1728-01-007
Proj IDSTP 2018(072)HESG
Work TypePAVEMENT MARKINGS
 
1.35820665.821470.007.1
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed12-10-17
Contract Working Days59
Addl Days Granted0
Working Days Charged17
Percent Time Used28
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0142-10-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173015
Totals184057.6542879.1042879.1023.2

CountyKERR
HighwayIH 10
From1.3 MI FROM KERR/GILLESPIE C/L
To0.4 MI EAST OF SH 16
CSJ0142-14-061
Proj IDNH 2018(501)
Work TypeSURFACE & PAVEMENT MARKINGS
 
7.8794379478.030.000.0
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-16-18
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0142-14-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183221
Totals4379478.030.000.000.0

CountyWILSON
HighwayUS 87
From2.5 MI N OF FM 539
ToFM 539
CSJ0143-03-044
Proj IDNH 2018(530)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
2.5172913595.443418.000.1
Work Order03-15-18
Work Began00-00-00
Work Completed
Time Computed04-14-18
Contract Working Days103
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-03-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183206
Totals2913595.443418.003418.000.1

CountyCOMAL
HighwaySH 46
From0.2 MI W OF FM 3009
To0.2 MI E OF FM 3009
CSJ0215-01-043
Proj IDSTP 2018(074)HES
Work TypeGRAD, BASE, SURF & SAFETY TREAT
 
0.400431702.1280390.0018.6
CountyCOMAL
HighwaySH 46
FromAT FM 3009
To.
CSJ0215-01-046
Proj IDSTP 2018(075)HESG
Work TypeSIGNALS, SIGNS, ILLUMINATION
 
0.400141803.7024324.8017.1
CountyCOMAL
HighwaySH 46
From0.3 MI W OF PR 31
To0.1 MI W OF PR 31
CSJ0215-07-026
Proj IDSTP 2018(076)HESG
Work TypeGRAD, SURF, BASE & PAVEMENT MRKINGS
 
0.200108424.48105418.7597.2
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed12-15-17
Contract Working Days73
Addl Days Granted0
Working Days Charged29
Percent Time Used39
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0215-01-043
ROADWAY SPECIALTIES, INC. (8.53)
FLASHER LIMITED (4.70)
SAECO ELECTRIC & UTILITY, LTD. (18.24)
GEOSOURCE, INC. (1.40)
ALTUS TRAFFIC MANAGEMENT LLC (0.00)
Contract #10173020
Totals681930.3038616.80210133.5530.8

CountyCOMAL
HighwayBS 46-C
FromIN THE CITY OF NEW BRAUNFELS
To.
CSJ0215-02-056
Proj IDSTP 2014(112)TE
Work TypeGRAD, BSE,SURF, SIDEWALK, SIGN
 
0.661796382.00871982.0899.9
CountyCOMAL
HighwayBS 46-C
FromIN THE CITY OF NEW BRAUNFELS
To.
CSJ0215-02-058
Proj IDROW 215-2-58
Work TypeUTILITY ADJUSTMENTS
 
0.66155799.0010250.0018.3
Work Order12-28-16
Work Began02-01-17
Work Completed
Time Computed09-09-16
Contract Working Days129
Addl Days Granted25
Working Days Charged136
Percent Time Used88
Contractor(s)
MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-056
AUSTIN MATERIALS, LLC (16.80)
E-Z BEL CONSTRUCTION, LLC (9.12)
FLASHER EQUIPMENT COMPANY (4.35)
FUQUAY, INC. (0.86)
Contract #08163216
Totals852181.005000.00882232.0899.9

CountyKENDALL
HighwaySH 46
FromUS 87
ToKENDALL / COMAL COUNTY LINE
CSJ0215-06-037
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
3.9055575747.694788414.3685.8
CountyCOMAL
HighwaySH 46
FromCOMAL / KENDALL COUNTY LINE
ToUS 281
CSJ0215-07-022
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
2.0503394595.792246189.0466.1
Work Order10-06-16
Work Began11-07-16
Work Completed
Time Computed11-05-16
Contract Working Days413
Addl Days Granted0
Working Days Charged387
Percent Time Used93
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-037
MPB, INC. (13.64)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (11.20)
FLASHER EQUIPMENT COMPANY (3.20)
ROADWAY SPECIALTIES, INC. (2.33)
THE LEVY COMPANY, L.P. (0.55)
EGGEMEYER LAND CLEARING, LLC (0.57)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.02)
Contract #08163008
Totals8970343.48274916.987034603.4078.4

CountyCOMAL
HighwaySL 337
FromSH 46, SOUTHERLY
ToIH 35
CSJ0216-01-036
Proj IDSTP 1702(434)
Work TypeGR, STRS, BASE & SURF
 
2.99718902660.079950078.3852.6
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToHILLCREST DRIVE
CSJ0216-01-054
Proj IDSTP 1702(435)MM
Work TypeGR, BASE, SURF, PVMT MRK, SGNS, STR
 
1.43112457946.033613132.7829.0
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToSH 46
CSJ0216-01-055
Proj IDNH 1702(436)
Work TypeGR,BASE,STRS, SURF
 
2.23010947785.373102301.2728.3
Work Order09-27-17
Work Began10-23-17
Work Completed
Time Computed10-27-17
Contract Working Days1,239
Addl Days Granted0
Working Days Charged175
Percent Time Used14
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0216-01-036
HOSS LAND SERVICE (0.23)
LONE STAR EROSION CONTROL (2.44)
INTERSTATE BARRICADES & MARKINGS, INC. (0.30)
VOGES DRILLING CO. (2.77)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.75)
CHEROKEE SERVICES (0.36)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.20)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.98)
HILL COUNTRY BRIDGE, INC (2.46)
GK CONSTRUCTION, LLC (0.41)
HOUSTON SAWING & DRILLING (0.03)
OSCAR ORDUNO, INC. (1.65)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.41)
THE LEVY COMPANY, L.P. (4.91)
FLASHER EQUIPMENT COMPANY (1.01)
R K STEPHENS CONSTRUCTION, LLC (2.21)
ROADWAY SPECIALTIES, INC. (1.07)
SOUTH TEXAS PAINTING COMPANY (0.08)
PIPE WHOLESALERS OF TEXAS, INC. (1.19)
HARPER BROTHERS CONSTRUCTION LLC (0.16)
Contract #07173003
Totals42308391.471555412.5816665512.4339.3

CountyCOMAL
HighwayUS 281
FromSB MAINLANE @ GUADALUPE RIVER
To.
CSJ0253-03-067
Proj IDBR 1702(038)
Work TypeGRAD,BSE,STRUCTURE,SURF,CLN & PAINT
 
0.1723271173.601086973.3433.2
Work Order06-14-17
Work Began08-07-17
Work Completed
Time Computed07-14-17
Contract Working Days304
Addl Days Granted0
Working Days Charged66
Percent Time Used21
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-067
S&S BRIDGE PAINTING (39.67)
FLASHER EQUIPMENT COMPANY (0.94)
AUSTIN MATERIALS, LLC (4.28)
Contract #05173036
Totals3271173.60154625.001086973.3433.2

CountyCOMAL
HighwayUS 281
From0.9 MI N OF FM 311
To1.5 MI N OF FM 311
CSJ0253-03-072
Proj IDNH 2018(594)
Work TypeGRAD, STRUC, BASE & SURF
 
0.600726396.370.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-072
FLASHER LIMITED (3.17)
LONE STAR EROSION CONTROL (7.39)
ROADWAY SPECIALTIES, INC. (2.76)
Contract #04183242
Totals726396.370.000.000.0

CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-146
Proj IDNH 2017(592)
Work TypeGR, STRS, BASE, SIGN, DELIN & PAV
 
3.778179542332.7158346759.1232.4
CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-151
Proj IDSTP 1602(378)
Work TypeROW ACQUISITION
 
3.57712759009.888548930.9567.0
Work Order03-15-17
Work Began08-01-17
Work Completed
Time Computed04-14-17
Contract Working Days1,077
Addl Days Granted0
Working Days Charged227
Percent Time Used21
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-146
FLASHER EQUIPMENT COMPANY (0.58)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.60)
LONE STAR EROSION CONTROL (0.59)
ROYAL VISTA INC. (4.54)
W. W. FOUNDATION DRILLING, LTD. (1.75)
WEBBER BARRIER SERVICES, LLC. (1.70)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.99)
EARTH REINFORCEMENTS LLC (0.95)
LONE STAR PAVING (7.22)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.17)
HOUSTON SAWING & DRILLING (0.03)
THE LEVY COMPANY, L.P. (5.61)
(USE 26300)BRADCO, LLC (2.06)
GEOSOURCE, INC. (0.05)
GK CONSTRUCTION, LLC (0.09)
HOSS LAND SERVICES LLC (0.01)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.01)
CP REBAR AND PT INSTALLATION (0.87)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (1.25)
DU MOR ENTERPRISES (0.50)
TEXAS HIGHWAY WALLS (0.75)
INDUS ROAD & BRIDGE, INC (2.29)
FUQUAY, INC. (1.18)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.17)
DAKOTA UTILITY CONTRACTORS, INC. (0.15)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.11)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.10)
SUPERIOR PUMP SOLUTIONS LLC (0.02)
HOWELL CRANE & RIGGING, INC. (0.00)
DAKOTA UTILITY CONTRACTORS, INC. (0.06)
JSS BORI GROUP, LLC (0.20)
FUQUAY, INC. (0.00)
CALAME CONTRACTING, LLC (0.39)
CHOCTAW ERECTORS, INC. (0.49)
BRYANT & FREY CONSTRUCTION (0.03)
Contract #02173001
Totals192301342.595901508.3766895690.0734.7

CountyBANDERA
HighwaySH 16
FromKERR COUNTY LINE
ToFM 2107
CSJ0291-04-024
Proj IDSTP 2015(933)HES
Work TypeGR, BASE, SURF & PAVMT MARKINGS
 
5.6702553976.462383044.7794.6
CountyBANDERA
HighwaySH 16
FromKERR COUNTY LINE
To0.6 MI S OF MESA VERDE ROAD
CSJ0291-04-025
Proj IDSTP 2015(934)HES
Work TypeGRS, BSE, SURF, STR, MBGF
 
2.700530989.38482277.9990.8
CountyBANDERA
HighwaySH 16
From0.2 MI WEST OF WINANS CROSSING
To2.8 MI EAST OF FM 470
CSJ0291-05-046
Proj IDSTP 2015(935)HES
Work TypeSTR, MBFG, GR,BASE, SURF & PVMT_MRK
 
6.0301760096.081648363.6393.6
Work Order06-11-15
Work Began10-01-15
Work Completed
Time Computed09-10-15
Contract Working Days442
Addl Days Granted33
Working Days Charged444
Percent Time Used108
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-04-024
RELMCO, INC. (28.36)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (10.94)
FLASHER EQUIPMENT COMPANY (4.11)
FUQUAY, INC. (3.91)
M.V. HENKE ENTERPRISES, INC. (1.67)
GEOSOURCE, INC. (1.36)
MURRAY CONSTRUCTION (2.00)
VOGES DRILLING CO. (0.60)
Contract #04153203
Totals4845061.92825.004513686.3993.8

CountyWILSON
HighwaySH 97
FromUS 181
ToUS 87
CSJ0328-01-014
Proj IDSTP 1502(611)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
10.61317618829.4617440851.1198.9
Work Order11-04-15
Work Began06-13-16
Work Completed
Time Computed01-04-16
Contract Working Days455
Addl Days Granted0
Working Days Charged420
Percent Time Used92
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-01-014
INTERSTATE BARRICADES & MARKINGS, INC. (2.37)
MURRAY CONSTRUCTION (0.22)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.40)
ROADWAY SPECIALTIES, INC. (3.27)
CATO ELECTRIC COMPANY (0.14)
E-Z BEL CONSTRUCTION, LLC (0.54)
AUSTIN WOOD RECYCLING (0.67)
Contract #08153006
Totals17618829.46762349.2017440851.1198.9

CountyWILSON
HighwaySH 97
FromATASCOSA COUNTY LINE
ToLP 181
CSJ0328-02-043
Proj IDSTP 2017(476)
Work TypeGRADE, BASE, SURF, PAVMT MRK
 
12.72818593935.6917282318.3592.9
Work Order02-22-17
Work Began04-07-17
Work Completed
Time Computed03-24-17
Contract Working Days586
Addl Days Granted0
Working Days Charged292
Percent Time Used49
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0328-02-043
MV HENKE COMPANY, LLC (0.34)
RELMCO, INC. (5.70)
THE LEVY COMPANY, L.P. (0.89)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.02)
MPB, INC. (0.47)
GEOSOURCE, INC. (0.93)
FUQUAY, INC. (1.10)
FLASHER EQUIPMENT COMPANY (2.07)
Contract #01173201
Totals18593935.69213032.4417282318.3592.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7